Summary: SECOND AMENDED PATENT SCHEDULING ORDER JAMES P. O'HARA , Magistrate Judge . The parties have filed a stipulated motion (ECF No. 68) to extend claim construction deadlines in the first amended patent scheduling order entered on January 23, 2019 (ECF No. 57). For good cause shown, the motion is granted, and the patent scheduling order is further amended as follows: SUMMARY OF DEADLINES AND SETTINGS Event Deadline/Setting Exchange of Preliminary Claim C
More

SECOND AMENDED PATENT SCHEDULING ORDER

The parties have filed a stipulated motion (ECF No. 68) to extend claim construction deadlines in the first amended patent scheduling order entered on January 23, 2019 (ECF No. 57). For good cause shown, the motion is granted, and the patent scheduling order is further amended as follows:

SUMMARY OF DEADLINES AND SETTINGS Event Deadline/Setting Exchange of Preliminary Claim Constructions and 3/29/2019 Extrinsic Evidence File Joint Claim Construction Statement 4/19/2019 Deadline for completing mediation 5/17/2019 Completion of claim construction discovery 5/17/2019 Service of opening claim construction brief 5/31/2019 Service of responsive claim construction brief 6/28/2019 Service of reply claim construction brief 7/12/2019

All other deadlines set in the initial patent scheduling order remain unchanged. The deadlines set in this second amended patent scheduling order will not be modified except by leave of court upon a showing of good cause.