SULLIVAN, J.
This is an appeal pursuant to the Administrative Procedures Act, G. L. c. 30A, § 14, from a decision of the Department of Environmental Protection (DEP) authorizing the construction of a 350 megawatt power plant (the plant) near the
Background. Brockton Power proposes to build the project partially within 100 feet of vegetated wetlands bordering the Salisbury Plain River, a protected wetland area. The plant would not take water directly from the river. Rather, the plant's cooling towers are projected to use approximately 1.9 million gallons per day of treated effluent from the adjacent Brockton Water facility — water that would otherwise be discharged into the river under the terms of an existing NPDES/MA
Brockton Power is located at a distance from the wetlands, but a portion of the project would fall within the buffer zone. Brockton Power filed an NOI with the commission on June 27, 2008. The NOI contained a detailed discussion of the impact of the construction of the project on the wetlands and the buffer zone, as well as remediation measures. The NOI did not address the impact of the purchase of the water (and concomitant reduction in discharge) on water levels or the wetlands.
On July 12, 2007, Brockton Power applied to the Department of Public Utilities (DPU) for an exemption from Brockton's relevant zoning restrictions pursuant to G. L. c. 40A, § 3, but the commission deemed the application for exemption insufficient. On October 23, 2008, the commission denied Brockton Power's request for approval of the project, finding that (1) the NOI contained insufficient information because it did not describe the impact of the project's use of Brockton Water's treated effluent on the water levels of the Sudbury Plains River, and (2) Brockton Power had failed to apply for local zoning approvals as required by 310 Code Mass. Regs. § 10.05(4)(e)-(f) (2008).
In early November, 2008, Brockton Power appealed the commission's decision to the DEP Bureau of Resource Protection (DEP Bureau), requesting a superseding order of conditions. A
The commission appealed from the superseding order of conditions, and both the commission and Brockton Power filed motions for summary decision under DEP adjudicatory procedures. The DEP upheld the superseding order of conditions in a final order. The DEP found that Brockton Power did not have to include the purchase of water in its NOI, because it was the customer in that transaction and not the supplier, the latter being the party that was responsible for the discharge.
The Superior Court judge heard and decided the matter on the administrative record on a motion for judgment on the pleadings. See Mass.R.Civ.P. 12(c), 365 Mass. 754 (1974). The judge affirmed the final decision of the DEP in all respects, reasoning that the word "alter" in the WPA was intended to cover only that work which had a "direct" rather than an "indirect" impact on
Discussion. We review an order allowing a motion for judgment on the pleadings de novo. See Wheatley v. Massachusetts Insurers Insolvency Fund, 456 Mass. 594, 600 (2010).
1. "Work" and the WPA. Because the DEP has not decided whether Brockton Water has an obligation to file an NOI, and because there was no challenge to the determination that the wetlands issues may be resolved by monitoring the NPDES/Surface Water Discharge Permit, the issue before the Superior Court judge was whether Brockton Power's purchase of the water was "work" that required inclusion in the NOI. Our review is similarly limited to that issue.
The commission carries the "formidable burden" of showing that the agency's interpretation of its own rules is not rational. Northbridge v. Natick, 394 Mass. 70, 74 (1985), quoting from Greenleaf Fin. Co. v. Small Loans Regulatory Bd., 377 Mass. 282, 293 (1979). "[W]e review an agency's decision to determine whether it was not supported by substantial evidence, was arbitrary or capricious, or was otherwise based on an error of law." Ten Local Citizen Group v. New England Wind, LLC, 457 Mass. 222, 228 (2010).
Ibid.
The DEP determined that the purchase of treated wastewater
The DEP did not read the word "alter" out of the statute. Instead, the DEP focused on which actor it would regulate. Put another way, the DEP did not refuse to consider whether an alteration might occur but, instead, focused on who would be responsible and how to regulate that conduct. This interpretation of the WPA and the DEP's own regulations is not arbitrary, capricious, or otherwise based on an error of law.
The DEP is charged with the implementation of a complex, comprehensive, and interconnected statutory scheme. See G. L. c. 21, § 43; G. L. c. 131, § 40. The DEP regulations leave decision-making regarding the scope of the NOI in the buffer zone to the expertise of the DEP. See note 4, supra. Here, the DEP considered the possibility that the sale of water would result in an alteration of the wetland. The DEP determined that the sale of water likely would not constitute an alteration so long as Brockton Water complied with its discharge permit. If Brockton Water violated that permit, the DEP reasoned, regulation should be at the point of discharge (Brockton Water), not
The DEP's determination is fully consonant with the WPA's statutory purpose. The purpose of the WPA is to protect wetlands in order to provide benefits to the public. See Citizens for Responsible Envtl. Mgmt. v. Attleboro Mall, Inc., 400 Mass. 658, 669 (1987). The WPA is an "entirely `procedural'" statute, which achieves these goals by granting regulators the authority to condition certain activities on, among other things, the permitting process. Ibid. The DEP found that the enforcement of the NPDES/MA permitting process, see note 3, supra, was the primary mechanism for ensuring that the discharge levels were appropriate. This allocation of regulatory authority is based on the DEP's practical concern that the WPA should first regulate the persons who have primary control over the "work" at issue. "We will not substitute our judgment as to ... the propriety of the means chosen to implement the statutory goals, for that of the agency, so long as the regulation is rationally related to those goals." Entergy Nuclear Generation Co. v. Department of Envtl. Protection, 459 Mass. 319, 331 (2011), quoting from American Family Life Assur. Co. v. Commissioner of Ins., 388 Mass. 468, 477 (1983).
Contrary to the commission's argument, the DEP's decision to interpret its regulatory program in this way is fully consistent with the DEP's decisions. For example, in Matter of Penn, Mass. DEP No. 93-102 (October 13, 1998), the DEP determined that the act of closing a gate valve that controlled the flow of water from a pond constituted "work." It required the owner of the gate valve to file an NOI. Here, Brockton Water has its
2. The zoning exemption. General Laws c. 131, § 40, and 310 Code Mass. Regs. § 10.05(4)(e) (2008) require an applicant to apply for "all permits, variances and approvals required by local by-law with respect to the proposed activity" that are "feasible to obtain" prior to filing its NOI with the local conservation commission. However, G. L. c. 40A, § 3, provides that public service corporations may seek and obtain from the DPU exemptions from the zoning ordinance or by-law "reasonably necessary for the convenience or welfare of the public." Called upon to harmonize these two statutory directives, the DEP determined that, as a public utility, Brockton Power need only file for an exemption with the DPU prior to filing an NOI with the commission. This interpretation reconciles the two statutes and fulfils the statutory purpose of both. See New England Legal Foundation v. Boston, 423 Mass. 602, 606 (1996). This approach permits the DPU to act on the exemption request while the NOI proceeds at the local level, and at the same time avoids the unnecessary delay and expense that would be associated with an application for zoning permits for which an exemption may be granted. If the DPU does not grant the request, the public utility must then return to the local authorities.
The commission argues that allowing the filing of an NOI before a utility has sought all possible local zoning approvals effectively eliminates any role for local conservation commissions in the over-all approval process. This overstates the issue, which is in the first instance one of timing. That is, the exemption process goes forward at the DPU; the local conservation commission acts on the NOI. Moreover, the exemption process
Judgment affirmed.