ROBB, Judge.
In 2006, Edward and Rebecca Rusnak contracted with Brent Wagner Architects ("BWA") for the design of a home to be constructed on a lot they had recently purchased. Alan R. Sommers Construction Company ("Sommers"), as general contractor, constructed the home between 2008 and 2010. This litigation commenced in 2013 when Sommers sued, seeking to enforce the Rusnaks' obligation to pay for the home.
In May 2006, the Rusnaks entered into a Tot Purchase Agreement with 400 North, TTC ("400 North") for the purchase of a lot in the Pepper Creek subdivision in Valparaiso. In September 2006, the Rusnaks entered into a contract for BWA to design the home they planned to build in Pepper Creek. The contract documents signed by the parties include "AIA Document B155 Standard Form of Agreement Between Owner and Architect for a Small Project," which identifies the following responsibilities of the architect for the project:
Appellants' App. at 163-64 (emphasis added). "AIA Document A205 General Conditions of the Contract for Construction of a Small Project," further describes the architect's administration of the contract:
Id. at 168. "Work" is defined as "the construction and services required by the Contract Documents, and includes all other labor, materials, equipment and services provided by the Contractor to fulfill the Contractor's obligation." Id. at 167. Document A205 also describes the contractor's responsibilities, including:
Id. at 168. Ultimately, the Rusnaks selected Sommers as their contractor and executed a promissory note to Sommers in the amount of $376,448.44. The home was built from 2008 to 2010.
On November 12, 2013, Sommers filed a lawsuit against the Rusnaks, alleging breach of contract and unjust enrichment for their failure to pay the promissory note in full. The Rusnaks filed their answer, affirmative defenses, and counterclaim against Sommers, and also filed a third party complaint against BWA.
During discovery, the Rusnaks' answers to interrogatories propounded by BWA explained their theory of liability against BWA:
Id. at 201. Their answers also set forth a litany of work they allege did not conform
Id. at 202.
The Rusnaks propounded the following interrogatories to BWA:
Id. at 223. With regard to the front steps, the Rusnaks' interrogatory answers stated:
Id. at 203.
On February 4, 2015, BWA filed a motion for summary judgment, arguing the Rusnaks "seek to hold BWA liable for the alleged acts and omissions of Sommers and its contractors in the construction of the home" but the AIA documents that comprise the contract and govern the relationship between BWA and the Rusnaks "make clear that BWA cannot be held liable for any alleged defects or mistakes by Sommers or its contractors." Id. at 151. On April 24, 2015, the Rusnaks responded to the motion for summary judgment, opposing the motion on the ground that BWA agreed to act as their representative during the construction phase and despite having the authority and duty to reject nonconforming work, failed to do so: "[BWA's] actions and inactions in failing to reject the nonconforming Work is a genuine issue of material fact that must be decided by the trier of fact in this matter." Id. at 173. The interrogatory answers set forth above were among the evidence designated by the parties. A hearing on the motion for summary judgment was scheduled for May 27, 2015.
On May 20, 2015, the Rusnaks filed a Motion for Leave to File Amended Complaint, alleging that through discovery,
On May 27, 2015, the trial court held the scheduled hearing on BWA's motion for summary judgment. The trial court took the matter under advisement. On June 1, 2015, BWA filed a response to the Rusnaks' motion to amend their complaint, asserting the motion "is untimely and prejudicial, and will be moot if the Court grants BWA's motion for summary judgment." Id. at 247.
On July 9, 2015, the trial court entered an order on both pending motions. The trial court denied the motion to amend without further comment. With respect to BWA's motion for summary judgment, the trial court stated:
Id. at 281. Because the summary judgment for BWA did not dispose of all claims against all parties involved in the litigation, BWA moved for entry of final judgment pursuant to Indiana Trial Rule 54(B). The trial court granted BWA's motion on July 17, 2015, noting it had granted summary judgment to BWA on all claims against it, determining there was no just reason for delay, and expressly directing entry of final judgment for BWA.
The Rusnaks filed a motion to correct error with respect to both the grant of summary judgment to BWA and the denial of leave to amend their complaint. After a hearing, the trial court entered the following order:
Id. at 330. The trial court denied the motion to correct error, and this appeal ensued.
The party moving for summary judgment must "affirmatively negate an
We review an order granting summary judgment de novo, which is the same standard of review applied by the trial court. Hughley, 15 N.E.3d at 1003. When the trial court has granted summary judgment to the moving party, the non-moving party has the burden on appeal of persuading us that the grant of summary judgment was in error. Id. However, "we carefully assess the trial court's decision to ensure that [the nonmoving party] was not improperly denied his day in court." Id. (citation omitted). In reviewing the record, we consider only the evidentiary matter the parties have designated to the trial court, see T.R. 56(C), (H), and we construe all reasonable inferences in favor of the nonmoving party, Hughley, 15 N.E.3d at 1003. "A fact is `material' if its resolution would affect the outcome of the case, and an issue is `genuine' if a trier of fact is required to resolve the parties' differing accounts of the truth, or if the undisputed material facts support conflicting reasonable inferences." Id. (quoting Williams v. Tharp, 914 N.E.2d 756, 761 (Ind.2009)).
Indiana's heightened summary judgment standard "consciously errs on the side of letting marginal cases proceed to trial on the merits, rather than risk short-circuiting meritorious claims." Id. at 1004.
This appeal requires the interpretation and construction of a contract, which are questions of law. John M. Abbott, LLC v. Lake City Bank, 14 N.E.3d 53, 56 (Ind.Ct.App.2014). As such, cases involving contract interpretation are particularly appropriate for summary judgment. Id. And because the interpretation of a contract presents a question of law, it is reviewed de novo by this court. Jenkins v. S. Bend Cmty. Sch. Corp., 982 N.E.2d 343, 347 (Ind.Ct.App.2013), trans. denied. We review the contract as a whole, attempting to ascertain the parties' intent and making every attempt to construe the language of the contract "so as not to render any words, phrases, or terms ineffective or meaningless." Four Seasons Mfg., Inc. v. 1001 Coliseum, LLC, 870 N.E.2d 494, 501 (Ind.Ct.App.2007). If a contract's terms are clear and unambiguous, we give those terms their plain and ordinary meaning. Dunn v. Meridian Mut. Ins. Co., 836 N.E.2d 249, 251 (Ind. 2005). When the terms of a contract are ambiguous or uncertain, however, and its interpretation requires extrinsic evidence, its construction is left to the factfinder. Johnson v. Johnson, 920 N.E.2d 253, 256 (Ind.2010). Any ambiguity in the contract is construed against the drafter. MPACT Constr. Grp., LLC v. Superior Concrete Constructors, Inc., 802 N.E.2d 901, 910 (Ind.2004). A contract is ambiguous if reasonable people would disagree as to the meaning of its terms. Beam v. Wausau Ins. Co., 765 N.E.2d 524, 528 (Ind.2002).
When summary judgment is granted based on the construction of a written contract, the trial court has either determined as a matter of law that the contract is not ambiguous or uncertain, or that any contract ambiguity can be resolved
The contract documents between the Rusnaks and BWA provide that during construction, BWA will visit the construction site to become familiar with the progress and quality of the contractor's work — that is, the construction and services required by the contract documents — and has the authority to reject non-conforming work on behalf of the owners. See Appellants' App. at 164 (Document B155, article 1.2) and 168 (Document A205, article 4). The designated evidence includes many examples of Sommers' work the Rusnaks claim do not conform to the contract. Edward Rusnak avers in his designated affidavit that the Rusnaks brought multiple non-conformities to BWA's attention, but BWA failed to address them with Sommers or reject any of the work. The designated evidence also includes an admission by BWA that it observed at least one non-conformity. Although BWA itself does not indicate that it brought that non-conformity to Sommers' attention or otherwise took action regarding the non-conforming work, the Rusnaks' answers to interrogatories indicate BWA did approach Sommers about the problem, and when told it was too late to fix the problem, did nothing further.
Focusing on the exculpatory clause in Document A205, BWA argues it "cannot be held liable for the alleged failure of Sommers to use the proper means, methods, techniques, or procedures in executing its own contractual obligations." Brief of Appellee at 11. The Rusnaks "agree wholeheartedly" that BWA is not responsible for the "shoddy construction work performed by Sommers." Appellants' Brief at 15. But they assert — and we agree — that the clause relieving BWA of liability for the contractor's performance of the work does not excuse BWA from meeting its own obligation to reject work it knows fails to conform to the contract documents, plans, and specifications. If the exculpatory clause were interpreted to mean that BWA cannot be held accountable for failing to reject non-conforming work because the work itself is the province of the contractor, then BWA's clearly stated responsibility to reject non-conforming work is essentially meaningless. We will not construe a contract such that a term is meaningless when it is possible to do otherwise. See Storch v. Provision Living, LLC, 47 N.E.3d 1270, 1273 (Ind. Ct.App.2015).
Because the designated evidence shows BWA observed at least one item of non-conforming work, the question is what does the contract term "reject non-conforming Work" mean? The Rusnaks' answers to interrogatories indicate BWA did address with Sommers the front steps — when they were still just framed — and Sommers said "they needed to deal with it" because the cement trucks were already on the way and it was too late to do anything about it. Appellants' App. at 203. The steps were poured as they were wrongly framed. "Reject" is defined as "to refuse to accept, consider, submit to, take for some purpose, or use." Merriam-Webster Online Dictionary, http://www.merriam-webster.com/dictionary/reject
There is a reasonable question about what the term "reject" as used in the contract documents means, and that uncertainty should be addressed by the factfinder. See Johnson, 920 N.E.2d at 256. Moreover, there is a question of fact at least as to whether BWA's actions in the face of a known non-conformity in the work met its contractual obligation to reject non-conforming work on the Rusnaks' behalf. Construing the designated evidence and reasonable inferences in the Rusnaks' favor and applying Indiana's heightened summary judgment standard, we conclude the trial court erred in granting summary judgment to BWA.
Trial Rule 15(A) provides that a party "may amend his pleading once as a matter of course" if within a certain time frame. "Otherwise a party may amend his pleading only by leave of court or by written consent of the adverse party; and leave shall be given when justice so requires." T.R. 15(A). Amendments to pleadings are to be liberally allowed, but the trial court retains broad discretion to grant or deny motions to amend pleadings. Hilliard v. Jacobs, 927 N.E.2d 393, 398 (Ind.Ct.App.2010), trans. denied. We will only reverse upon an abuse of that discretion, which occurs when the trial court's decision is clearly against the logic and effect of the facts and circumstances before the court or when the trial court has misinterpreted the law. Id. We judge an abuse of discretion by evaluating several factors, including "undue delay, bad faith, or dilatory motive on the part of the movant, repeated failure to cure deficiency by amendment previously allowed, undue prejudice to the opposing party by virtue of the amendment, and futility of the amendment." Id. (citation omitted).
The trial court explained in its order on the Rusnaks' motion to correct error that there was no evidence of bad faith, dilatory motive, or previous failure to cure deficiencies by the Rusnaks. Nonetheless, because the parties had already
Appellants' App. at 330-31. In short, it appears the trial court denied the Rusnaks' motion to amend their complaint to add a second count because it was simultaneously granting BWA's motion for summary judgment on the initial — and at that time, only — count.
The Rusnaks filed their third party complaint against BWA on January 8, 2014, alleging that BWA "owed a duty to [the Rusnaks] to properly design and supervise the construction project [and BWA] breached this duty by allowing the construction conduct to fall below the applicable standard of care." Id. at 42. The parties engaged in discovery throughout 2014, during which the Rusnaks elaborated in their interrogatory answers on their theory of BWA's liability, focusing solely on BWA's obligations during the construction phase. BWA filed its motion for summary judgment on February 4, 2015, and the Rusnaks made a request in mid-February 2015 for a higher resolution copy of certain architectural drawings previously supplied in discovery. They also asked for an extension of time to file their summary judgment response. After receiving the drawings from BWA in mid-March, the Rusnaks made a second request in early April for an extension of time to respond to the summary judgment motion and noted they were going to have an engineer review the drawings. The Rusnaks filed their summary judgment response on April 22, 2015, addressed only to their claim BWA breached the contract during the construction phase, and one month later, filed their motion for leave to amend their complaint to add a count of breach of contract for design defects.
"The stated policy of this court and our Supreme Court is to freely allow such amendments in order to bring all matters at issue before the court." Kreilein v. Common Council of City of Jasper, 980 N.E.2d 352, 358 (Ind.Ct.App. 2012). Leave to amend should be granted unless the amendment will result in prejudice to the opposing party. Id. In Hilliard, we held the trial court did not abuse its discretion in denying the plaintiff's motion for leave to file a third amended complaint in part because of prejudice to the opposing party. 927 N.E.2d at 401. The motion to amend was filed three years after the original complaint, the claims to be added could have been raised in the original complaint and there was no convincing explanation for why they had not been, and the plaintiff sought leave to amend only after it was apparent the initial claims would fail. Id. at 400; see also Crawford v. City of Muncie, 655 N.E.2d 614, 623 (Ind.Ct.App.1995) (holding the trial court did not abuse its discretion by denying leave to amend the complaint because
Here, the Rusnaks filed their first and only motion to amend approximately eighteen months after the original complaint was filed. The statute of limitations had not yet run, no discovery deadlines or trial dates had been set in the existing litigation, and summary judgment on the initial claim, while fully briefed, had not yet been decided. The Rusnaks asserted they had only just recently discovered a basis for a design defect claim such that the claim could not have been brought in the original complaint.
There are issues for the factfinder regarding the nature of BWA's obligations under the contract and whether it met them; therefore, summary judgment for BWA was improper at this stage. The trial court abused its discretion in denying the Rusnaks' motion to amend their complaint to add an additional claim because no prejudice will result to BWA. The judgment of the trial court is reversed and this case is remanded for further proceedings consistent with this opinion.
Reversed and remanded.
BARNES, J., and ALTICE, J., concur.