RICHARD G. STEARNS, District Judge.
On December 15, 2016, the Massachusetts Water Resources Authority (MWRA) filed its (now) Biannual Compliance and Progress Report (the 240
There were no scheduled activities for the past sixth months on Schedule Seven.
The MWRA has begun preliminary work to implement the courtordered CSO post-construction monitoring program and performance assessment intended to confirm compliance with the long-term CSO control plan. The assessment will begin in January of 2018 and be completed in December of 2020 in compliance with Schedule Seven (if all transpires as anticipated).
The MWRA reports that the Massachusetts Department of Environmental Protection (DEP) has issued final determinations extending to August 31, 2019, the CSO variances to the Massachusetts Surface Water Quality Standards for the Lower Charles River and Basin and the Alewife Brook and Mystic River. These determinations build on previous determinations and approvals that have been in place since 2006. In planning for post-consent decree determinations, on MWRA submitted for the DEP's review a completed scope of work for a modified water quality monitoring program. The revised monitoring program will allow the measurement of CSO impacts over a range of storm events in a format consistent with the database the MWRA has maintained since it began sampling water quality in the affected water bodies in 1989.
The MWRA is coordinating power usage at Deer Island with the exploratory work of Eversource contractors looking to reposition the existing cross-harbor cable to accommodate the Army Corps of Engineers' planned channel-deepening project. As this is the subject of separate ongoing litigation before the court, I will reserve any comment.
Consistent with the court's revised Scheduling Order, the MWRA will submit Compliance Report No. 241 on or before June 15, 2017.
SO ORDERED.