SHELLY D. DICK, District Judge.
Before the Court is Third Party Defendant's, Command Construction Industries, LLC ("Command"), Motion in Limine Re: Evidentiary Issues Governed by Contract.
This case originates from a construction contract dispute. Movant, Command, was the general contractor on a state road project in Ascension Parish. By subcontract, dated April 22, 2013, Command engaged Sun as a sub-contractor to install signalization and electrical work in connection with the road project. Work commenced in the summer of 2013. The Parties have divergent views of the facts. Sun claims non-payment of sums due under the sub-contract which prompted Sun to "reduce forces" on the project, which Command characterizes as "walking-off" the job. The scope of work was expanded by DOTD which required change orders and additional long lead time materials be ordered for the project. Command argues the project delays stem from Sun's "walking-off" of the job and on its failure to timely order the long lead time materials. Sun, in turn, claims Command is responsible for project delays owing to non-payment, "failure to provide a time schedule," and "failure to properly supervise."
All pretrial deadlines have passed and this matter is scheduled for jury trial on Monday, March 27, 2017. Command now moves for an in limine order excluding the following evidence at trial:
Each point will be addressed by the Court seriatim.
It is axiomatic, and uncontested by the Parties, that the contract is the law between the parties. Contract interpretation is a question of law for the Court. Absent ambiguity or absurd consequences, a contact is to be interpreted by the Court according to its plain language. At the outset, the Court observes that, by way of this Motion in Limine, Command seeks to dispose of Sun's claims and its defenses to Command's Counter-Claim in their entirety. Because the dispositive motion deadline has passed, the Court will not entertain this evidentiary Motion as an end-run around the dispositive motion deadlines or as a substitute for a Rule 56 Motion.
Sun claims breach of contract which resulted in labor cost damages. Command argues that the contract precludes recovery of these damages, mandating that evidence of same be excluded.
Command advances Articles 1.2 and 14.4 of the sub-contract in support of its contention that these labor cost damages are not recoverable by Sun as a matter of contract. The relevant portion of Article 1.2 of the sub-contract provides:
Command argues that, under this provision, Sun's relief is limited to "justifiable time extensions," not monetary damages. Without addressing this contention, Sun responds that its labor cost damages are directly attributable to "Command's acts or failures to act."
Article 14.4 provides:
Command submits that, per this provision of the subcontract, "the only amount Sun can claim is the actual amount that DOTD paid Command for Sun's work."
Sun contends that, owing to contractual breaches by Command and the resultant injuries, it is entitled to claim and recover, if proven, labor cost damages attributable to the alleged breach.
The subcontract in this case called for Sun to be remunerated for its work on a unit price basis.
Sun does not assert contractual ambiguity on this point, and the Court finds none. The contract limits Command's liability to "the granting of justifiable time extensions."
Accordingly, Command's Motion in Limine to exclude evidence of labor cost increases and premium time labor costs is GRANTED and Sun's Exhibit numbers 18, 20, and 27 shall be excluded at the trial of this matter.
Command argues that "Sun never made a valid request for stored materials."
As aptly noted by Sun, "Command's argument regarding Sun's mobilization and demobilization claims against Command are substantially the same as Command's argument regarding Extended General Conditions and Premium Time [i.e. labor cost damages]."
Sun seeks recovery for damages to its finished work which occurred during the pendency of the project and for which Sun incurred uncompensated repair costs. Command argues that Article 6 of the subcontract places the sole of risk of loss with Sun. Accordingly, Command moves for exclusion of evidence of Sun's repair cost damages. The Court finds that, on this point, the contract is unclear. Therefore, Command's Motion in Limine to exclude evidence of Sun's repair cost damages is DENIED.
Sun seeks payment for the costs of temporary signalization it installed pending project completion. Pointing to the "Scope of Work" and unit price remuneration specified in the subcontract, Command moves for exclusion of evidence of these costs. Command does not argue that the temporary signalization was not ordered by the Owner, and in turn by Command. Command instead argues that no "written Change Order" was executed and, thus, moves to exclude evidence of Sun's request for a Change Order. The Court finds Sun's arguments on this point persuasive and Command's Motion in Limine is DENIED on this issue.
Under the guise of a Motion in Limine, Command moves to prohibit Sun from defending Command's counter-claim for breach of contract. Citing to Article 22.4 of the sub-contract, Command argues that its determination of Sun's alleged default is conclusive proof of same. Command moves to prohibit Sun from defending Command's default determination.
A motion in limine is not a substitute for a dispositive motion. "[A] motion in limine cannot be a substitute for a motion for summary judgment, a motion to dismiss, or a motion for directed verdict."
For the reasons articulated above, Command's Motion in Limine for penalties and attorney's fees is DENIED because it is an untimely motion for summary judgment.
Accordingly, Command's Motion in Limine
Command's Motion in Limine
On all other points and remaining matters, Command's Motion in Limine