JERRY A. BROWN, Bankruptcy Judge.
This matter came before the court on the plaintiff/debtor, Factory Sales & Engineering, Inc.'s ("FSE") Emergency Motion for Temporary Restraining Order (P-2), and the objections thereto filed by Electrica Nueva Energia S.A. ("ENESA") and JP Morgan Chase Bank, N.A. ("Chase"). An order was entered on August 21, 2017 granting a temporary restraining order (P-5), and a hearing was held on August 25, 2017. At the hearing, the court determined that it needed more time to study the matter, and entered an order continuing the temporary restraining order until September 8, 2017 (P-10). On September 8, 2017, the court entered an order granting a preliminary injunction, but stated that it would write an opinion stating the reasons for that order. For the reasons set forth below, the court grants the preliminary injunction prohibiting ENESA from drawing on the letter of credit and will enter a final order in conjunction with this memorandum opinion.
This dispute centers on whether ENESA is entitled to draw on a letter of credit applied for by FSE and issued by Chase for the benefit of ENESA. FSE and ENESA entered into an Agreement for Purchase and Sale of Equipment ("ENESA contract") dated August 10, 2015, that was for the construction of a facility in Santiago, Chile to produce energy by burning eucalyptus bark in a piece of equipment called a Bubbling Fluidized Bed Boiler. For the 20% down payment on the contract in the amount of $1,526,000, FSE was required to provide a letter of credit to ENESA. Chase issued the letter with the following terms:
"Factory Sales and Engineering, Inc., d/b/a FSE Energy has:
On June 6, 2017, an involuntary Chapter 7 petition was filed against FSE. On July 10, 2017 FSE filed a motion to convert the case to a Chapter 11 proceeding, and the court entered the order for relief on July 17, 2017. On that date the automatic stay issued which prohibited any actions against the debtor or property of the estate. After the order for relief was entered, FSE moved to obtain post-petition DIP financing for the express purpose of completing the work on the ENESA contract. The court approved the DIP financing in an interim order dated July 26, 2017, a second interim order dated August 7, 2017, and a final order dated September 6, 2017.
August 17, 2017, almost one month after the automatic stay took effect, ENESA sent a letter dated August 16, 2017 via email to FSE stating that ENESA was terminating the August 10, 2015 contract for cause. Also on August 16, 2017 ENESA presented a request to draw on the letter of credit to Chase. FSE then filed its motion for a temporary injunction seeking to prevent Chase from making payment to ENESA.
The contract between the parties contains a section entitled Article XV: Termination of the Agreement. Article XV requires that ENESA give 60 days notice in writing to FSE before it could terminate the contract. ENESA does not contend that it gave any written notice to FSE prior to the August 16 letter that it emailed on August 17, 2017. ENESA presented its draw request to Chase on August 16, before it had even sent the letter to FSE. ENESA, both in its memorandum and at oral argument, argued at length that FSE had failed to meet its obligations under the contract. ENESA presented at the hearing on the motion for preliminary injunction an affidavit from its Chief Executive Officer, Jose Bertran.
In his affidavit, Mr. Bertran states that FSE should have been finished with the project in April and discusses the problems the project had encountered; however, as of June 14, ENESA was still requesting that FSE continue to work on and make functional the boiler. ENESA does not contend that the June 14, 2017 letter constituted a notice of termination. The court understands ENESA's problem with the debtor's performance, but the contract appears to have been drafted by ENESA, and Article XV states that a written notice must be given 60 days prior to termination. It is clear that the August 16, 2017 letter ENESA sent to FSE purporting to terminate the contact does not comply with the 60 day written notice requirements of Article XV of ENESA's contract.
A major problem with ENESA's attempt to terminate the contract stems from the fact that the order for relief was entered in the FSE involuntary proceeding on July 17, 2017, one month before ENESA attempted to terminate the contract. This brought section 362(a)(3) of the Bankruptcy Code into effect. Section 362(a)(3) stays any act to obtain possession of property of the estate or of property from the estate or to exercise control over property of the estate. Executory contracts and leases are property of the bankruptcy estate. "As property of the estate, the debtor's interests in such contracts or leases are protected against termination or other interference that would have the effect of removing or hindering the debtor's rights in violation of section 362(a)(3)."
Both ENESA and Chase argue strenuously that the automatic stay does not apply to the letter of credit because neither the letter of credit nor its proceeds are "property" of the debtor or the debtor's estate.
This does not mean that ENESA had no rights in the bankruptcy case to seek relief. ENESA could have filed a motion for relief from the stay to terminate the contract. Additionally, relief for the non-debtor party to a contract can be found under section 365, which permits the other party to an executory contract with the debtor to move for an order requiring the debtor to assume or reject the contract. In the case before the court, FSE filed a motion on August 29, 2017 to assume the ENESA contract, and a hearing is set on that matter before the end of this month. Assumption of the contract will require the debtor to cure defaults as a condition of assuming the contract.
The debtor argues that the automatic stay precludes any attempt by ENESA to terminate the contract without first making application to the bankruptcy court for relief from the stay, citing In re Mirant Corp., 440 F.3d 238 (5
ENESA relies on Louisiana Revised Statute 10:5-109 which states that an issuer may only dishonor a facially valid presentation if a "required document is forged or materially fraudulent or honor of the presentation would facilitate a material fraud by the beneficiary on the issuer or the applicant." ENESA argues that this provision does not apply in this situation. The court disagrees.
In Itek Corp. v. First Nat. Bank of Boston, 730 F.2d 19 (1
The Itek court goes on to note that there is an exception to the rule that payment on letters of credit should not be enjoined, and that is the exception codified in both the Uniform Commercial Code and the Louisiana Revised Statute at issue here:
ENESA argues that it bargained for the benefit of being able to call the letter of credit in the event that FSE failed to perform under the contract, and that by enjoining payment of the letter of credit, the court is running afoul of the purpose of and the law governing letters of credit.
Here, the court finds that ENESA committed material fraud in the presentment of the letter of credit. The third condition in the presentment requirement to draw on the letter requires ENESA to certify that pursuant to Article XV of the contract ENESA has terminated for cause the right of FSE to continue its performance under the contact such that ENESA is entitled to draw under the letter of credit (emphasis added). Article XV of the contract states the following: "The PURCHASER will be entitled to terminate this Agreement unilaterally at any time, by written notice given to the SUPPLIER at least sixty (60) days prior to the termination date."
ENESA has neither given written 60 day notice pursuant to Article XV of the contract nor does it contend that it has. Additionally, as the court has found, ENESA has not actually terminated the contract and could not do so without seeking relief from the automatic stay that became effective July 17, 2017. As such, its statement that:
is simply not true and is a material misrepresentation. Because the parties negotiated that the demand for payment under the letter of credit require this specific language about the termination of the contract, it follows that the contact must actually be terminated to demand the payment. The parties could have agreed to put any demand language they wanted in the letter of credit. The first paragraph requires that ENESA certify that FSE is in material default of the contract. The parties certainly could have left it at that. Or the parties could have made the payment of the letter conditioned on a simple written demand, as was the case in Itek. But the parties chose a different approach; they chose to provide that ENESA was required to state the contract had been terminated pursuant to Article XV of the contract, and it is simply not true at this time, or when the request for payment was made, that the contract has been terminated, whether pursuant to Article XV or otherwise.
The court emphasizes that this decision on the preliminary injunction does not determine whether FSE's performance under the contract was unsatisfactory; that is a matter for the court to decide at a later time. The court is enjoining payment on the letter of credit because one of the three conditions that the parties bargained for and agreed upon when the letter of credit was issued was clearly not fulfilled before the call for payment on the letter of credit was made.
ENESA also reminds the court that the purpose of a preliminary injunction is to preserve the status quo and avoid injury to litigants until disputes can be resolved in an appropriate forum. It argues that in essence this is a dispute about money, and if the court finds that ENESA owes the money to FSE at a later date, then the court can order that the money be paid to FSE. The court disagrees with that argument. If the temporary restraining order and the preliminary injunction had not issued, the status quo would have been altered drastically as payment of the letter of credit to the beneficiary ENESA would have thwarted FSE's chance of reorganization at almost the very outset. It would also have prevented a determination of whether FSE had a right to assume the basic contract between the parties, which assumption would require a cure to the defaults that ENESA claims FSE committed.
The court's analysis in this case considers many factors, including the purpose of the Bankruptcy Code in a Chapter 11 reorganization case. The court entered an order for relief allowing FSE the opportunity to reorganize. FSE has a qualified lender willing to loan it money in order to allow it to finish the ENESA project. The court has approved that financing. FSE has filed a motion to assume the ENESA contract, and that matter is set for hearing later this month on October 30. The order for relief was entered only one month before ENESA attempted to terminate the contract, and this case has been pending for a relatively short time. If, after hearing evidence on the motion to assume the contact, the court allows FSE to assume the contract, then ENESA should have the working boiler that it contracted for, and the court will determine what damages it may be entitled to for any delays caused by FSE. If the court finds that the defaults by FSE cannot be cured, the court will revisit the issue of whether the contract may be terminated by ENESA. If the court allows the contract to be terminated, then ENESA will be able to truthfully represent to the bank that it is entitled to payment on the letter of credit. Either way, the court has every intention of reaching a quick resolution in this matter.
The court finds that ENESA did not terminate the contract before the automatic stay issued, which prevented termination without relief from the stay. The attempted termination violated the stay and there was a material fraud by ENESA in presenting the letter of credit for payment before the proper termination of the contract between ENESA and FSE. For those reasons the temporary restraining order and the preliminary injunction were proper and necessary. Accordingly the court grants the motion for preliminary injunction. A separate order will be entered.