GRIFFIS, P.J., for the Court:
¶ 1. This case considers whether the circuit court was in error to dismiss Glen Avent's complaint against Entergy Mississippi, Inc. for failure to prosecute under
¶ 2. Avent was employed by Andy Bland Construction Company. On July 3, 1994, Avent was working at a construction site in Tunica County, Mississippi. He operated a man-lift that became stuck in wet sand. There was an effort to free the lift and pull it out of the sand. The lift came into contact with an overhead electrical line. As a result, Avent was injured.
¶ 3. Sheraton owned the property that was the construction work site. Sheraton contracted with W.G. Yates and Son Construction Co., as the general contractor. Entergy had installed the electrical line. Andy Bland was a subcontractor of Yates.
¶ 4. On November 8, 1996, Avent filed a lawsuit. The complaint named several defendants, including Mississippi Power & Light (now known as Entergy Mississippi, Inc.) Yates, Sheraton, and several John Does. After the defendants were served, they responded to the complaint, and the parties engaged in discovery.
¶ 5. Sheraton filed a motion for summary judgment on May 21, 1997. Avent promptly responded to Sheraton's motion.
¶ 6. The circuit court entered an "Agreed Scheduling Order" on April 18, 1997, requiring all discovery completed by August 30, 1997; plaintiff's experts to be designated by June 15, 1997; defendant's experts by July 30, 1997; and all motions filed by September 30, 1997. On August 28, 1997, the circuit court entered an "Agreed Amended Scheduling Order," requiring all discovery completed by November 30, 1997; plaintiff's experts designated by August 30, 1997; defendant's experts by September 30, 1997; and all motions filed by December 30, 1997. On November 13, 1997, the circuit court entered another "Agreed Amended Scheduling Order," requiring all discovery completed by March 30, 1998; plaintiff's experts designated by December 30, 1997; defendant's experts designated by January 30, 1998; and all motions filed by April 30, 1998.
¶ 7. Yates filed a motion for summary judgment on May 1, 1998. After the circuit court heard the summary-judgment motions, the court granted Sheraton's motion, which was filed on May 21, 1997, and dismissed Sheraton as a party on October 6, 1998. A week later, the circuit court granted Yates's motion for summary judgment and dismissed Yates as a party.
¶ 8. Several filings were entered on the docket from the time of the final judgment through August 10, 1999, when the clerk filed a letter from Entergy's counsel that gave notice that the name of his law firm had changed. None of the filings were significant.
¶ 9. For almost six years, according to the clerk's docket, this case was dormant.
¶ 10. Almost another year passed with no action on this case. On January 11,
March 29, 2006: Avent mailed a letter to Entergy, investigating whether the case could be disposed of through mediation.April 5, 2006: Entergy responded by mail to Avent's March letter.April 10, 2006: Entergy sent a follow-up letter to Avent regarding mediation.April 12, 2006: Avent set mediation for May 30, 2006.April 12, 2006: Entergy confirmed mediation dates, but questioned the value of mediation due to the length of time that the case had been dormant.April 18, 2006: Entergy filed a notice of service of its third set of interrogatories.April 25, 2006: Entergy sent a letter to Avent cancelling mediation, requesting a new deposition, and expressing concern about the likelihood of finding crucial witnesses given the age of the case.May 9, 2006: Avent sent Entergy a letter with potential deposition dates.June 6, 2006: Entergy filed its motion to dismiss based on want of prosecution; at the same time, Entergy filed an affidavit explaining its inability to locate witnesses.February 9, 2009: Avent filed a motion for a pretrial conference.February 10, 2009: Entergy filed a response to Avent's pretrial-conference motion.May 26, 2009: Entergy filed a supplemental motion to dismiss.September 23, 2009: Avent sent Entergy a proposed pretrial statement.February 18, 2010: Entergy filed a notice of hearing on its motion to dismiss.March 15, 2010: Entergy supplemented its motion to dismiss, detailing its inability to locate certain witnesses.April 30, 2010: The circuit court dismissed Entergy from Avent's lawsuit.
¶ 11. The circuit court held a hearing on Entergy's motion to dismiss on April 20, 2010. At the conclusion of the hearing, the circuit judge ruled:
(Emphasis added).
¶ 12. On April 30, 2010, the circuit judge signed a final judgment granting Entergy's motion to dismiss. It is from this judgment that Avent now appeals.
¶ 13. Rule 41(b) of the Mississippi Rules of Civil Procedure states:
M.R.C.P. 41(b). The circuit court relied on Rule 41(b) to dismiss Avent's claims against Entergy for failure to prosecute. We find that the circuit court was within its discretion, and the dismissal was proper.
¶ 14. Recently, in Barry v. Reeves, 47 So.3d 689, 692-93 (¶¶ 8-9) (Miss.2010), the Mississippi Supreme Court addressed the dismissal of a plaintiff's case for failure to prosecute, stating:
(Internal citations and footnote omitted).
¶ 15. Charles Barry filed suit against John Reeves in 2001 for alleged malpractice that Barry claimed had occurred in 1996. Id. at 693 (¶ 10). In 2007, Reeves filed a motion to dismiss for want of prosecution, which the Hinds County Circuit Court granted. Id. The circuit court found that Barry had failed to prosecute his case from 2004 to 2007 and dismissed the case. Id. The supreme court reversed the circuit court's judgment and noted that "the record reveals that both parties actively participated
Barry, 47 So.3d at 694 (¶¶ 14-16).
¶ 16. The facts here are not similar to the facts of Barry. Instead, Avent was injured in an accident that occurred on July 2, 1994. Avent filed his lawsuit on November 8, 1996. The last "agreed" scheduling order required experts to be designated by January 30, 1998, and discovery to end by March 30, 1998. No significant action was taken from 1999 until 2006. Then, after Entergy's motion to dismiss was filed on June 6, 2006, another three years lapsed before Avent filed a motion for a pretrial conference on February 9, 2009. Very little occurred from then until the circuit court dismissed Entergy as a party on April 30, 2010, almost sixteen years after the accident.
¶ 17. Entergy's motion to dismiss was not based solely on the passage of time. Entergy provided credible evidence that its ability to defend Avent's claims had been prejudiced by the delay. Entergy claimed that available witnesses' memories had faded over time. Entergy established that a significant number of witnesses were no longer available. Entergy offered affidavits of two legal assistants who testified about their unsuccessful efforts to locate the individuals identified in Avent's May 15, 2006, discovery answers. One of the legal assistants testified she attempted
¶ 18. To make matters worse, even though Avent responded to Entergy's motion to dismiss on June 18, 2006, Avent took no further action to move this case to judgment for another two years. The circuit judge recognized this case was a clear example of an inexcusable delay by the plaintiff that had prejudiced the defendant's efforts to defend the claims asserted. Avent offered no good cause for the delay. The circuit judge acknowledged Entergy's problem with locating witnesses, fading witnesses' memories, increased litigation costs, and the burden to the court system. The circuit judge did, in fact, consider the "clear record of delay ... by the plaintiff" and determined "lesser sanctions would not serve the best interest of justice." Barry, 47 So.3d at 692 (¶ 8). The circuit judge's reasoning also indicated that he found this was an "egregious" case. Id.
¶ 19. We find no error in the circuit court's judgment granting Entergy's motion to dismiss. The facts here are distinguishable from Barry. Here, the "significant, protracted delays in the prosecution of this case were" not beyond Avent's control. The circuit court considered the delay, the cause of the delay, and determined Entergy had been significantly prejudiced by the delay. The circuit court was within its discretion, and the dismissal was proper under Mississippi Rule of Civil Procedure 41(b). This issue lacks merit.
¶ 20. Avent also claims that the summary judgment was improperly granted as to Sheraton.
¶ 21. Although Sheraton owned the construction site, where it was in the process of constructing a casino, it was not the general contractor on the site. According to the terms of Sheraton's construction contract with Yates, Yates was "responsible for initiating, maintaining[,] and supervising all safety precautions and programs in connection with the performance of the [c]ontract." The same provision further stated that Sheraton was "not ... responsible in any way for providing a safe place for the performance of the [w]ork by [Yates], any [s]ubcontractor or [s]ub-subcontractor, or any of their respective agents or employees." A separate provision further stated that Yates was required to "take reasonable precautions for [the] safety of, and shall provide reasonable protection to prevent damage, injury[,] or loss to ... employees on the [w]ork and other persons who may be affected thereby...." The contract also stated that Yates was responsible for providing
¶ 22. Toby Arnheim, Sheraton's project manager responsible for the site, provided an affidavit that was considered by the circuit court. In it, Arnheim stated that he and Carl Bosworth, Sheraton's facilities director, were the only Sheraton employees who were ever at the site. Arnheim stated that he was there simply to "ensure that the work complied with the [c]ontract [d]ocuments." Bosworth also supplied an affidavit; he stated that he was not responsible for any of the work that was performed outside the building. Bosworth further stated that no Sheraton employee was responsible for the safety procedures in place at the site. Mike Sesko, who worked for Yates in July 1994, provided an affidavit which confirmed that Yates had complete control over the site and that Sheraton had nothing to do with the installation of the power line in question or the general safety conditions on the site.
¶ 23. Avent acknowledges the above, but claims that Mississippi law prohibits an entity from delegating its duty to provide a safe work environment. However, this argument is undermined by numerous cases. In Magee v. Transcontinental Gas Pipe Line Corp., 551 So.2d 182, 183 (Miss. 1989), Transcontinental Gas Pipe Line Corporation (Transco) contracted with Singley Construction Company to connect a well to existing gas pipelines for Transco. As here, Transco's contract with Singley explicitly made Singley responsible for the conditions on the site. Id. at 184-85. James Magee sued Transco and Singley after he was injured while working on the lines. Id. at 183. The Hinds County Circuit Court granted summary judgment on behalf of Transco, and Magee appealed. Id. at 184. Our supreme court found summary judgment was appropriate and affirmed the circuit court's judgment; in so doing, the supreme court stated the following:
Id. at 185-86 (emphasis added) (internal citations omitted). The Transco court recognized that an injured worker could recover against an owner like Transco if the owner "maintained substantial de facto control over those features of the work out of which the injury arose...." Id. at 186.
¶ 24. Like Transco, Sheraton contracted its responsibility for the site condition to Yates, its general contractor. Therefore, Sheraton has no liability for any injuries that Avent suffered as a result of the conditions on the construction site. We see no way to distinguish this case from Transco. There is nothing in the record to suggest that Sheraton maintained any sort of control over the power line from which Avent's injuries arose. Accordingly, summary judgment was properly granted on Sheraton's behalf, and this contention of error is without merit.
¶ 25.
BARNES, ISHEE, ROBERTS, CARLTON AND MAXWELL, JJ.,
IRVING, P.J., dissenting:
¶ 26. The majority finds that the Mississippi Supreme Court's decision in Barry does not require reversal of the Tunica County Circuit Court's dismissal of Avent's complaint against Entergy for failure to prosecute. I disagree; therefore, I dissent. I would reverse the circuit court's judgment of dismissal and remand this case for a trial.
¶ 27. In Barry, our supreme court addressed the propriety of dismissing a plaintiff's case for lack of prosecution, stating:
Barry, 47 So.3d at 692-93 (¶¶ 8-9) (footnote omitted) (emphasis added).
¶ 28. I believe the facts in Barry are very analogous to the facts here. Therefore, I set forth the salient dates in both Barry and our case, beginning with Barry.
Barry, 47 So.3d at 691-92 (¶¶ 3-6).
¶ 29. In the order dismissing Barry's lawsuit, the circuit court explicitly found that Barry had failed to prosecute his case from 2004 to 2007. Id. at 693 (¶ 10). The trial court's order of dismissal also stated:
Id. (footnote omitted).
¶ 30. In reversing the circuit court's judgment, our supreme court noted that "the record reveals that both parties actively participated in the discovery process by requesting, producing, and supplementing discovery until at least April 30, 2002." Id. at 693 (¶ 11). As to the period between 2004 and 2007, the supreme court noted that Barry had filed motions for settings and hearings and sent letters to opposing counsel during those years. Id. After the passage of ten months, Barry filed a motion to reopen discovery and for a trial setting. Id. at 691-92 (¶¶ 3-6). The circuit court heard argument on this motion within two months of it being filed; however, the court did not rule on it. Id. Seventeen months later, Barry sent a letter to the circuit court requesting a status conference. Id. During the twenty-seven months prior to Reeves filing his motion to dismiss, Barry filed a motion to reopen discovery, sent letters to opposing counsel seeking trial dates, and sent a letter to the circuit court requesting a status conference. Id.
¶ 31. Here, the record shows that Avent designated experts, responded to discovery, set a date for mediation, and exchanged correspondence with Entergy's counsel from 2005 to 2010, before the circuit court granted Entergy's motion to dismiss. It is true that little to nothing happened in this case between 1999 and 2005; however, Entergy chose not to file a motion to dismiss until mid-2006, at which
¶ 32. It is noteworthy that as in Barry, the parties engaged in significant discovery in the years immediately following the filing of the complaint, but then there was a cessation of action on the part of the plaintiff. Also, as did the defendant in Barry, Entergy filed a motion to dismiss but did not bring it on for a hearing. In Barry, the order of dismissal was entered approximately twenty-two months after it was filed. Here, almost four years passed prior to the order of dismissal being entered. Moreover, the record reveals that Entergy did not even notice its motion to dismiss for a hearing until February 18, 2010, more than three years and ten months after it was filed. Further, as did the plaintiff in Barry, Avent continued to prosecute his case while the motion to dismiss was pending. In Barry, eleven months after the motion to dismiss was filed, the plaintiff filed a motion for a status conference. Here, Avent filed a motion for a pretrial conference four months after Entergy filed its motion to dismiss.
¶ 33. Given the "severity and finality" of dismissing a case for want of prosecution,
¶ 34. For the reasons presented, I dissent.
RUSSELL, J., JOINS THIS OPINION.