MARILYN KELLY, J.
This case involves a dispute over a construction contract. At issue is whether the limitations period in MCL 600.5839(1) applies to an action for breach of contract. The Court of Appeals held that it does and that the statute's six-year limitations period expired before plaintiff filed its complaint, barring the suit. Accordingly, the Court of Appeals reversed the judgment of the trial court, which had awarded plaintiff damages for breach of contract, and remanded the case for entry of a judgment in favor of defendant.
Plaintiff alleges that the general statute of limitations for breach of contract actions, MCL 600.5807(8), controls its action and that it filed suit within six years of the date its action accrued. Defendant alleges that the contractor statute of repose, MCL 600.5839(1), controls plaintiff's action and that plaintiff filed it more than six years after the occupancy, use, or acceptance of the roof defendant built.
We agree with plaintiff that MCL 600.5839(1) does not apply to actions for breach of contract. MCL 600.5807(8) is the applicable statute. The limitations period in both statutes is six years. But unlike the period in MCL 600.5839(1), which runs from "the time of occupancy of the completed improvement, use, or acceptance of the improvement," the limitations period in MCL 600.5807(8) runs from the date the "claim first accrued...."
Accordingly, we reverse the judgment of the Court of Appeals. Because there is a question about the date plaintiff's action accrued, we remand the case to the Court of Appeals to resolve this issue, as well as other issues not yet considered.
Plaintiff, Miller-Davis Company, was the general contractor hired to improve and construct various buildings for the YMCA Camping and Retreat Services of Battle Creek and Kalamazoo. The project included construction of a natatorium. Plaintiff contracted with defendant Ahrens Construction, Inc., to install the natatorium's roof.
A temporary certificate of occupancy was issued for the entire project on June 11, 1999. The roof was installed before that date. Soon after its installation, the YMCA noticed excessive condensation in the natatorium, so severe at times that it appeared to be "raining" in the pool area. The parties refer to this condition as the "natatorium moisture problem" (NMP).
The temperature and air pressure in the pool were adjusted. Also, defendant performed corrective work on the roof. But the NMP continued into 2003, when plaintiff's architect recommended removing the roof as the only means to determine whether defendant's improper installation caused the NMP. The architect, who eventually testified as plaintiff's expert witness, opined that rips in and missing sections of
Defendant insisted that the NMP was the result of design defects rather than poor workmanship. After all defendant's efforts to correct the problem were unsuccessful, plaintiff declared a default. Plaintiff eventually performed the corrective work itself in the fall of 2003.
In May 2005, plaintiff sued defendant, alleging that it had breached its contract by installing a roof that did not conform to the plan's specifications. Plaintiff sought indemnification for the necessary corrective work. Its complaint did not allege that defendant's work created a defective and unsafe condition, that defendant caused the NMP, or that plaintiff's damages arose from a defective and unsafe condition. Nor did it refer to defendant's express one-year guarantee or allege a breach of warranty.
Defendant sought summary disposition under MCR 2.116(C)(7), claiming that plaintiff had filed suit after expiration of the six-year period specified in the statute of repose contained in MCL 600.5839(1). The trial court denied defendant's motion without addressing the applicability of MCL 600.5839(1).
The case proceeded to a bench trial. Plaintiff's theory was that defendant had constructed a defective roof and that the nature of the defect became apparent only when the roof was removed. It asserted that the NMP did not reappear after the roof was reconstructed. Defendant's defense was that design defects caused the NMP. For example, defendant claimed that the NMP arose because the roof's design allowed the vapor barrier to come into contact with cold outside air. Defendant's expert testified that once the defectively designed roof had been removed, the NMP was corrected because trapped moisture was allowed to escape. Alternatively, defendant argued that the alleged defects in the roof were caused when plaintiff removed it. In closing argument, defendant again raised the statute of repose.
The trial court ruled in favor of plaintiff. It determined that defendant was in material breach of its contract for having performed nonconforming and defective work on the roof, which required corrective measures. This resulted in damages of $348,851.50. On the indemnity claim, the court ruled in favor of defendant because no suits had been filed against plaintiff. Hence, no indemnification was required. The court did not address the statute of repose issue.
Defendant appealed as of right, raising the statute of repose, among other defenses. Plaintiff cross-appealed the denial of its indemnity claim. The Court of Appeals agreed with defendant on the statute-of-repose issue and reversed the judgment of the trial court.
We granted plaintiff's application for leave to appeal.
The issue in this case is whether the statute of repose contained in MCL 600.5839(1) or the statute of limitations contained in MCL 600.5807(8) applies to plaintiff's civil action. This case also involves the interpretation and application of MCL 600.5805. The issue presents a question of law that we review de novo.
MCL 600.5805 sets forth various periods of limitations for civil actions. It provides, in pertinent part:
MCL 600.5839 provides:
Plaintiff asserts that MCL 600.5839(1) does not apply to its action. Rather, it claims that the general statute of limitation for contract actions, MCL 600.5807(8), applies. It provides: "The period of limitations is 6 years for all other actions to recover damages or sums due for breach of contract."
In order to determine the scope of MCL 600.5839(1), we consider first the overall statutory scheme involving periods of limitations for tort and contract actions contained in the Revised Judicature Act.
Section 5805(1) requires that all actions for injury to persons or property be brought within the time periods set forth in the section. There follow 14 subsections, 12 of which clearly refer to various types of tort suits.
Subsection (14), through reference to MCL 600.5839, uses language similar to that found throughout the remainder of section 5805, referring to "injury to property" and "bodily injury."
In contrast to MCL 600.5805, the next section in the code, MCL 600.5807, sets forth the limitations periods for suits seeking damages for breaches of contract. Unlike MCL 600.5805, MCL 600.5807 contains no reference to MCL 600.5839. And no subsection of MCL 600.5807 refers to injuries to persons or property. Thus, MCL 600.5805 and MCL 600.5839 apply to tort actions, and MCL 600.5807 applies to contract actions.
The Michigan Supreme Court's decision 34 years ago in Huhtala v. Travelers Ins. Co.
Under Huhtala, if an action is founded on a "consensual" duty or obligation or the breach of an "express promise," the action is not for personal injury.
In distinguishing between tort actions and contract actions in the context of sections 5805 and 5807, Huhtala concluded that any "action to recover damages for injury to persons or property" is a tort action.
The United States Court of Appeals for the Sixth Circuit did apply the reasoning of Huhtala to MCL 600.5839(1) in Garden City Osteopathic Hosp. v. HBE Corp.,
In that case, a hospital contracted with a builder and an architect for the construction of a building addition. The hospital discovered a defect in the work and sued the builder and architect for breach of contract. The federal district court granted the defendants' motion for summary disposition. It found that MCL 600.5839(1) barred the hospital's claims.
The Sixth Circuit reversed that decision. It surveyed Michigan caselaw and found that the distinction outlined in Huhtala supplied the proper analysis for determining whether MCL 600.5839(1) applied to the hospital's breach of contract claim.
In arriving at this conclusion, it noted that the nature and origin of the claim was "that the defendants failed to perform the express promise to construct the improvement in conformity with the governing contract documents."
In this case, the Court of Appeals relied on Michigan Millers Mut. Ins. Co. v. West Detroit Bldg. Co.
Without supporting analysis, the Court of Appeals found it "clear" that the limitations period in MCL 600.5839(1) did not pertain solely to tort actions given that the statute used the language "`any action to recover damages for any injury to property....'"
Rather, the Court concluded that MCL 600.5839(1) applies "to all actions brought against contractors on the basis of an improvement to real property, including those brought by owners for damage to the improvement itself."
The Michigan Millers Court turned to the statute's legislative history in an attempt to substantiate its holding. However, the history on which it relied does not support expanding the scope of MCL 600.5839(1) beyond tort actions. It said only that "`[t]he bill would ensure that, in future claims against engineers, architects, and contractors, ... [they would] be protected from suits charging malpractice or negligence in building improvements....'"
By expanding the scope of MCL 600.5839 to contract actions, Michigan Millers blurred the critical distinction between third-party tort claims and contract claims between parties to an express contract. It expanded the applicability of the statute beyond any arguable legislative intent. Furthermore, its holding exceeded that necessary to resolve the issues involved. In sum, the Court of Appeals in this case relied on Michigan Millers for a proposition that is unsubstantiated. We overrule Michigan Millers and Travelers. Ins. Co. because they are inconsistent with § 5839.
In the 1980 case of O'Brien v. Hazelet & Erdal,
MCL 600.5839 was crafted in response to changes in tort law. A reference to it was placed in the general tort statute of limitations, MCL 600.5805. MCL 600.5839 also uses language—"injury to property" and "bodily injury or wrongful death"—that is generally associated with tort actions. The logical conclusion is that it was intended to apply to tort actions. However, no similar conclusion can be drawn with respect to its applicability to actions for breach of contract.
In 1986, in City of Marysville v. Pate, Hirn & Bogue, Inc.,
We agree that the language of the provision strongly supports the conclusion that MCL 600.5839 does not apply to a breach of contract claim for a defect in a building improvement. We conclude that the Legislature intended the provision to be limited to actions in tort. Thus, it does not apply to a claim against an engineer or contractor for a defect in an improvement when the nature and origin of the claim is the breach of a contract.
In this case, the complaint alleged two counts against the construction company: (1) breach of contract for installing a roof that did not conform to plan specifications and (2) indemnity for the corrective work plaintiff had to perform. Neither
There was no allegation that the roof deck system caused any "injury to property" or "bodily injury or wrongful death."
A claim for damages for deficiencies in an improvement is not an "action to recover damages for any injury to property . . . or for bodily injury or wrongful death. . . ."
MCL 600.5839(1) applies to actions for "injury to property" or "bodily injury or wrongful death," which are commonly viewed as tort actions. There is a reference to MCL 600.5839 in the statute of limitations covering tort actions, MCL 600.5805, but there is no similar reference to MCL 600.5839 in the statute of limitations covering contract actions, MCL 600.5807. Thus, the statutory language and the overall statutory scheme lead to the conclusion that MCL 600.5839 is limited to tort actions. This view is supported by Huhtala and Garden City Osteopathic Hosp. While Michigan Millers reached the opposite conclusion, it did so in dictum, and it misconstrued the legislative history. We overrule Michigan Millers and Travelers Ins. Co., which relied on it.
We hold that MCL 600.5839(1) is limited to tort actions. It does not apply to breach of contract actions. The Court of Appeals erred by concluding that plaintiff's contract action was barred by MCL 600.5839(1). Accordingly, we remand this case to the Court of Appeals for application of MCL 600.5807(8) and, if necessary, for consideration of the remaining issues raised in the appeal and cross-appeal.
ROBERT P. YOUNG, JR., MICHAEL F. CAVANAGH, STEPHEN J. MARKMAN, DIANE M. HATHAWAY, MARY BETH KELLY and BRIAN K. ZAHRA, JJ., concur.