MILTON I. SHADUR, Senior District Judge.
International Union of Operating Engineers, Local 150, AFL-CIO (the "Union") brought this case to enforce an arbitration award against C3 Construction Services, Inc. ("C3").
As
Because "`a party cannot be required to submit to arbitration any dispute which he has not agreed to arbitrate,'" questions whether the parties have actually agreed to commit a dispute to arbitration are resolved according to ordinary contract principles (
As to charges that the arbitrator's decision did not "draw[] its essence from the contract," that standard does not authorize an inquiry into the merits of the award (
When the City of Chicago (the "City") wishes to demolish a building, it solicits task order bids from prequalified demolition contractors. As part of the prequalification process the contractors sign the City of Chicago Master Term Agreement for Demolition Services ("Master Agreement"). Master Agreement § 10 reproduces the City of Chicago Multi-Project Labor Agreement ("Multi-Project Agreement") in full, while Master Agreement § 2.57 specifies:
And the Multi-Project Agreement in turn incorporates a number of area-wide collective bargaining agreements, requiring that those agreements be made a part of all contracts entered into by the City when "the total Project value exceeds $25,000" (Multi-Project Agreement § 1).
C3 accepted the Master Agreement by signing Contract (PO) No. 26182, which prequalified it to submit task order bids and to be paid up to $3 million for demolition services from February 1, 2012 through January 31, 2015 (Complaint Ex. A). One of the Multi-Project Agreement signatory unions listed in the Master Agreement was the Union (Master Agreement § 10.1).
On May 17, 2013 the Union sent C3 a demand for arbitration pursuant to the Heavy and Highway and Underground Agreement Between the Mid-America Regional Bargaining Association (MARBA) and International Union of Operating Engineers, Local 150, AFL-CIO ("Collective Bargaining Agreement" — hereafter simply "CBA"). While C3 had been paid just under a half million dollars under the Master Agreement by August 2013, it responded that it was not bound by the CBA (or its arbitration clause) because no single demolition task was worth more than $25,000. It maintained that each task order bid it won gave rise to a separate contract and constituted a distinct "project."
That dispute was heard by Arbitrator Edwin H. Benn, who issued an opinion and award ("Arbitration Award") in the Union's favor on April 15, 2014. Arbitrator Benn held that the CBA formed a part of the Master Agreement that C3 had signed because it had been incorporated into the Multi-Project Agreement, which had itself been made a part of the Master Agreement (Award 5, 12).
When C3 refused to comply with the Arbitration Award, the Union filed this enforcement action on August 13, 2015. Because both sides agreed at the initial status hearing that the central issue in their case might be decided as a matter of law (Oct. 21, 2015 Tr. 3:9-4:2) — albeit with the reservation that some kind of (unspecified) factual dispute might require resolution before the case was disposed of entirely (
In its memorandum C3 urges that Arbitrator Benn's authority stemmed solely from the CBA. It takes a quantum leap from that premise to the conclusion that he thus exceeded his authority by interpreting the Master Agreement, so that his decision did not "draw its essence" from the CBA (C. Mem. 3). And C3 takes another leap by arguing that because it did not sign the CBA it never agreed to submit the dispute for arbitration in the first place (C. Mem. 4).
But both of those contentions collapse of their own weight (perhaps more precisely, they have no weight at all) because C3
What is at issue then is not at all whether C3 agreed to arbitrate according to the procedures outlined in the CBA. On the contrary, it was certainly the case that when C3 signed the Master Agreement, it agreed to submit to arbitration under the CBA all grievances arising from any project or projects whose total value exceeded $25,000 and that involved the Union. Thus it consented to arbitration under those near-plenary conditions.
Nor does this case turn on the question whether those conditions were satisfied. For while arbitrability is ordinarily for the courts to decide, parties can contract to submit that matter to arbitration as well (
And on that score there is nothing unsettled for this Court to decide, for our Court of Appeals has already held in
In light of that parallel, the ruling in
In short, because that same determinative language is present in an identical context in the CBA (which it must be remembered was made a part of the Master Agreement), C3 clearly consented to have the arbitrator determine the scope of his authority.
That being so, C3 cannot now base its opposition to the Union's enforcement suit on the argument that Arbitrator Benn erred in determining whether the Master Agreement required that its dispute with the Union be submitted for arbitration under the CBA. And C3's untenable insistence that Arbitrator Benn did not draw the essence of his decision regarding arbitrability from the CBA because he looked to the Master Agreement is no more than a stalking horse for the contention that he erred in his arbitrability determination, for it is plain that Arbitrator Benn was properly addressing the question whether he had authority under the contract that by its terms gave him that authority.
As the analysis in this opinion has shown, that authority expressly encompasses "interpretation or application of the [CBA]," which in turn calls for interpretation or application of the term "project," whose scope defines the relationships among the Union, the City and C3. On that score it must be remembered that the Master Agreement was not specifically tailored for the City-Union relationship — instead it is a sort of one-size-fits-all document.
It can scarcely be gainsaid that what has just been said in the preceding paragraph and its footnote clearly torpedoes the totally artificial construct of the concept of a "Project" sought to be advanced by C3. And it necessarily follows both as an original matter and a fortiori that Arbitrator Benn's reading of that concept "draws its essence from the contract" without any need to be bolstered by this Court's own independent arrival at the same destination.
Because the CBA assigns the question of arbitrability to the arbitrator and because that agreement was integrated into the Master Agreement that C3 signed with the City of Chicago, this Court rejects C3's lame effort to block enforcement of the Arbitration Award on the even less than specious ground that it was beyond the scope of the arbitrator's authority. To discuss where this opinion leaves the case, a status hearing is set for March 21, 2016 at 8:45 am.