ACREE, CHIEF JUDGE.
The appellants, Fidelity & Deposit Company of Maryland and Zurich American Insurance Company of Baltimore (collectively, the Surety), and Elmo Greer & Sons, LLC, appeal from an order of the Laurel Circuit Court granting summary judgment in favor of Construction Machinery Company, LLC. For the following reasons, we affirm in part, reverse in part, and remand.
Haydon Brothers Contracting, Inc., a heavy equipment highway contractor, subcontracted with Elmo Greer & Sons to build a road in Pike County, Kentucky (the Project). The Kentucky Department of Transportation (KDOT) funded the project. On December 23, 2008, Elmo Greer & Sons, as principal, and the Surety, entered into a payment bond in favor of the KDOT wherein they obligated themselves to pay "each and every person, firm or corporation who may furnish labor, materials or supplies for use on the [P]roject."
Haydon Brothers began work on the Project in August 2009. Haydon Brothers rented a drill from Construction Machinery to be used on the Project. During Haydon Brothers' use, Construction Machinery performed repair work on the drill. It is undisputed that Haydon Brothers stopped working on the Project on August 18, 2010.
Haydon Brothers allegedly did not pay for the drill rental or the repair work. On October 14, 2010, Construction Machinery submitted a claim of $44,118.34 on the payment bond to the appellants. In its notice, Construction Machinery declared the drill was last used on the Project on August 17, 2010. To support its claim, Construction Machinery attached invoices to its notice.
By letter dated December 22, 2010, the Surety acknowledged receipt of Construction Machinery's $44,118.34 claim, but declared it had "questions regarding the claim documentation" submitted by Construction Machinery. First, the Surety stated it was unsure whether Construction Machinery's claim was timely because the payment bond required claims to be filed within 90 days of the last performance. Although Construction Machinery's October letter stated it supplied labor or materials on August 17, 2010, the last invoice was dated June 8, 2010. Additionally, the Surety noted that Construction Machinery requested payment for repair services and that the payment bond did not cover repair work. Finally, the Surety noted Construction Machinery's invoices did not reference the Project. The Surety requested additional documentation to establish both the claim's timeliness and proof that the drill was used on the bonded job.
In response, Construction Machinery sent the appellants a letter dated January 24, 2011, and an affidavit signed by John Haydon, the President of Haydon Brothers. In the letter, Construction Machinery stated that:
In his affidavit, Haydon stated:
Based on the invoices attached to Haydon's affidavit, Construction Machinery made a claim for $86,706.85, which was $42,588.51 more than it originally requested.
By letter dated February 4, 2011, the Surety again disputed Construction Machinery's claim. As to the rental of the drill, the letter stated that the invoices were not sufficient because they did not reference the Project. As to the claim for repairs, the letter stated that the payment bond did not cover such costs.
On March 11, 2011, Construction Machinery sued the appellants and Haydon Brothers
The parties took Haydon's deposition. Haydon testified that Haydon Brothers entered into a rental equipment agreement with Construction Machinery for the rental of a drill to use on the Project. While working on the Project, the drill broke a few times and Haydon Brothers hired Construction Machinery to fix it. Haydon further acknowledged that all twelve of Construction Machinery's invoices attached to his affidavit were for the Project because that is where the drill was located. Haydon Brothers had no other rental equipment from Construction Machinery at any other worksite during the time period covered by the invoices.
Thereafter, Construction Machinery moved for summary judgment. After a hearing, the Laurel Circuit Court entered an order and amended order granting summary judgment in favor of Construction Machinery against the appellants and Haydon Brothers, jointly and severally, for the entire claim plus prejudgment interest and court costs, resulting in a judgment of $95,154.81.
This appeal followed. Additional facts are set forth below.
As set forth in Hammons v. Hammons, 327 S.W.3d 444 (Ky. 2010):
Id. at 448 (citations omitted).
The appellants first contend that the trial court erred in granting summary judgment because Construction Machinery's payment bond claim was not timely. The relevant provisions of the payment bond are as follows:
The appellants assert that, because Construction Machinery submitted a claim in a letter dated October 14, 2010, any claim related to an invoice dated prior to July 14, 2010, is barred by the 90-day period. Additionally, the appellants note that the last day Haydon Brothers worked on the project was August 18, 2010; therefore, they contend that any invoice offered in support of Construction Machinery's claim had to be dated prior to August 18, 2010. We disagree.
The express terms of the payment bond clearly state that "[a]ll claims for non-payment must be made within 90 days
However, we agree that Construction Machinery only submitted a claim for $44,118.34 within the 90-day period. As set forth above, not until the January 24, 2011 letter did Construction Machinery assert a claim for $86,706.85, which was substantially more than the original amount sought. The January 2011 letter fell outside the 90-day window. Therefore, we conclude Construction Machinery is entitled to no more than $44,118.34, exclusive of interest and costs assessed.
Next, the appellants contend there is a genuine issue of material fact whether the invoices are for the rental and repair of a drill used on the Project, thereby precluding summary judgment. Notably, appellants argue, Construction Machinery provided no supporting documentation for its claim other than its own invoices that fail to reference the Project, Haydon's affidavit, and Haydon's deposition.
In Steelvest, Inc. v. Scansteel Service Center, Inc., 807 S.W.2d 476 (Ky. 1991), our Supreme Court stated that, "a party opposing a properly supported summary judgment motion cannot defeat it without presenting at least some affirmative evidence showing that there is a genuine issue of material fact for trial." Id. at 482. The appellants failed to carry their burden.
Here, Construction Machinery submitted invoices, coupled with Haydon's affidavit and deposition testimony, substantiating their claim for compensation under the payment bond. The appellants failed to present any evidence contradicting Construction Machinery's and Haydon's representations that the invoices submitted by Construction Machinery were for the rental and repair of the drill for the Project. Instead, the appellants argue we should disregard Haydon's affidavit and deposition testimony because they are self-serving. Further, the appellants argue they asked for a copy of the equipment rental agreement between Haydon Brothers and Construction Machinery at Haydon's deposition, but never received it.
The appellants concede they made no requests for production of documents, and they took no depositions. This case was litigated for almost a year before summary judgment was granted. The appellants had ample opportunity to take any depositions or conduct any other form of discovery they might have wished to respond substantively to the motion for summary judgment.
Because the appellants failed to present some affirmative evidence to the contrary, we cannot say there is a genuine issue of material fact that the invoices submitted by Construction Machinery were for the rental and repair of the drill for the Project.
We affirm in part the trial court's conclusion that Construction Machinery is entitled to its claim of $44,118.34 on the payment bond. However, we reverse the trial court's conclusion that Construction Machinery is entitled to the additional $42,588.51 submitted after the 90-day claim period had expired. Therefore, we remand for the trial court to enter a new judgment in favor of Construction Machinery for $44,118.34 plus prejudgment interest and court costs.
ALL CONCUR.