TANYA WALTON PRATT, District Judge.
This matter is before the Court on both a Motion for Judgment on the Pleadings (
Federal Rule of Civil Procedure 56 provides that summary judgment is appropriate if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a). In ruling on a motion for summary judgment, the court reviews the record in the light most favorable to the non-moving party and draws all reasonable inferences in that party's favor. Zerante, 555 F.3d at 584; Anderson, 477 U.S. at 255.
The party seeking summary judgment bears the initial responsibility of informing the court of the basis for its motion, and identifying "the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any," which demonstrate the absence of a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986) (noting that when the non-movant has the burden of proof on a substantive issue, specific forms of evidence are not required to negate a non-movant's claims in the movant's summary judgment motion, and that a court may grant such a motion, "so long as whatever is before the district court demonstrates that the standard . . . is satisfied"); see also Fed. R. Civ. P. 56(c)(1)(A) (noting additional forms of evidence used in support or defense of a summary judgment motion, including "depositions, documents electronically stored information, affidavits or declarations, stipulations . . ., admissions, interrogatory answers, or other materials").
Thereafter, a non-moving party who bears the burden of proof on a substantive issue may not rest on its pleadings, but must affirmatively demonstrate by specific factual allegations that there is a genuine issue of material fact that requires trial. Hemsworth v. Quotesmith.Com, Inc., 476 F.3d 487, 490 (7th Cir. 2007); Celotex Corp., 477 U.S. at 323-24; Fed. R. Civ. P. 56(c)(1). Neither the mere existence of some alleged factual dispute between the parties nor the existence of some "metaphysical doubt" as to the material facts is sufficient to defeat a motion for summary judgment. Chiaramonte v. Fashion Bed Grp., Inc., 129 F.3d 391, 395 (7th Cir. 1997); Anderson, 477 U.S. at 247-48; Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586 (1986). "It is not the duty of the court to scour the record in search of evidence to defeat a motion for summary judgment; rather, the nonmoving party bears the responsibility of identifying the evidence upon which [it] relies." Harney v. Speedway SuperAmerica, LLC, 526 F.3d 1099, 1104 (7th Cir. 2008).
Similarly, a court is not permitted to conduct a paper trial on the merits of a claim and may not use summary judgment as a vehicle for resolving factual disputes. Ritchie v. Glidden Co., ICI Paints World-Grp., 242 F.3d 713, 723 (7th Cir. 2001); Waldridge v. Am. Hoechst Corp., 24 F.3d 918, 920 (7th Cir. 1994). Indeed, a court may not make credibility determinations, weigh the evidence, or decide which inferences to draw from the facts. Payne v. Pauley, 337 F.3d 767, 770 (7th Cir. 2003) (highlighting that "these are jobs for a factfinder"); Hemsworth, 476 F.3d at 490. When ruling on a summary judgment motion, a court's responsibility is to decide, based on the evidence of record, whether there is any material dispute of fact that requires a trial. Id.
The following facts are virtually undisputed, but any disputes, as required by Federal Rule of Civil Procedure 56, are presented in the light most favorable to Bishop as the non-moving party. See Zerante v. DeLuca, 555 F.3d 582, 584 (7th Cir. 2009); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255 (1986).
Drees hired Bishop in May 2014 as a Market Manager in its Indianapolis Division, and Bishop's duties included discussing building and financing options with customers, reviewing home building plans, and receiving purchasing orders and executed contracts. (
The Compensation Agreement also specifies what effect an employee's voluntary or involuntary termination has on his commission payments. The Compensation Agreement provides as follows:
(
Bishop filed suit in Indiana state court raising several claims against Drees involving unpaid wages. He seeks payment for the unpaid commissions under Indiana Code Sections 22-2-9-2(a) (commonly referred to as the "Indiana Wage Claims Statute") and 22-2-5-2 (commonly referred to as the "Indiana Wage Payment Statute"); breach of the implied promise of good faith and fair dealing; tortious breach of the implied promise of good faith and fair dealing; quantum meruit; and unjust enrichment. (
At the heart of Bishop's claim is his contention that the Compensation Agreement is unenforceable (or void) as contrary to public policy. (
Bishop argues that the Compensation Agreement is void, because it —
(
The Indiana Court of Appeals has articulated the general rule that "a person employed on a commission basis to solicit sales orders is entitled to his commission when the order is accepted by his employer." Vector Eng'g & Mfg. Corp. v. Pequet, 431 N.E.2d 503, 505 (Ind. Ct. App. 1982). In Vector, however, the court concluded that "[t]his general rule may be altered by a written agreement by the parties or by the conduct of the parties which clearly demonstrates a different compensation scheme." The court highlighted that "[i]f Vector had desired to deny commissions to [the employee] subsequent to his termination as an employee, Vector could have provided for this contingency in clear and unambiguous language." Id.
Bishop concedes that the Indiana Supreme Court has never concluded that contracts with commission-termination provisions such as the one hypothesized in Vector and at issue here are unenforceable. (
Drees points to a number of other Indiana Court of Appeals cases applying the Vector rule that commission-termination provisions may be used to contract around the default commission accrual rule. In Robinson v. Century Pers., Inc., 678 N.E.2d 1268, 1271 (Ind. Ct. App. 1997), the court explicitly adopted the Vector rule, and declined to follow the concurring opinion in Weiser. The court concluded that the Weiser opinion "as a plurality decision, is of no precedential value and is not binding upon either the trial court or this court." Robinson, 678 N.E.2d at 1271. The court also concluded that employers and employees were free to agree that commissions would not be paid after an employee's termination. Id. A number of other Court of Appeals decisions post-dating Weiser and Robinson have likewise applied the rule formulated in Vector. See, e.g., Helmuth v. Distance Learning Systems Indiana, Inc., 837 N.E.2d 1085, 1089 (Ind. Ct. App. 2005); J. Squared, Inc. v. Herndon, 822 N.E.2d 633, 637 (Ind. Ct. App. 2005); Davis v. All American Siding & Windows, Inc., 897 N.E.2d 936, 940 (Ind. Ct. App. 2008).
The Court has not uncovered any Indiana Supreme Court decisions addressing this issue, but "when the intermediate appellate courts of the state have spoken to the issue, [the Court] shall give great weight to their determination about the content of state law, absent some indication that the highest court of the state is likely to deviate from those rulings." Pisciotta v. Old Nat. Bancorp, 499 F.3d 629, 635 (7th Cir. 2007). The balance of authority from the Indiana Court of Appeals favors the rule announced in Vector. Bishop cites no authority other than the concurring opinion in Weiser in support of his argument, and every other on-point authority reviewed by this Court applies the rule announced in Vector. Moreover, the Indiana Supreme Court has repeatedly counseled that "[c]ourts in Indiana have long recognized the freedom of parties to enter into contracts and have presumed that contracts represent the freely bargained agreement of the parties. We continue to believe that it is in the best interest of the public not to restrict unnecessarily persons' freedom of contract." Trimble v. Ameritech Pub., Inc., 700 N.E.2d 1128, 1129 (Ind. 1998).
Given the balance of Indiana intermediate appellate court authority, and the Indiana Supreme Court's emphasis on avoiding the unnecessary restriction of parties' freedom to contract, the Court concludes that the contract is not void, and it is enforceable between the parties as written.
Drees moves for summary judgment on Bishop's claims under the Indiana Wage Payment Statute and Indiana Wage Claim Statute. In his response, Bishop fails to provide any argument in opposition to summary judgment regarding those claims. A party waives arguments not presented to the district court in response to summary judgment motions. See Laborers' Int'l Union v. Caruso, 197 F.3d 1195, 1197 (7th Cir. 1999).
Perhaps Bishop does not respond because he cannot prevail on the merits of this claim. Drees argues the Indiana Wage Payment Statute does not apply to Bishop, because it only applies to those employees who are currently employed or have voluntarily left their employment. (
Regarding the Indiana Wage Claim Statute, Drees argues that, because no further compensation is due under the terms of the contract, Bishop cannot maintain a claim for unpaid wages. (
The Court
Drees next argues that Bishop cannot maintain a claim for breach (or tortious breach) of the implied promise of good faith and fair dealing, because it fully complied with the terms of the Compensation Agreement. (
As for Drees' first argument, the Court agrees. It is undisputed that Drees acted in accordance with the terms of the contract. Under those circumstances, the Court cannot conclude that Drees' conduct constitutes bad faith. See Hanover Ins. Co. v. N. Bldg. Co., 751 F.3d 788, 794-95 (7th Cir. 2014) ("Hanover did exactly what it was empowered to by the Agreement. We cannot call that bad faith.").
As for Drees' second argument, Bishop contends, without any citation to legal authority, that Drees' "conclusions" (the Court assumes with respect to either whether Bishop was an at-will employee or as to whether the implied covenant of good faith and fair dealing applies to at-will employees) "are only valid, if at all, for situations where no written contract is present." (Filing No. 43 at 13.) Under Indiana law, "[e]mployment at will exists when an employee may be terminated for any reason or for no reason at all. In Indiana, the employment relationship is terminable at will unless there is a promise of employment for a fixed duration or consideration given by the employee in addition to his services." Hamblen v. Danners, Inc., 478 N.E.2d 926, 928 (Ind. Ct. App. 1985). The undisputed evidence establishes that Bishop was an at-will employee. As to the duty of good faith and fair dealing, "Indiana does not recognize that a duty of good faith and fair dealing is owed by an employer to an employee at will." Hamblen, 478 N.E.2d at 929 (citing Perry v. Hartz Mountain Corp., (S.D. Ind. 1982)). Drees cites no case law to support the assertion that this rule only applies to at-will employees when there is no written contract. Indeed, Hamblen involved an executed, written employment agreement. Therefore, the Court concludes that under Indiana law, Drees did not owe Bishop a duty of good faith and fair dealing.
Accordingly, the Court
Drees argues that the existence of an express contract between the parties precludes equitable claims for unjust enrichment and quantum meruit. (
As described above, Bishop's argument is unavailing, because the Court has concluded that the contract is indeed enforceable. Bishop does not and could not successfully raise an argument that these equitable forms of relief would be available given the Court's conclusion that the contract is valid. See Kohl's Indiana, L.P. v. Owens, 979 N.E.2d 159, 168 (Ind. Ct. App. 2012) ("When the rights of the parties are controlled by an express contract, recovery cannot be based on a theory implied in law. The existence of an express contract precludes a claim for unjust enrichment because: (1) a contract provides a remedy at law and (2) as a remnant of chancery procedure a plaintiff may not pursue an equitable remedy when there is a remedy at law.") (citations omitted); see also Indus. Dredging & Eng'g Corp. v. S. Indiana Gas & Elec. Co., 840 F.2d 523, 525 (7th Cir. 1988) ("Indiana appellate courts have uniformly held that the existence of a valid express contract for services . . . precludes implication of a contract covering the same subject matter. The rights of the parties are controlled by the contract and under such circumstances recovery cannot be had on the theory of quantum meruit.") (internal quotations and citations omitted). The Court therefore
For the reasons stated above, Drees' Motion for Summary Judgment, (Filing No. 39), is
Final judgment will issue under separate order.