MARK A. GOLDSMITH, District Judge.
This matter is before the Court on Defendant Morrison Management Specialists, Inc.'s motion for judgment on the pleadings (Dkt. 28). Plaintiff Watermark Senior Living Retirement Communities, Inc., brings this breach of contract action against Morrison for allegedly failing to exercise ordinary care in executing its obligations to manage the kitchen at one of Watermark's retirement communities, resulting in the death of one of its residents. Briefing on the motion is complete. Because oral argument will not aid the Court's decisional process, the motion will be decided based on the parties' briefing.
This action arises from the tragic death of Willie Mae Henderson. Henderson resided at Watermark's assisted-living community, The Fountains of Franklin. In 2012, Henderson wandered from her room in the memory care unit to the facility's kitchen, opened a cabinet door under a sink that contained toxic dishwashing detergent, and drank the toxic detergent, which resulted in her death. Compl. ¶¶ 5-7. At that time, Morrison was under contract to provide dietary services at the facility, which included managing and securing the kitchen facility.
Henderson's estate sued Watermark in state court, alleging that Watermark was negligent for leaving the cabinet door unlocked. Compl. ¶¶ 4-6. Watermark did not implead Morrison in the state court action. Instead, it defended the action alone. Countercl. ¶ 4 (Dkt. 25). The jury found against Watermark and awarded Henderson's estate $5.08 million.
Morrison filed a motion to dismiss this case, arguing that collateral estoppel barred the action (Dkt. 3). Judge O'Meara agreed with Morrison and granted the motion (Dkt. 17). Watermark appealed. The Sixth Circuit found that the indemnification claim was precluded, because it depended on Watermark showing that the damages it sought were not the result of its own negligence — a proposition it could not establish, as the state court jury had found to the contrary.
Morrison moved under Federal Rule of Civil Procedure 12(c) for judgment on the pleadings. Any party may move for the entry of a judgment after the pleadings are closed, but early enough not to delay trial. Fed. R. Civ. P. 12(c). Courts apply the same analysis to motions for a judgment on the pleadings under Rule 12(c) as is applied to applications for dismissal under Rule 12(b)(6).
When evaluating a motion for a judgment on the pleadings, a court considers the complaint, the answer, and any written instrument attached as exhibits. Fed. R. Civ. P. 12(c). A court may also consider any undisputed facts.
Morrison makes three arguments in support of its motion for judgment on the pleadings. First, it argues that Watermark sat on its rights for more than four years and, therefore, laches bars any recovery in this case. Second, it argues that Watermark fails to state a breach of contract claim because the damages it seeks do not naturally arise from a contract breach. Finally, Morrison argues that the Sixth Circuit has already found that Watermark was responsible for Henderson's death, which triggers Morrison's contractual right to indemnification. The Court will take each argument in turn.
Morrison argues that the doctrine of laches bars Watermark's breach of contract claim, because Watermark delayed bringing this action for more than four years. Mot. at 7. Laches is an affirmative defense that bars an action where there is an unexcused or unexplained delay in commencing the action resulting in prejudice to an opposing party. Pub.
There is an interplay between laches and the statute of limitations.
Here, Watermark filed its breach of contract claim against Morrison within the statute of limitations. Nonetheless, Morrison argues that laches should bar the claim because it is prejudiced by Watermark's decision to not implead it in the state case. Mot. at 10. It argues that the state jury could have allocated liability between Watermark and Morrison, but that opportunity is now lost.
Although Morrison's position may have materially changed because it may be subject to a multi-million-dollar exposure, its position may have improved in that the extent of its exposure may have been reduced by virtue of the settlement. In other words, Watermark's decision to delay suing Morrison may not have put Morrison in a worse position. However, the Court cannot make such a determination without some development of the record. Therefore, Morrison's motion with respect to laches is denied without prejudice.
Morrison makes two arguments in support of its argument that Watermark has failed to state a claim for breach of contract. First, it argues that the damages Watermark seeks, the $3.65 million settlement, are not available under Michigan law. Second, it argues that the settlement is not the type of damages that naturally arise from a contract breach. Mot. at 11. Watermark appears to argue that Michigan law does allow it to recover the settlement amount and expenses from Morrison and that such damages flow from the alleged breach. Resp. at 13-19. Watermark has the better part of the argument.
In Michigan, contract damages are limited to those damages "that arise naturally from the breach or those that were in the contemplation of the parties at the time the contract was made."
For example, consequential damages are sometimes available and "may include litigation or settlement costs from prior litigation with a third-party where those costs were occasioned by a breach of contract."
Morrison's first argument misses the mark. As noted above, Michigan courts allow the recovery of expenses, including settlements, from prior actions as damages in a subsequent breach of contract action. Morrison attempts to rely on a case that found otherwise, but such reliance is misplaced. Mot. at 12-13 (citing
Morrison's second argument that the settlement does not naturally arise from a contract breach is also unpersuasive. Morrison cites Restatement (Second) of Contracts § 351 (1981) for the proposition that "[l]oss may be foreseeable as a probable result of a breach because it follows from the breach . . . in the ordinary course of events. . . ." As noted above, this section also addresses when the recovery of litigation expenses, including settlements, by the party in breach are foreseeable. It offers the following example:
Illustration 10 to Restatement (Second) of Contracts § 351 (1981).
Morrison argues that the sequence of events that led to Watermark settling a $5.08 million judgment was not foreseeable when its contract with Watermark was made. But Morrison focuses too narrowly on how the specific events giving rise to this case unfolded, instead of the bigger picture that when a party does not take ordinary care to fulfil its contractual duties through negligence, for example, dire consequences are foreseeable.
Here, Watermark contracted with Morrison to provide food and kitchen services to a retirement community. Watermark alleges that Morrison breached the contract by not using ordinary care in complying with its contractual obligations to maintain the kitchen in a reasonably safe manner. Specifically, Morrison employees allegedly did not properly secure toxic chemicals. The mishandling of the toxic chemicals allowed Henderson to access and ingest the toxic chemicals resulting in her death. Henderson's estate sued Watermark in state court and the case eventually resulted in a settlement. Like a lawsuit arising from the delivery of defective machine parts, a lawsuit arising from the mishandling of toxic chemicals is foreseeable in the ordinary course of events.
Accordingly, a lawsuit resulting in a settlement was foreseeable at the time the parties entered into their agreement and the type of damages that naturally arise from a contract breach. Accordingly, the Court cannot say that as a matter of law that Morrison is clearly entitled to judgment based on the pleadings.
Finally, Morrison argues that the Sixth Circuit's ruling regarding Watermark's liability triggers Watermark's obligation to contractually indemnify Morrison. Mot. at 15. Morrison is mistaken.
The Sixth Circuit explained that Watermark's contractual-indemnification claim could not succeed because Morrison has no obligation to indemnify Watermark for its own negligence.
The Sixth Circuit's ruling does not, however, work in the other direction. The indemnification provision also requires Watermark to indemnify Morrison for any damages arising "solely" from Watermark's conduct. Agreement, Ex. A to Mot., at Art. 6.3(b). But neither the Sixth Circuit nor the state court jury found that Watermark was solely responsible for Henderson's death. The state court jury was not asked to determine whether Morrison had any level of responsibility in the matter. That issue is what is ultimately before this Court and it is not one that can be resolved on the pleadings.
Because Morrison is not clearly entitled to judgment, its motion for judgment on the pleadings (Dkt. 28) is denied.
SO ORDERED.