ERIC F. MELGREN, District Judge.
This matter comes before the Court on a Motion for Entry of Final Judgment (Doc. 130) filed by Defendant Hartwig, Inc., after it prevailed in the Court's granting of summary judgment against all of the claims asserted by Plaintiff Patriot Manufacturing LLC. Hartwig seeks an entry of final judgment under Federal Rule of Civil Procedure 54(b) to allow Patriot to appeal before Hartwig's breach-of-contract counterclaim goes to trial. Because Hartwig fails to show hardship to either party that outweighs the policy against piecemeal appeals, the Court denies the motion.
This case involves competing breach of contract claims that were asserted after Defendant Hartwig, Inc., repossessed a machine shop lathe it sold to Plaintiff Patriot Manufacturing LLC in 2008.
Before the Court is Hartwig's Motion for Entry of Judgment. Hartwig asks the Court to direct entry of a final judgment as to Patriot's claims to allow Patriot the option of appealing the Court's ruling and to stay proceedings on Hartwig's pending counterclaim.
Hartwig has moved for an Entry of Final Judgment under Federal Rule of Civil Procedure 54(b). Hartwig seeks a Rule 54(b) certification of the Court's February 6, 2014, Order that granted Hartwig's motion for summary judgment based on judicial estoppel of Patriot's breach-of-contract claims. Hartwig has indicated its intention to voluntarily dismiss its counterclaim— and avoid the cost of a trial—if the Court's order is affirmed. But Hartwig wishes to preserve its counterclaim in the event that the Court's order is reversed and a trial takes place. Patriot, however, opposes the motion.
Under Rule 54(b), when multiple claims or parties are involved in an action, "the court may direct entry of a final judgment as to one or more, but fewer than all, claims or parties only if the court expressly determines that there is no just reason for delay."
To be final, an order "must be final in the sense that it is an ultimate disposition of an individual claim entered in the course of a multiple claims action."
Here, the Court finds that its February 6 Order is a final judgment with respect to all of Patriot's claims for purposes of Rule 54(b). The order granted Hartwig summary judgment on all of Patriot's claims based on judicial estoppel as a result of Spencer failing to report his ownership interest or this lawsuit in his bankruptcy filing. Thus, Patriot has no remaining claims from its six-count complaint. Patriot's claims are distinct and separable from Hartwig's counterclaim for breach of contract because they involved different legal issues and a separate recovery is possible. The Court notes that Patriot's claims were not resolved on the merits, and the claims turn on the same factual questions as Hartwig's breach-of-contract counterclaim.
In deciding whether the second requirement for Rule 54(b) certification is satisfied, the Court "must take into account judicial administrative interests as well as the equities involved."
Here, Hartwig argues for Rule 54(b) certification because it believes it would be judicially efficient to allow Patriot to appeal this Court's adverse judgment now and stay resolution of Hartwig's counterclaim. Hartwig asserts that granting its motion will necessarily eliminate one entire trial and states that it would be in the best interests of the parties to do so. Patriot, however, disagrees and opposes the motion. Patriot argues that avoiding the expense of a trial does not warrant Rule 54(b) certification.
Notably, this is not the usual case of a losing party seeking Rule 54(b) certification. Rather, the prevailing party seeks to force the losing party to appeal before all claims are final. Patriot has no claims remaining and is not the party seeking immediate appeal through a Rule 54(b) motion. Thus, it is difficult for the Court to conclude that Patriot will suffer hardship or injustice because of a delay in having its appeal heard. Patriot's opposition to the motion and its willingness to wait suggests otherwise.
Further, it cannot be said that Hartwig suffers hardship by trying its counterclaim before Patriot may appeal. Hartwig did not lose any of its claims through summary judgment and has nothing to appeal immediately. Hartwig's primary justification for seeking a Rule 54(b) certification is to potentially save the expense of a second trial that could result from reversal on appeal. Other jurisdictions have held that the possible saved expense of having one trial rather than two does not justify a Rule 54(b) certification.