MILTON I. SHADUR, Senior District Judge.
United States Surety Company ("Surety") brought this contractual action against Stevens Family Limited Partnership and four individual defendants (collectively the "Partnership"
Surety now asks for judgment on the pleadings under Fed.R.Civ.P. ("Rule") 12(c). As explained here, Surety's pleading-based motion is denied as to the first of those contentions but granted as to the second.
As with Rule 12(b)(6) motions, Rule 12(c) motions call for the factual allegations in a complaint to be viewed in the light most favorable to the nonmovant plaintiff, drawing all reasonable inferences in its favor (Emergency Servs. Billing Corp. v. Allstate Ins. Co., 668 F.3d 459, 464 (7th Cir.2012)). Hence for purposes of the current motion assertions in Surety's First Amended Complaint ("Complaint") will be considered untrue if Partnership has denied those assertions in its Answer. Moreover, Partnership's Rule 8(b)(5) disclaimer that it lacks sufficient knowledge or information to form a belief about any of Surety's assertions has the effect of a denial.
Partnership owns a construction company — Architectural Specialties Trading Company, Inc. ("Architectural Specialties") — that specializes in architectural millwork (Ans. ¶ 9). Two construction projects are relevant to this action, each of them including Architectural Specialties as a subcontractor (id. ¶¶ 14, 16). First, in May 2008 Architectural Specialties contracted to help build an armed forces retirement home — a project run by general contractor W.G. Yates & Sons Construction Co. ("Yates") (id. ¶ 14). Second of the projects was one to build the Dental Sciences Building for the University of North Carolina at Chapel Hill — an undertaking that began in June 2009 and was led by BE & K Building Group, LLC ("BE & K") (id. ¶ 16). Both projects required Architectural Specialties to provide its general contractors with payment and performance bonds (id. ¶¶ 15, 17). Partnership purchased those bonds (together the "Bonds") from Surety — Bond No. 10000825985 was issued to Yates in the penal sum of $1,368,000, and Bond No. 1000825982 was issued to BE & K in the penal sum of $1,251,234 (id.).
That provision is coupled with this collateral security provision (Agreement ¶ 6):
Surety alleges that it has received claims on both Bonds (Compl. ¶ 18-19). It asserts that it has incurred $7,931.42 of claim investigation costs in connection with the Retirement Home Project (id. 18). But Partnership responds that it does not have sufficient information to determine whether that is accurate (Ans. ¶ 18). As to the Dental Building Project, Partnership admits that BE & K sent Surety several letters discussing Architectural Specialties's alleged default as well as a claim on the Bond issued in connection with the Project (id. ¶ 19). Included in those letters was a June 2011 "Notice of Default" letter, a July 2011 "Failure to Cure Default" letter and an August 2011 letter demanding payment of $439,030 for costs incurred due to Architectural Specialties's alleged default (id.). Partnership admits that BE & K sent it those letters but maintains that it never defaulted (id.).
Surety avers that in response to BE & K's claim it first demanded collateral security in the amount of $100,000 (Compl. ¶ 25), and it later supplemented that demand with a request for an additional $400,000 (id. at ¶ 26). Although Partnership's Ans. ¶¶ 25-26 deny its having received those demands for collateral, its response to Surety's motion puts the lie to that denial, for its P. Mem. ¶¶ 4-7 state that it did offer up collateral in response to Surety's demands.
This action was brought based on Surety's belief that it was not properly indemnified and collateralized under the terms of the Agreement. On consideration of Surety's motion for judgment on the pleadings, this Court holds that Partnership's admission referred to in the preceding paragraph entitles Surety to a judgment as a matter of law on its demand for collateralization but that its motion for current enforcement of the Agreement's indemnification provisions must be and is denied.
Surety's contract action was brought pursuant to this Court's diversity jurisdiction, so that Illinois law — including its choice-of-law principles — applies (Assaf v. Trinity Med. Ctr., 696 F.3d 681, 685 (7th Cir.2012)). Application of California substantive law is called for by a clear choice-of-law provision in Agreement ¶ 12.24. Partnership pointed to that fact in response to Surety's citation to Illinois caselaw in its original memorandum (P. Mem. ¶ 9), and Surety replied by including California caselaw in its reply memorandum. Because Illinois' choice-of-law doctrine would honor the Agreement's provision, California law controls.
California regularly recognizes indemnity contracts in favor of sureties (First Nat'l Ins. Co. v. Hunt, No. Civ. 10-1449, 2011 WL 2173765, at *3 (E.D.Cal. June 2, 2011), citing Fid. & Deposit Co. of Md. v. Whitson, 187 Cal.App.2d 751, 756, 10 Cal.Rptr. 6 (1960)). And as with all contracts, California law seeks to give effect to the contracting parties' intentions (Myers Bldg. Indus., Ltd. v. Interface Tech., Inc., 13 Cal.App.4th 949, 968, 17 Cal.Rptr.2d 242 (1993)).
Generally speaking, California requires that four elements be shown for a plaintiff to succeed in an action for breach of an indemnity agreement: "the existence of an indemnity agreement, the plaintiff's performance under the agreement, breach of the agreement, and damages." (First Nat'l Ins., 2011 WL 2173765, at *3). Here it is beyond peradventure that the first two of those elements have been fulfilled. What this Court must therefore determine is whether it is clear that (1) Partnership had an obligation to collateralize Surety, indemnify Surety or both under the circumstances, (2) that Partnership failed to fulfill its obligation or obligations and (3) what damages, if any, resulted.
Surety's Complaint asserts a right to indemnification for two different types of costs: (1) indemnification for expenses and fees incurred while "defending, investigating and evaluating claims against the bonds" and (2) indemnification for losses it may incur "through the payment or settlement of claims [under the bonds]" (Compl. ¶ 30). As to the first request for indemnification, Partnership's Rule 8(b)(5) disclaimers (see Ans. ¶¶ 18, 30, 31) have effectively denied that such expenses and fees exist, so that indemnification for costs already incurred cannot be awarded at this stage of the litigation.
Surety's Complaint does not assert — or even suggest — that it has either
14A Cal. Jur.3d Contrib. & Indemnification § 52 (2012) explains the difference between those two types of indemnification:
True enough, Agreement ¶ 2 requires that Surety must be held "harmless from and against any and all demands, liabilities, losses, costs, damages, attorneys' fees and expenses ... whether or not the Surety shall have paid any sums in partial or complete payment thereof." But an appreciation of the distinction between a hold-harmless provision and an indemnification provision (which connotes making the indemnitee whole for damages it has sustained, as required by the California fourth element of "resulting damages" and the California Civil Code) points the way to the correct result here.
While the parties agree that BE & K has made a claim on the Bonds in connection with its Project, it is not yet clear whether that claim will actually be sustained so as to require payment. Partnership says that it never defaulted against BE & K, so that the claim is not valid (Ans. ¶ 19). For its part, Surety's Complaint ¶ 30 (emphasis added) states only that it "may incur losses through the payment or settlement of claims."
Although in the end Surety has "sole and absolute discretion to determine whether any claims under any Bond or Bonds shall be paid, settled or defended against" (Agreement ¶ 3.1), it is too early in the day for Surety to look to that provision — and in any event that does not justify a current requirement of payment of the claim by the Partnership just because Surety might otherwise ultimately have to pay on the claim. That of course is precisely why the Partnership's hold-harmless obligation is implemented by the Agreement's collateral security provision. This opinion turns, then, to a consideration of that provision.
Surety bargained for, and Partnership agreed to, Surety's right to demand collateral security not because they were remarkably prescient but rather because the problem posed here is a common one. Provisions of that nature are both recognized and enforced in California (Safeco Ins. Co. of Am. v. Schwab, 739 F.2d 431, 433 (9th Cir.1984), citing Gen. Ins. Co. v. Howard Hampton Inc., 185 Cal.App.2d 426, 8 Cal.Rptr. 353 (1960)).
While the breach of such a collateral security provision cannot be rectified through the traditional legal remedy of monetary reimbursement (remember that a surety will not have suffered an actual loss at the point where collateralization, as opposed to reimbursement, is appropriate), California courts have employed the equitable remedy of specific performance to enable sureties to receive the benefit of their collateral-security bargains (Safeco, 739 F.2d at 433).
All that the Agreement requires to trigger Surety's right to demand collateral is a "claim made against Surety" (Agreement ¶ 6). Partnership does not deny that BE & K made a $439,000 claim on the Bond on its Project (Ans. ¶ 19), bringing that provision facially into play. Partnership nonetheless argues that it was not obligated to meet Surety's collateral demands for two reasons: (1) Surety had a duty to investigate whether BE & K's claim was legitimate before asking for the full amount of the claim as collateral and (2) Partnership assigned all of its property to Surety in the Agreement, thus providing plenty of security and obviating the need for collateral.
Partnership's first argument is clearly bankrupt. Surety unequivocally had no obligation to examine the validity of BE & K's claim before demanding collateral to cover its possible losses. Under Agreement ¶ 6 collateral can be demanded in an amount sufficient to cover a claim and additional costs so long as the "claim is made against Surety, whether disputed or not." It matters not whether Partnership believes the claim to be bogus — collateral must be provided to protect Surety against the possibility that the claim is legitimate (Travelers Cas. & Sur., 2010 WL 5017798, at *6). Here BE & K sent Surety several letters asserting that Architectural Specialties defaulted on its subcontract, which gave Surety plenty of reason to believe that it might be liable to BE & K for the full amount claimed.
Partnership's second argument is likewise flat-out foreclosed by the clear language of the Agreement. It is true that the Agreement's assignment provision, which assigns to Surety all of Partnership's rights in its real and personal property, provides Surety with a level of security. But if Partnership were correct, that would read the collateral security provision out of the Agreement entirely as wholly meaningless — an impermissible way to read a contract. Simply put, the Agreement provides Surety with two levels of security, a belt-and-suspenders approach for which Surety bargained and that Partnership could have challenged before — but not after — the contract was arrived at by mutual agreement.
Partnership next argues that even if Surety had a right to demand $500,000 in collateral in response to BE & K's claim, Partnership met its obligations by offering Surety a stake in two pieces of real property. Partnership maintains that Surety's rejection of that offer amounted to a demand for cash collateral, which Partnership apparently believes to be illegitimate under the Agreement. Two separate clauses in the Agreement's collateral security provision torpedo that argument.
First, Agreement ¶ 6 (emphasis added) states that collateral must take the form of "cash or other property acceptable to Surety." It was up to Surety to determine whether a non-cash tender was adequate to the task, and because the real property offered as collateral was subject to a bank lien (a fact admitted by P. Mem. ¶ 6),
Partnership's final argument is that the effective demand for cash collateral will force it to liquidate assets, which would do irreparable harm to Partnership, so that this Court should not require that Partnership collateralize Surety with cash.
In sum, Partnership has failed to provide adequate collateral to protect Surety under the terms of the Agreement. And that failure entitles Surety to specific performance of the Agreement's collateral security provision, even at the pleading stage.
It is true that requiring specific performance of a collateral security provision is an equitable remedy (Travelers Cas. & Sur., 2010 WL 5017798, at *6) and that equitable remedies are inappropriate under California law when a legal remedy suffices to make an aggrieved litigant whole (see Bi-Rite Meat & Provisions Co. v. Redev. Agency of Hawaiian Gardens, 156 Cal.App.4th 1419, 1433 n. 12, 68 Cal.Rptr.3d 81 (2007)). But the very nature of the current situation negates the availability or adequacy of a legal remedy.
Remember that Partnership challenges the existence of the major default claimed by BE & K. Would it have Surety pay off the disputed claim, thus becoming entitled to demand cash indemnification from Partnership?
If this Court had been limited to consideration of the Complaint and Answer alone, as Surety's Rule 12(c) motion would normally have required, Partnership's combination of denials and Rule 8(b)(5)
What the foregoing analysis has demonstrated in that light is that Surety's motion for indemnification must be and is denied at this stage,