WILLIAM M. NICKERSON, Senior District Judge.
This case arises out of a construction contract between Plaintiff Universal Contractors, Inc. (Universal) and Defendant Commercial Interiors, Inc. (Commercial). Defendant Commercial was the general contractor on a project to build a convenience store on the federal military base at Fort Meade, Maryland. Defendant Hartford Fire Insurance Company was the surety for the project. Universal entered a subcontract, dated January 31, 2013, to do the excavation work on the project which included, inter alia: clearing and grubbing the site; grading, stripping and re-spreading topsoil; demolishing light poles; installing a temporary fence; and backfilling. Also included in Universal's subcontract was the responsibility for sediment control during construction and the construction of a permanent storm water management facility.
Universal began work on the site in April, 2013 and its work was scheduled to have been completed by the end of September 2013. For reasons not explained in the record, Universal's portion of the project was not completed on time and Universal continued to work on the project into November 2013. On November 20, 2013, work was suspended due to winter weather. When work was suspended, Universal's remaining tasks were primarily those related to sediment control and construction of the permanent storm water management facility. In its November 2013 Pay Application, Universal indicated that there was about $56,000 of work remaining to be done on the original subcontract, as modified by approved change orders. ECF No. 24-2.
Beginning in March of 2014, Commercial made repeated requests of Universal to return to the site and complete the remaining work. While there were back and forth emails and letters exchanged between the parties, Universal did not return to the site to finish the work.
On October 29, 2014, Universal filed this Miller Act
Universal has now filed a motion for summary judgment seeking judgment in its favor in the amount of $32,408.83, which it claims was a "retainage" withheld under the subcontract. ECF No. 20 at 5. Universal also seeks summary judgment on Commercial's counterclaim, asserting that it did not breach the contract.
Commercial filed a cross motion for summary judgment asking the Court both to deny Universal's claim and to enter judgment in its favor in the amount of $32,605.71. As to the denial of Universal's motion, Commercial contends that, even should Universal be entitled to the "Retainage Held," the amount would be either $21,261.60 (citing a "Recap of Invoice Ft. Meade Express 5-21-14" produced by Universal in discovery, ECF No. 24-5) or possibly $22,433.52 (citing an Application and Certification for Payment which Universal submitted on November 11, 2013, with a retainage due in that amount, ECF No. 24-2).
Summary judgment is proper if there are no issues of material fact and the moving party is entitled to judgment as a matter of law.
Here, there are significant disputes of material fact that prevent the Court from entering summary judgment for either party. As to whether Universal was in breach of the subcontract, which is the central issue in Commercial's counterclaim, it appears that most of the Farrell revisions were neither adopted nor incorporated into the scope of the work and, thus, Commercial is correct that the scope of Universal's work was not changed in that regard. Nonetheless, the sequence of the work to be completed was changed and Universal maintains that this change in sequence added significant costs to its performance.
On the other hand, the current record would not appear to support Universal's claim to entitlement to the entire retainage held under the subcontract, even assuming the Parties now agree that the correct amount of the retainage is $21,736.79. Whether its refusal to return to the job was justified or not, Universal did not complete the work it contracted to do and Commercial incurred significant costs to have Diversified do it in Universal's stead. Furthermore, despite its concession that the retainage is significantly less than what was originally claimed, Universal continues to assert its entitlement to a judgment of $32,408.83, apparently based upon its supplement work performed in May of 2014. That assertion, however, lacks anything close to sufficient evidentiary support. The timesheets purport to show the number of hours worked by various employees, which the Court must simply assume are related to the Fort Meade project, but provide no hourly rate for any employee. The Court certainly could not enter judgment on Universal's behalf based upon this scant record.
Both motions will be denied. The Court will also schedule a telephone conference to set a date for the trial of this matter.
Accordingly, IT IS this 18th day of November, 2015, by the United States District Court for the District of Maryland, ORDERED:
(1) That Plaintiff Universal Contractors, Inc.'s Motion for Summary Judgment, ECF No. 20, is DENIED;
(2) That Defendant Commercial Interiors, Inc.'s Cross Motion for Summary Judgment, ECF No. 23, is DENIED;
(3) That a telephonic scheduling conference shall be held on Wednesday, December 2, 2015, at 10:00 a.m., to be initiated by counsel for Plaintiff; and
(4) That the Clerk of the Court shall transmit a copy of this Memorandum and Order to counsel of record.