JOHN W. LUNGSTRUM, District Judge.
This matter presently comes before the Court on plaintiff's motion for summary judgment on its claim for breach of contract (Doc. # 33). For the reasons set forth below, the Court
The following facts are undisputed. Plaintiff Missouri Highways and Transportation Commission brought this case on behalf of Buildex, Inc ("Buildex").
Buildex has brought claims against Western for breach of contract and quantum meruit. By those claims, Buildex seeks to recover the outstanding amount due, plus contractual interest, as well as additional interest and attorney fees pursuant to Missouri statute. Buildex also asserts a claim on the bond for the project issued by defendant Travelers Casualty and Surety Company of America ("Travelers"). Western has asserted various counterclaims against Buildex, including claims for breach of warranty based on the allegation that the aggregate did not meet specific gravity requirements.
Buildex seeks summary judgment against defendants on its contractual claim for the outstanding purchase price and for contractual interest.
Western does not dispute that it accepted the goods delivered by Buildex (the aggregate) and that it failed to pay $65,309.86 that was due on the purchase price. Under UCC § 607, "[t]he buyer must pay at the contract rate for any goods accepted." See Mo. Rev. Stat. § 400.2-607(1). Under UCC § 2-709, "[w]hen the buyer fails to pay the price as it becomes due the seller may recover . . . the price . . . of goods accepted." See id. § 400.2-709(1)(a). Thus, if a buyer accepts goods, it is ordinarily liable to the seller for the purchase price.
Buildex notes Western's explanation that it did not pay a portion of the purchase price because the aggregate did not conform to the requirements of the contract. Thus, Buildex has addressed Western's possible defense under UCC § 2-717, which provides as follows:
See id. § 400.2-717. Buildex argues, however, that Western did not satisfy the requirements of that provision because it did not provide notice to Buildex of any intention to deduct damages from the remaining outstanding purchase price before those amounts were due. Buildex thus argues that Western cannot rely on that defense, and that Buildex is therefore entitled to summary judgment on its claim for the purchase price.
The Court first addresses the scope of Buildex's motion for summary judgment. In its motion and supporting brief, Buildex has requested summary judgment on its claim against Western for breach of contract and its claim against Travelers on the bond, but it has not requested summary judgment on any counterclaim asserted by Western. Nevertheless, Buildex suggests in its initial brief that, should it prevail on its motion for summary judgment, the only issue remaining for trial would be its entitlement to additional interest and fees pursuant to Missouri statute. In addition, in its reply brief, Buildex argues that Western's counterclaims for breach of warranty should be barred because Western did not pay the full purchase price. Buildex also argues in its reply brief that Western's other counterclaims are barred under the economic loss doctrine and because they restate Western's warranty claims.
The Court rejects any such arguments. As noted, Buildex moved for summary judgment only on its own claims, and the Court will not consider new arguments concerning the viability of the counterclaims raised for the first time in the reply brief. See, e.g., U.S. Fire Ins. Co. v. Bunge N. Am., Inc., 2008 WL 3077074, at *9 n.7 (D. Kan. Aug. 4, 2008) (citing Minshall v. McGraw Hill Broadcasting Co., 323 F.3d 1273, 1288 (10th Cir. 2003)).
Moreover, Buildex has not provided any authority to support the argument that Western may not pursue its counterclaim under the UCC if it may not rely on Section 2-717. To the contrary, UCC § 2-714 provides that as long as a buyer has given notice to the seller pursuant to Section 2-607(3), the buyer may recover damages for any nonconformity of accepted goods. See Mo. Rev. Stat. § 400.2-714(1). The comment to that section notes that Section 2-717 provides an additional remedy if part of the purchase price is still owed, which two remedies may be available concurrently. See id. cmt. 1. Indeed, even in one of the main cases on which Buildex relies, Quaker Alloy Casting Co. v. Gulfco Industries, Inc., 686 F.Supp. 1319 (N.D. Ill. 1988), the court permitted the defendant's warranty counterclaims to go forward (on the basis of existing questions of fact) despite granting partial summary judgment to the plaintiff seller for the remainder of the purchase price for accepted goods. See id. at 1344. Moreover, Section 2-717 does not contain any language suggesting that the buyer of accepted goods forfeits all rights to recover for a breach of warranty by failing to satisfy that provision's notice requirement; rather, the comment to that section states only that such a buyer must give the required notice if it wishes to avoid a default within the meaning of Section 2-609 regarding assurances. Accordingly, the Court denies Buildex's motion to the extent that Buildex seeks any relief or ruling relating to Western's counterclaims.
Buildex's motion for summary judgment rests on its argument that Western is not entitled to a deduction pursuant to UCC § 2-717 because it provided notice to Buildex of its intention to deduct damages for breach only after the payments were due. In its brief, Western does not address whether its notice was timely under Section 2-717.
With respect to Buildex's claim for the purchase price, the timing of a ruling on Buildex's claim for the outstanding balance is fairly irrelevant—whether it receives that ruling now or at trial, and whether or not Western may assert a defense pursuant to Section 2-717, Buildex must await trial on Western's counterclaim to determine the net amount due between the parties. See ECHO, Inc. v. Whitson Co., Inc., 52 F.3d 702, 704 (7th Cir. 1995).
IT IS THEREFORE ORDERED BY THE COURT THAT plaintiff's motion for summary judgment (Doc. # 33) is
IT IS SO ORDERED.