JAMES T. TRIMBLE, Jr., District Judge.
Pursuant to "Golden Nugget's Motion to Partially Dismiss Yates' Counterclaim" (R. #9), Plaintiff/Counterclaim defendant, Golden Nugget Lake Charles, LLC, f/k/a Ameristar Casino Lake Charles, LLC, f/k/a Creative Casinos of Louisiana, LLC ("Golden Nugget" or "Plaintiff") moves to dismiss the counterclaim
Yates entered into a construction contract with Creative Casinos Louisiana, LLC, for the construction of a casino resort, hotel and spa, which development was to be known as Mojito Pointe. Yates was the General Contractor for the project and Creative Casinos Louisiana, LLC was the Owner of improvements to be constructed on property on which it held a long term leasehold interest. On October 3, 2012, Ameristar purchased the ownership interest in Creative Casinos Louisiana, LLC. Pinnacle then purchased Ameristar and the Golden Nugget and/or a related company named as defendant became the Owner for purposes of the construction contract on or about November 20, 2013. The contract originally had a Guaranteed Maximum Price ("GMP") of $265,826,992, but was revised and increased to $437,776,573.
The Golden Nugget is an approximately $700 Million luxury five-star resort located in Lake Charles, Louisiana; it first opened to the public in December 2014. The instant litigation involves a series of disputes between the owner (Golden Nugget) and the General Contractor (Yates). Specifically, the complaint alleges that Yates overbilled the Owner, failed to correct work that did not conform to the high quality standards agreed upon in the construction contract, and failed to be provide the appropriate records and/or documentation to support payment applications. The Golden Nugget is currently withholding approximately $18.7 Million (2.5% of the overall project value) allegedly to protect itself against estimated potential damages.
The Golden Nugget filed the instant litigation asserting the following claims against Yates; (1) breach of contract, (2) breach of warranty, (3) negligence, (4) negligent misrepresentation, (5) negligent suppression, and (6) declaratory judgment. Yates alleges that the Golden Nugget is scheming with the subcontractors to give large discounts in exchange for immediate payments rather than face the possibility of a lengthy legal proceeding in order to obtain payment.
In its answer and counterclaim, Yates denies all allegations and asserts that the Golden Nugget is wrongfully withholding money from Yates and its subcontractors. Yates avers that the Golden Nugget has not acted in good faith, has withheld payments for work performed, has not adequately cooperated in scheduling availabilities of rooms or building areas for corrective work, and has caused or contributed to delays in completing punch list items and corrective work.
In its answer, Yates asserts that it was filing a statement of lien and privilege pursuant to Louisiana Revised Statute 9:4801 et seq. to secure payment for the price of its work, including a lien and privilege on the leasehold interest and improvements owned by the Golden Nugget. Yates further seeks recognition of the lien and privilege by this court. It is this assertion that causes the Golden Nugget to bring the instant motion to partially dismiss. The Golden Nugget maintains that the statement of lien and privilege was filed untimely; the Golden Nugget seeks to have the court dismiss Yates' claim for recognition of the lien.
Fed. R. Civ. P. 8(a)(2) requires that pleadings which state one or more claims for relief must contain ". . . a short and plain statement of the claim showing that the pleader is entitled to relief. . ." This "notice pleading" requirement is balanced against Fed. R. Civ. P. 12(b)(6), which provides that a court may dismiss one or more claims when the pleader fails to state a claim upon which relief may be granted.
For the purpose of considering a motion to dismiss pursuant to Rule 12(b)(6), the court must take all well-pled factual allegations as true and must view them in the light most favorable to the plaintiff.
The court's analysis is restricted to the pleading at issue, its proper attachments and matters of public record.
The Golden Nugget maintains that because the Statement of Claim and Privilege was not timely filed, it should not be recognized by the court. Yates was the General Contractor on the building project for the Golden Nugget. On July 20, 2012, before Yates began its work on the project, a written Notice of Contract was filed pursuant to Louisiana Revised Statute 9:4831.
The Louisiana Private Works Act ("LPWA") requires general contractors to record a statement of claim or privilege (a "Lien") in the mortgage records of the parish in which the work was performed "within sixty days after the filing of the notice of termination or substantial completion of the work."
The Golden Nugget maintains that Yates must have properly filed a statement of claim or privilege by early February 2015 to timely preserve it. Thus, because Yates filed the statement of claim or privilege on December 23, 2015, over a year after the property was occupied, it was substantially more than 60 days after substantial completion and therefore untimely. The Golden Nugget maintains that Yates' right to a claim and privilege has been extinguished.
Yates acknowledges that a Certificate of Substantial Completion was executed on December 1, 2014 by Yates, the Golden Nugget and the Project architect. However, Yates complains that the Certificate of Substantial Completion has not been recorded in the mortgage records for the Parish of Calcasieu, as set forth in La. R.S. 9:4822(E). Likewise, the Golden Nugget has not filed a notice of termination of the Project work as set forth in Louisiana Revised Statute 9:4822(E).
The LPWA regulates the rights and responsibilities of persons involved in the construction and improvements of an immovable.
Yates relies in part on Louisiana Revised Statute 9:4811(D) as to the requirement of timely filing of a notice of contract as follows:
Yates remarks that it is undisputed that the Notice of Contract was timely filed in accordance with Louisiana Revised Statute 9:4804. Yates then relies on Louisiana Revised Statute 9:4811(D) which sets forth the procedure for a general contractor to preserve the privilege granted by Louisiana Revised Statute 9:4801.
Accordingly, Yates argues that the Notice of Contract must be timely filed after which the general contractor must file a statement of privilege within sixty (60) days after the filing of the notice of termination or substantial completion of the work. Yates asserts that the Golden Nugget incorrectly alleges that Yates failed to fulfill the second requirement of timely filling the Lien.
Yates remarks that the Golden Nugget failed to file either a notice of termination or a certification of substantial completion as contemplated by Louisiana Revised Statute 9:4822(B). Thus, because the Golden Nugget failed to file either the notice of termination or a certificate of substantial completion, the time period for which Yates must filed its statement of claim never started to run. Yates informs the court that the Louisiana states courts and the federal Fifth Circuit Court of Appeals, in considering the filing requirement procedure in Louisiana Revised Statute 9:4822, has concluded that if the notice of contract is filed, but the notice of termination or certificate of substantial completion is not filed or is deficient, the time periods for claimants to file their statements of privilege do not start to run. Yates further relies on the First Circuit Court of Appeal ruling in
The court of appeal reasoned that because the contract/notice of termination procedure provides an owner with a method for cutting off the valid assertion of potential claims or privileges, and the statutes requires an affirmative action be taken by the owner, when the owners fails or neglects to take such affirmative action, he should be made to bear the consequences of his failure to file a notice of termination, not the claimant. Thus, because Louisiana Revised Statute 9:4822(A) clearly places the onus on the owner to file a notice of termination when a notice of contract has been filed, the 30-day period is the applicable time period for filing a statement of claims and privileges when a notice of contract has been filed.
The Golden Nugget argues that Louisiana Revised Statute 9:4822 (A) and (C)
The Golden Nugget comments that the
The Golden Nugget challenges Yates' reliance on
The court agrees with the Golden Nugget that there is no filing requirement of a certificate of substantial completion. If a notice of termination is not filed, then the 60 day filing period commences upon the substantial completion of the work, which in this matter is undisputedly December 1, 2014. We must therefore conclude that Yates' December 23, 2015 filing of the Statement of Claim and Privilege Under Private Works Act" is untimely.
For the reasons set forth above, the motion for partial dismissal will be granted dismissing with prejudice Yates' claim for a statutory lien.