BAKER, Judge.
Timothy Paul appeals the judgment of the trial court finding that he breached his contract with Stone Artisans, Ltd. (Stone Artisans), and foreclosing a mechanic's lien on his home. Finding no error, we affirm.
In September 2012, Timothy Paul wanted to replace the countertops and backsplashes in the bathrooms and kitchen of his home. Paul spoke with an interior designer who contacted Stone Artisans on his behalf. The interior designer provided Stone Artisans with information regarding the countertops and backsplashes that Paul desired for his home.
On September 11, 2012, Stone Artisans emailed Paul a contract detailing the cost of the necessary materials and labor needed to install the new countertops and backsplashes. The contract amount totaled $5,499.00. The email accompanying the contract stated: "Please approve of the following contract. Please email me that you approve of the attached contract." Appellant's App. p. 11. Later that day, Paul responded by email, simply stating "agree." Id.
The contract required half of the total amount, $2,749.50, to be paid before Stone Artisans would begin any work on Paul's home. Paul paid this amount by check and Stone Artisans began to perform the work, completing performance at some point before September 30, 2012. Upon completion, both Paul and the interior designer expressed their satisfaction with Stone Artisans's work.
Stone Artisans billed Paul for the remaining amount approximately seven days after completion of the work but did not receive payment from Paul. After a month had passed with no payment from Paul, Stone Artisans filed a Sworn Statement and Notice of Intention to Hold Mechanic's Lien (Mechanic's Lien) in the Office of the Hamilton County Recorder on October 29, 2012. The Mechanic's Lien identified the amount owed by Paul as $2,899.00.
About six months later, on April 17, 2013, Stone Artisans filed a Complaint to Foreclose Mechanic's Lien and for Damages in the trial court. Paul filed an answer on May 15, 2013, claiming, among other things, that no contract existed between
The trial court held a bench trial on March 4, 2014, and found in favor of Stone Artisans, entering an in rem judgment as to Paul's home in the amount of $12,577.13. The judgment consisted of the balance due under the contract, attorney fees, costs, and interest. Paul now appeals.
In entering its judgment in favor of Stone Artisans, the trial court issued findings of fact and conclusions of law. When the trial court issues findings of fact and conclusions of law, we employ a two-tiered standard of review. Cyr v. J. Yoder, Inc., 762 N.E.2d 148, 149-50 (Ind.Ct. App.2002). We first determine whether the evidence supports the findings and then we determine whether the findings support the judgment. Id. at 150. We will not disturb the trial court's findings or judgment unless they are clearly erroneous. Infinity Prods., Inc. v. Quandt, 810 N.E.2d 1028, 1031 (Ind.2004). We will consider only the evidence favorable to the findings and judgment and all reasonable inferences drawn therefrom. Id. We will not reweigh the evidence or assess the credibility of the witnesses. Id. at 1032. Questions of law will be reviewed under a de novo standard. Hayes v. Chapman, 894 N.E.2d 1047, 1052 (Ind.Ct.App.2008).
Paul first claims that no valid contract existed because the contract sent by Stone Artisans failed to include all the essential terms of the agreement. The trial court disagreed, noting: "The Contract includes an offer, consideration, and acceptance and represents an enforceable contract between Stone Artisans and Mr. Paul." Appellant's App. p. 80.
Here, the contract between Stone Artisans and Paul was for the purchase and installation of countertops and backsplashes. The contract listed four countertops and backsplashes to be installed, and provided descriptions of the materials to be used and prices for each. The contract further specified that the countertops would contain cutouts for the sinks and faucets. Paul argues that, in order for the contract to include all essential terms, the contract "had to include measurements defining the position, size and shape for the sink and plumbing holes." Appellant's Br. p. 9. However, the contract was sent to Paul before Stone Artisans came to Paul's home to take these measurements. Therefore, Paul argues that the contract sent by Stone Artisans was merely a preliminary negotiation because "the final essential terms do not appear in [the contract] and were never before the trial court." Id.
Our Supreme Court has held that "[a]ll that is required to render a contract enforceable is reasonable certainty in the terms and conditions of the promises made" and that "certainty in all terms is not required." Conwell v. Gray Loon Outdoor Mktg. Grp., Inc., 906 N.E.2d 805, 813 (Ind.2009). Paul provides no support for his contention that the exact measurements of the size of the holes for the sink and the faucets were essential terms of the contract. Paul does not argue that he was induced into entering into the contract based, in part, upon his understanding of the exact size of these holes. The size of
Paul next argues that the contract is void for failure to strictly comply with the requirements of HICA. The trial court found that although the contract did not satisfy all of HICA's requirements, it substantially complied with the Act, and this substantial compliance was sufficient to support a judgment in favor of Stone Artisans.
Under HICA, a home improvement contract is required to contain nine elements. I.C. § 24-5-11-10. The trial court found that Stone Artisans's contract contained all of these elements with two exceptions. The contract omitted "[t]he approximate starting and completion dates of the home improvements" and "a legible printed or a typed version of [the consumer's] name placed directly after or below the signature," as required by subsections (a)(6) and (a)(9), respectively. Id. Consequently, the contract failed to strictly comply with HICA.
Initially we note that, when interpreting statutes, "[c]ourts must consider the goals of the statute and the reasons and policy underlying the statute's enactment." Bowyer v. Ind. Dep't. of Natural Res., 944 N.E.2d 972, 988 (Ind.Ct.App. 2011) (quotations omitted). Additionally, we must consider the effects of our interpretation. Kitchell v. Franklin, 997 N.E.2d 1020, 1026 (Ind.2013). This Court has observed that the purpose of HICA
Benge v. Miller, 855 N.E.2d 716, 720 (Ind. Ct.App.2006) (citations omitted). Consequently, HICA requires home improvement contracts for an amount greater than $150 to contain the nine elements listed in Indiana Code section 24-5-11-10.
Violations of HICA are labeled "deceptive acts" and are actionable by the attorney general or by the consumer. I.C. § 24-5-11-14. HICA provides victims of deceptive acts with the same remedies specified for victims of deceptive sales under the Deceptive Consumer Sales Act, which provides that "[a] person relying upon an uncured or incurable deceptive act may bring an action for the damages actually suffered as a consumer as a result of the deceptive act or five hundred dollars
This Court has observed that, generally, contracts made in violation of a statute are void. Imperial Ins. Restoration & Remodeling, Inc. v. Costello, 965 N.E.2d 723, 728 (Ind.Ct.App.2012). However, "because we value freedom of contract so highly," we will not void a contract for contravening a statute unless the statute dictates unambiguously that such contravention renders a contract void. Id. "The Indiana General Assembly has made clear its intent that certain types of contracts not be enforced by declaring them `void' or `unenforceable.'" Id.
With respect to HICA, the General Assembly has not included a provision that contracts that violate HICA's requirements are void. Rather, HICA creates a cause of action for which voiding the contract is one possible remedy. Costello, 965 N.E.2d at 729. This Court has previously elaborated:
Costello, 965 N.E.2d at 729. Thus, the statute leaves it to the trial court to determine whether voiding the contract is an appropriate remedy.
In making this decision, the trial court must apply a balancing approach and examine certain factors to determine if the contract violates public policy. Id. The court should consider (1) the nature of the subject matter of the contract, (2) the strength of the public policy underlying the statute, (3) the likelihood that refusal to enforce the bargain or term will further that policy, (4) how serious or deserved the forfeiture suffered by the party attempting to enforce the bargain would be, and (5) the parties' relative bargaining power and freedom to contract. Id.
As noted above, the public policy underlying HICA is to protect consumers when making home improvement contracts. However, the trial court observed that in this case, "[n]ot enforcing the contract would do little to further the policy behind [HICA]." Appellant's App. p. 86. HICA was a response to "well-known abuses found in the home improvement industry." Benge, 855 N.E.2d at 720. The trial court found no such abuse here, noting that "[d]espite any deficiencies in the contract, Mr. Paul received the benefit of Stone Artisans' services and was fully aware of all the terms of his relationship with Stone Artisans." Appellant's App. p. 86.
In regard to the forfeiture that would be suffered by Stone Artisans were the contract not enforced, the trial court noted that "[a]t no time prior to the completion of the work at the Paul Residence, and Mr. Paul's approval of Stone Artisans' work,
We agree with the trial court's determination that a consideration of the relevant factors points decisively towards enforcing this contract. Although any violation of HICA is considered a "deceptive act," Paul was not deceived here. I.C. § 24-5-11-14. He contracted for services which were performed to his satisfaction. It was not until it came time to pay for these services that he lodged any complaint. Appellant's App. p. 82. HICA aims to protect consumers from abuse, not to provide an escape from legitimate contractual obligations.
The judgment of the trial court is affirmed and the cause is remanded to the trial court for further calculation of appellate attorney fees and costs as provided for in the contract.
ROBB, J., and BARNES, J., concur.