JOHN R. TUNHEIM, District Judge.
Plaintiffs Richard Lewandowski and Creekwood Rental Townhomes, LLC ("Creekwood") (collectively, "Plaintiffs") bring this action against Defendant Kiln Underwriting Limited ("Kiln"), alleging
At the time of the hail storm giving rise to the present lawsuit, Lewandowski and his wife Lalainia were co-owners of five townhome buildings located in the 7100 block of Excelsior Way in St. Louis Park, Minnesota ("the Property"). (Def.'s App.,
Kiln issued Policy No. NMB 101-0203 ("the Policy"), a commercial property policy providing insurance to Plaintiffs for the period March 23, 2008, through March 23, 2009. (Def.'s App., Ex. A.)
Under the Policy, Kiln agreed to "pay for direct physical loss of or damage to Covered Property at the premises described in the Declarations caused by or resulting from any Covered Cause of Loss." (Id., Ex. A at 31.) A cause of loss is covered under the Policy unless specifically excluded or limited. (Id., Ex. A at 6, 45.)
On March 23, 2008, Kristin Dill of Kiln conducted an inspection of the Property and noted that the roof was in "average" condition. (Aff. of Coleman J. Braun ¶ 4, Ex. 2 at 2, Ex. 3, July 20, 2011, Docket No. 47.) An underwriting inspection conducted by Kiln on April 7, 2008, also noted that the buildings were in "good" condition. (Second Aff. of Scott May, Ex. 2 at 3, Dec. 1, 2011, Docket No. 140.)
On May 31, 2008, a hailstorm struck St. Louis Park. (Am. Compl. ¶ 12, July 26, 2010, Docket No. 23; Lewandowski Dep. 20:13-25; Second McColgan Aff., Ex. 3.) On June 3, 2008, Plaintiffs submitted a claim under the Policy, and described the damage for which coverage was sought as "[h]ail storm damage to roofs of buildings." (Second McColgan Aff., Ex. 3.)
On January 14, 2008 Jeff Queen from Kiln's claims adjuster, North American Claim Services, Inc. ("NACS"), met with Lewandowski's roofing contractor to conduct an inspection of the Property. (Id., Ex. 4 at 2, 4.) Queen concluded that "the roofs were in need of repair/replacement" "due to the deterioration of the shingles caused by typical weather conditions," and that "it did not appear that hail caused any additional damage to the actual roof, but for minor hail dents in the roofing vent caps." (Id., Ex. 4 at 4-5.) NACS then retained a registered roofing observer, Wendell O. Finken of AMBE, Ltd., who inspected and photographed the roofs on September 19, 2008, and prepared a report. (Id., Ex. 4 at 5; id., Ex. 5.) Finken concluded:
(Id., Ex. 5 at 3-4; see also id., Ex. 4 at 5.)
NACS reported its findings to Kiln in a letter dated October 21, 2008. (Id., Ex. 4.) Citing the provisions of the Policy that exclude coverage for losses caused by wear and tear or inadequate maintenance, NACS recommended that Kiln decline coverage because "the current roofs pre-loss, were in dire need of maintenance and repair due to the deterioration of the existing shingles prior to the hail storm." (Id., Ex. 4 at 3-4, 6.) NACS noted that "[t]he hail exacerbated the deterioration of the southern portion of the roof shingles which were already in need of replacement." (Id., Ex. 4 at 3.) NACS also stated that Finken believed defective shingles may have caused at least part of the damage. (Id., Ex. 4 at 5.) NACS concluded:
(Id., Ex. 4 at 6.)
Additionally, in an email dated November 7, 2008, an NACS employee advised Kiln that Lewandowski "has fully admitted that he knew the roofs of the complex needed to be replaced long before the hail storm hit" but "[h]e just doesn't want to go down the same path of litigating against the product manufacturer who supplied what was suppose[d] to be a 25 year asphalt shingle that broke down in less than 8 years." (Id., Ex. 6 at 2.)
Upon direction from Kiln, NACS sent Plaintiffs a denial of coverage letter dated November 21, 2008. (Id., Ex. 7.) The denial of coverage was based on the provisions of the Policy excluding from coverage damage caused by wear and tear or faulty maintenance and Kiln's conclusion that the roof was in need of replacement prior to the hailstorm due to deterioration of the shingles. (Id., Ex. 7 at 3-4.) NACS informed Lewandowski that "[a]ll parties acknowledge that the hail storm struck the roofs of the property, however the replacement needed of the shingles is not caused by the hail storm." (Id., Ex. 7 at 3.)
Following the denial of coverage, Plaintiffs demanded an appraisal in an email dated November 25, 2008. (Id., Ex. 8.) The demand was made pursuant to the Policy's Appraisal Condition, which states:
If there is an appraisal, [Kiln] will still retain [its] right to deny the claim. (Def.'s App., Ex. A at 39.)
In December 2008, Kiln appointed Engle Martin Claims Administrative Services, Inc. ("EMCAS") to replace NACS as Kiln's third party claims administrator. (Lewandowski Dep. 36:9-15; Def.'s App., Ex. D at 3.) EMCAS retained Engle Martin & Associates ("EMA") to respond to the appraisal demand. (Second May Aff., Ex. 7.) Scott May of EMA was appointed to serve as Kiln's adjuster on Plaintiffs' claim. (Def.'s App., Ex. D (Dep. of Scott May ("May Dep.") 62:22-63:9); Second May Aff. ¶ 2, Ex. 7.)
May met with Lewandowski at the Property in December 2008, to inspect the roofs, but did not complete the inspection due to weather conditions. (See Lewandowski Dep. 38:21-39:23; May Dep. 117:20-25.) May wrote Plaintiffs a letter on December 15, requesting that Plaintiffs contact him when the roofs were "free of snow and ice" so that they could be inspected. (Second May Aff., Ex. 7.) However, Plaintiffs had already replaced the roofs on two of the townhomes in October 2008 and replaced the roofs on the other three townhomes in the spring of 2009, before May was able to inspect them. (Lewandowski Dep. 124:6-19; Appraisal Hearing Tr. ("Tr.") 99, Aug. 3, 2011, Docket No. 66.)
Plaintiffs reiterated their appraisal demand in February 2009. (Second McColgan Aff., Ex. 10.) An appraisal panel was formed, consisting of three appraisers: Paul Norcia, who was appointed by Plaintiffs, Richard Herzog, who was appointed by Kiln, and James Stoops, who was selected by Norcia and Herzog to serve as the umpire. (Second McColgan Aff., Ex. 11 (Dep. of Thomas Irmiter ("Irmiter Dep.") 60:9-21); Second May Aff., Ex. 9 at 3; Tr. 3.)
The appraisal was scheduled for April 29, 2009. (Second McColgan Aff., Ex. 12 at 3.) The appraisal panel, May, Lewandowski, and Lewandowski's expert Thomas Irmiter met at the Property to begin the appraisal. (Second May Aff., Ex. 9 at 3.) At the site visit, Norcia raised the issue that portions of the townhomes other than the roofs — specifically the fascia, downspouts, gutters, windows, and siding — may have also been damaged by the hail storm. (Id.) Umpire Stoops determined that the appraisal process could not proceed until
The appraisal was rescheduled to August 27, 2009, and consisted of a site visit followed by a hearing during which documentary evidence and live witness testimony was presented. (Lewandowski Dep. 48:11-20; see generally Tr.) The focus of the appraisal was "the scope and price issues pertaining to the storm damage claim that is at issue." (Tr. 5.) At the appraisal, in its opening statement Kiln admitted that there was damage caused by the hail storm to the soft metals on the north and east facing sides of the buildings and soft metal on the roof. (Tr. 9.) Kiln denied, however, that the shingles were damaged by hail, claiming instead that damage was due to deterioration and defective shingles exacerbated by weather conditions and improper ventilation. (Tr. 9, 11-12.)
May testified that he saw evidence of delamination and blistering, but not hail damage on sample shingles from the Plaintiffs' roofs that were available at the appraisal hearing. (Tr. 86-87.) May further testified that it was difficult for him to make any recommendation to the insurance company about the damage because of the number of repairs that had been made on the Property prior to his inspection. (Tr. 91.) He also testified that he could not state whether there was hail damage to the roofs because of his lack of inspection. (Tr. 99.)
Kiln's engineering expert, Nathan Prieve, P.E., inspected photographs of the damage to the Property but did not inspect the roofs before they were replaced. (Tr. 151.) Based on the photographs, Prieve testified that the roofs of Plaintiffs' buildings sustained no hail damage on the north or south sides as a result of the May 31, 2008 storm. (Tr. 153-56.) He did state, however, that there may have been granule loss to the shingles from the storm. (Tr. 170.) He observed heavy wear and tear, erosion, and shingles that did not hold up as well as some other shingles. (Tr. 153.) He suggested that the wear was worse on the southern side because of the sun exposure. (Tr. 154.) He stated, based on having observed marks caused by the hail in other locations on the Property, that the hail that hit the roofs was relatively small in size. (Tr. 153, 156, 162-63.) While Prieve did not believe the damage to the roof was caused by hail, he admitted that there was no published standard on what constitutes a "hail hit" on a shingle. (Tr. 167.)
Finken, the roof consultant retained by NACS in September 2008 to assess Plaintiffs' claim, agreed with Prieve's testimony. Finken testified, based upon his personal observation of the roofs that:
(Tr. 119.) He stated that the deterioration was worse on the south facing surfaces. (Id. at 120.) He further stated that he did not believe these issues were caused by hail but rather the deterioration was caused by "normal conditions," product failure, and improper ventilation. (Tr. 119-20, 125.) He opined that the south facing shingles were so far deteriorated that they could not hold up to normal weather conditions, including any level of hail. (Tr. 126.) Thus, he stated, "South facing roofs are damaged by hail but it appears that the roof was already deteriorated
Plaintiffs responded that there was hail damage on the roof. (Tr. 27.) Plaintiffs retained Irmiter, a licensed building official, to act as their damages consultant and to present evidence to the appraisal panel. (Second McColgan Aff., Ex. 11 at 3.) Irmiter works for Forensic Building Science, Inc. ("FBS"). (Id.) Irmiter testified that he has personally replaced hundreds of roofs, is a certified state building official, has a great deal of experience with shingles and roofing materials, and has been qualified as an expert by various courts on construction defects and other issues. (Tr. 35-36.) Irmiter consulted with Bryan Oakley of FBS, a professional engineer, in arriving at his conclusions. (See Tr. 35; List of Exs. in Supp. of Mot. for Summ. J., Ex. D 48:6-17, Dec. 1, 2011, Docket No. 142.)
At the hearing, Plaintiffs produced actual shingles from the north side of the roofs and Irmiter testified that they showed hail dents rather than deterioration. (Tr. 16, 27.) Plaintiffs also produced photographs of the alleged hail damage. In addition, Plaintiffs presented a damage estimate prepared by the Lindsay Consulting Group (the "Lindsay Estimate"). (Second McColgan Aff., Ex. 13.) Irmiter personally prepared the Lindsay Estimate. (Irmiter Dep. 62:16-17.) The appraisal panel admitted the Lindsay Estimate into evidence. (Id. 65:10-14; Tr. 20.) The Lindsay Estimate concluded that the Property required $1,349,891.13 in repairs as a result of the May 31, 2008 hail storm. (Second McColgan Aff., Ex. 13 at 11.) The Lindsay Estimate called for total replacement of all roofs, window and stucco upgrades due to building codes, repairs to the soffit and fascia, repairs to gutters that would be damaged during replacement of the roofs, and installation of ice shields to prevent ice damming. (Id., Ex. 13.) Irmiter testified that the Lindsay Estimate "represented the scope of work that was required as a result of the storm in its entirety," (Irmiter Dep. 66:22-67:7) and took "into account removing the roofs, removing the damaged windows, damaged doors, the damaged metal and replacing those areas" (Tr. 30).
With respect to the code upgrades referenced in the Lindsay Estimate, Irmiter testified that flashing had to be replaced on the roofs in order to meet city code requirements. (Tr. 27-28.) Irmiter also testified that certain costs of repairing the windows were required by city and zoning regulations. (Tr. 28.) Herzog asked Irmiter whether he had any documentation from his discussions with the building official regarding the work to the Property mandated by city and zoning regulations. (Tr. 31.) Irmiter indicated that he believed the information to be confidential, but that he could provide the appraisal panel with documentation if necessary to make its decision with regard to the codes. (Tr. 31-32.)
With respect to material unavailability, Irmiter testified that because the shingles at issue were no longer manufactured, Plaintiffs had replaced the entire roof, affecting the scope and cost of the work. (Tr. 27.) May testified that he was unaware whether the original shingles used on the Property were still available. (Tr. 110.)
The appraisal panel issued an appraisal award on August 28, 2009, which was
(Id.)
In handwritten notes attached to the typewritten form, the award states with respect to the roof:
(Id., Ex. 14 at 3.) The award also provides individual award amounts for fascia ($9,205.00), door trim ($3,878.22), garage trim ($6,262.40), gutter/downspouts ($14,026.32), windows ($11,313.10), stucco tie in work ($48,000), dumpsters ($5,320), permits ($2,876.47), sales tax ($5,522.82), and profits and overhead ($23,851.68). (Id.) Neither Kiln nor Plaintiffs ever asked the appraisal panel to reconsider, modify, or clarify the award.
In October 2009, Kiln paid $111,190.05 to Plaintiffs, which Kiln claims was the portion of the appraisal relating to damage to the Property other than the roofs. (See Second McColgan Aff., Ex. 14; Pls.' App., Ex. C, May 3, 2013, Docket No. 241.)
Damaged Item Identified by Appraisers Appraisal Award Fascia 9,205.00 Door trim 3,878.22 Garage trim 6,262,40 Gutters/downspouts 14,026.32 Windows (10 at $681.31 each for a total of $6,813.10 and 20 at $225 each 11,313.10 for a total of $4,500. $6,813.10 + $4,500 = $11,313.10) Stucco tie-in work 48,000.00 Dumpsters (5 × $532 each) 2,600.00SUBTOTAL (1) 95,345.04 Sales tax 2,860.35 Permits 2,876.47SUBTOTAL (2) 101,081.86 Profits and overhead (10%) 10,108.19TOTAL $111,190.05
(Id., Ex. C at 3; see also Am. Compl. ¶ 20.)
On June 10, 2010, Plaintiffs sent Kiln a letter demanding appraisal to determine the amount of loss for the following items of damages that they believed were not adequately considered or addressed by the appraisal panel:
(Pls.' App., Ex. F.) Kiln determined that Plaintiffs were not entitled to a second appraisal and declined to appoint an appraiser. (Answer to First Am. Compl. ¶ 21, Aug. 9, 2010, Docket No. 25.)
In connection with the present motions, the parties dispute the scope of the items the appraisal panel considered in rendering the award. Plaintiffs and Kiln have submitted the testimony of various individuals to support their respective positions that the award failed to take into consideration certain damages to the Property and that the award constituted a complete finding with respect to damage to the Property resulting from the May 2008 hail storm.
Lewandowski testified that he believed the entire scope of damages that occurred at the Property as a result of the hail storm had been presented to the appraisal panel. (Lewandowski Dep. 45:5-10.) Appraiser Herzog also submitted an affidavit in which he indicated that the appraisal panel "initially was tasked with determining the fair and reasonable cost to repair roof damage to Plaintiffs' five townhomes resulting from a hailstorm that took place on May 31, 2008." (Aff. of Richard F. Herzog, P.E., ¶ 4, Oct. 21, 2011, Docket No. 105.) Herzog also indicated that as a result of the initial site visit, the parties were allowed to present evidence of "the damage resulting from the May 31, 2008 hailstorm" and the appraisal panel "considered all of the damage evidence and testimony presented by both parties." (Id. ¶¶ 9, 11.) Appraiser Norcia submitted an affidavit explaining that "[t]he appraisal award of August 27, 2009, provides the amount of loss for items which were either directly damaged from the hail event, or were immediately effected by the replacement of said hail damaged items." (Pls.' App., Ex. D (Aff. of Paul Norcia ("Norcia Aff.") ¶ 4).)
With respect to the cost of replacing portions of the Property for purposes of code upgrades, Herzog averred that Plaintiffs
(Norcia Aff., ¶ 3.)
In the present motions, in addition to disputing the scope and significance of the appraisal award as it relates to Plaintiffs' coverage under the Policy, the parties dispute the impact of litigation by Lewandowski related to the Property that predated the May 2008 hail storm.
In 2007, the Lewandowskis sued the general contractor for the Property, MM Home Builders, Inc., in Hennepin County District Court (the "Stucco litigation"). (Fourth Aff. of Kristine M. Sorenson, Ex. 1, Dec. 1, 2011, Docket No. 141.) The claims in the amended complaint in the Stucco litigation arose, at least in part, out of alleged water damage to the townhomes at the Property discovered in the spring of 2007, prior to the hailstorm. (Id., Ex. 1 at 4; Def.'s App., Ex. J at 3-4.) The amended complaint stated that the Lewandowskis discovered that the townhomes "had major construction defects and mold as a result of water infiltration into the wall cavities and sheathing [and] said damage was caused by negligence, departure from good building practices, and breaches of warranties of the Defendant." (Fourth Sorenson Aff., Ex. 1 at 4.)
Plaintiffs admitted in discovery in the present case that in the Stucco litigation they
(Def.'s App., Ex. J at 4.) Plaintiffs also indicated that the compensation sought in the Stucco litigation was "for the cost of remedying the defects and/or deficiencies at issue in that litigation, which would include the cost of work performed to the townhomes at the property for those defects and/or deficiencies." (Id., Ex. J at 4-5.) Additionally, at the appraisal hearing, Irmiter admitted that Plaintiffs sued MM Home Builders based, in part, on allegations
After the Lewandowskis filed the Stucco litigation, the general contractor brought third-party complaints against a number of subcontractors. (Fourth Sorenson Aff., Ex. 1 at 8-10.) Although the parties have presented no specific information regarding settlements, it appears that the Stucco litigation resulted in multiple settlement agreements. (Tr. 73-74; Fourth Sorenson Aff., Ex. 3 at 4.) The parties do not dispute that some of the settlement funds received in the Stucco litigation were used by Plaintiffs to fund replacement of at least some of the roofs on the Property. (Pl.'s Mem. in Opp'n to Mot. for Summ. J. at 8, May 17, 2013, Docket No. 249; see also Tr. 55; Fourth Sorenson Aff., Ex. 3 at 4.)
In addition to the Stucco litigation, in 2007 the Lewandowskis asserted a claim against their first-party property insurer, Owners Insurance Company, for water damage to the townhomes. (Def.'s App., Ex. J at 3-4; May Dep. 118:7-12.) Plaintiffs described the claim as one
(Def.'s App., Ex. J at 3.) Plaintiffs also admitted that in connection with the water damage claim they "contended the roofs of all five buildings should be replaced due to the non-availability of certain roofing materials and the inability to match or reuse existing building materials." (Id., Ex. J at 4.) Plaintiffs ultimately settled this claim with their insurer, and used at least some of those funds to replace the roofs on all units on the Property. (Tr. 55; Fourth Sorenson Aff., Ex. 3 at 4 ("The proceeds from the Owners settlement enabled the [Lewandowskis] to complete reroofing of all units and repairs of 14 of 38 units.").)
On May 28, 2010, Plaintiffs' filed the instant lawsuit, alleging a single cause of action for breach of contract. (Compl., May 28, 2010, Docket No. 1.) Under the breach of contract claim, Plaintiffs allege that Kiln wrongfully withheld Policy benefits by failing to pay the remaining amount of the appraisal award and by refusing to engage in a second appraisal. (Id. ¶¶ 22-26.) Plaintiffs amended their complaint to name Kiln as a defendant, removing other syndicates of Lloyd's of London. (Compare Compl. at 1, with Am. Compl. at 1, July 26, 2010, Docket No. 23.) On November 15, 2010, the Court granted Kiln's motion to deposit the disputed portion of the appraisal award into the Court's registry. (Order, Nov. 15, 2010, Docket No. 40.) A receipt for $151,178.46 was issued by the Court on December 17, 2010. (Receipt, Dec. 17, 2010, Docket No. 41.)
The parties previously filed motions for summary judgment that the Court denied as premature. See Creekwood Rental Townhomes, LLC v. Kiln Underwriting Ltd., Civ. No. 10-2179, 2012 WL 4481239, at *6 (D.Minn. Sept. 28, 2012). The Court noted that the Lewandowskis had filed for Chapter 11 bankruptcy in the United States Bankruptcy Court for the District
In support of their present motion for summary judgment Plaintiffs argue that they are entitled to recover the remaining $151,178.46 of the appraisal award that Kiln declined to pay. Additionally, Plaintiffs argue that they are entitled to a second appraisal for consideration of certain damages to the Property allegedly not considered by the original appraisal panel. With respect to Plaintiffs' entitlement to the full appraisal award, Kiln argues that summary judgment in its favor is warranted because no coverage exists for the $151,178.46 portion of the appraisal award related to the roofs of the Property, as damage to the roofs was due to wear and tear — an excluded cause of loss under the Policy. Additionally, Kiln argues that Plaintiffs may not recover the remainder of the appraisal award because they were already compensated for damage to the Property through the Stucco settlement and the water damage insurance settlement and used those funds to replace the roofs. With respect to Plaintiffs' entitlement to a second appraisal, Kiln argues that the amount determined by the appraisal panel is binding and that Plaintiffs failed to follow the procedures set forth in the Minnesota Uniform Arbitration Act to revisit that amount. Finally, Kiln argues that Creekwood lacks an insurable interest in the Property and therefore has no standing in the present lawsuit, and summary judgment in Kiln's favor with respect to Creekwood's claims is appropriate.
Although not framed specifically in terms of Plaintiffs' breach of contract claims, in essence the parties' arguments focus on whether material issues of fact remain regarding Kiln's alleged breach of the Policy — for failure to pay the full appraisal award and failure to submit to a second appraisal proceeding. With this framework in mind, the Court will address each of the parties' contentions in turn.
Summary judgment is appropriate where there are no genuine issues of material
The heart of the parties' motions centers around the scope of the appraisal award and its preclusive effect. Pursuant to the Policy, the appraisal panel's determination of "amount of loss" is binding. (See Def.'s App., Ex. A at 39 ("The appraisers will state separately the value of the property and amount of loss. If they fail to agree, they will submit their differences to the umpire. A decision agreed to by any two will be binding.").) Therefore, an examination of the scope of the appraisal panel's "amount of loss" determination has important implications for the present motion, as that determination will establish what issues remain to be decided by the Court and which issues have already been conclusively determined by the appraisal panel.
Plaintiffs argue that the appraisal award determined that $262,368.51 was the amount of loss caused by hail damage. Kiln, on the other hand, argues that the appraisal panel did not make a determination that the amount of loss was caused by hail damage, and even if it had, that the Court may revisit that issue to determine that the loss to the roofs was actually caused by wear and tear and is therefore excluded under the Policy. Based on the record before it, the Court concludes that the appraisal panel had the authority to consider the cause of the loss as part of its amount of loss determination, and in rendering the appraisal award made a determination that the damages awarded were caused by hail. Because the Court finds that the parties in their motions have identified no coverage issues related to the cause of loss determination, the Court concludes that the appraisal award and its accompanying determination that the award was for damages caused by hail is conclusive and binding on the parties.
In Quade v. Secura Insurance, 814 N.W.2d 703 (Minn.2012), the Minnesota Supreme Court examined the scope of an appraisal panel's authority and the preclusive effect of appraisal panel determinations. In that case the Quades submitted a claim to their property insurer — Secura — for storm damage to several buildings. Id. at 704. Secura paid for some of the damages which it determined were caused by the storm, but declined to pay for others, determining that some damage to the
The court began by explaining that the phrase "amount of loss" as used in insurance policy appraisal clauses is not ambiguous and "in the insurance context, an appraiser's assessment of the `amount of loss' necessarily includes a determination of the cause of the loss, and the amount it would cost to repair that loss." Id. Although the court noted that "[t]he scope of appraisal is limited to damage questions while liability questions are reserved for the court," it acknowledged that "the line between liability and damage questions is not always clear." Id. The court went on to explain:
Id. at 706-07.
The court clarified that "an appraisal award does not preclude the insurer from subsequently having its liability on the policy judicially determined" and that "[i]f the appraisal award is flawed because it answers questions of liability outside the scope of the appraisal process, then the award can be challenged later before the district court." Id. at 707-08 (internal quotation marks omitted). Specifically, the Court concluded that "the appraisers must necessarily determine the cause of the loss, as well as the amount necessary to repair the loss. However, to the extent that determination goes beyond the scope of appraisal and interprets policy exclusions, that determination is reviewable by the district court." Id. at 708. Whether an appraisal award will be conclusive on a particular issue in any given case "will depend on the nature of the damage, the possible causes, the parties' dispute, and the structure of the appraisal award." Id.
Kiln appears to argue generally that the appraisal panel did not make a cause of loss determination, but it has presented no specific evidence or interpretation of the appraisal award in support of
This conclusion is further supported by the nature and scope of the appraisal hearing. At the initial appraisal site visit on April 29, 2009, the parties discussed areas of the townhomes that had been damaged by the hail storm. Additionally, at the August 27, 2009 hearing the appraisal panel stated that the focus of the hearing was "the scope and price issues
Finally, the structure of the appraisal award itself indicates that the appraisal panel made a cause of loss determination in assessing the amount of loss. On the appraisal award form, in the line for "cause" the appraisal panel wrote "storm — wind & hail." (Second McColgan Aff., Ex. 14 at 2.) Additionally, although again, far from a model of clarity, the
Kiln next argues that, even if the appraisal panel concluded that the loss to the Property was caused by hail damage, that causation finding is not conclusive and is instead subject to judicial review. But Kiln's contention is contrary to the Minnesota Supreme Court's holding in Quade.
Here, Kiln asks the Court to revisit the issue of causation. Kiln, however, has identified no Policy provision that the appraisal panel interpreted, misinterpreted, or applied in determining that the $262,368.51 amount of loss to the Property was caused by hail damage. SeeCedar Bluff Townhome Condo. Ass'n, Inc. v. Am. Family Mut. Ins. Co., No. A13-0124, 2013 WL 6223454, at *3-*4 (Minn.Ct.App. Dec. 2, 2013) (allowing challenges to an appraisal panel's determination where the parties argued that the appraisal panel had necessarily interpreted the phrase "other property of like kind and quality" in determining the cost of replacement
Kiln appears to acknowledge that this Court's role is limited to coverage disputes, by explaining that "it does not matter whether the Appraisal Panel determined causation in rendering the Appraisal Award. Under Quade, it is up to this Court to determine if the loss is covered under the Policy and Kiln is liable to Plaintiffs for the remainder of the appraisal award." (Def.'s Mem. in Opp'n to Mot. for Summ. J. at 19, May 17, 2013, Docket No. 252.) According to Kiln's own argument, therefore, the question for this Court is whether a loss caused by hail is covered under the Policy and whether Kiln is liable to Plaintiffs for the remainder of the appraisal award. Because Kiln has not identified any part of the Policy that would exclude coverage for losses caused by hail damage, it has not identified any reviewable portion of the appraisal panel's award.
Finally, the Court notes that Kiln's interpretation of Quade would require the district court to revisit every causation determination of an appraisal panel because a causation determination is always at least tangentially related to coverage and an insurer's ultimate liability under a policy. Such a practice would undermine the court's determination in Quade that an appraiser's determination of the amount of loss is binding on the parties and that "an appraiser's duty to determine the `amount of loss' requires the appraiser to determine causation." 814 N.W.2d at 706. Although "the line between liability and damage questions" will not always be clear, see id., the Court finds that where, as here, the party seeking to challenge the appraisal award has not identified a coverage question that the appraisal panel inappropriately considered or resolved, the appraisal panel's determination of the cause of loss is conclusive and binding on the parties. Accordingly, the Court finds that Plaintiffs are entitled to recover the remaining $151,178.46 amount of loss awarded by the appraisal panel for damages caused by the hail storm.
Finally, Kiln argues that Plaintiffs cannot recover the remainder of the appraisal award because the settlements in the stucco litigation and the water intrusion insurance claim that were used, in part, to replace roofs on the Property, preclude Plaintiffs from recovering any additional damages related to those roofs. As support for this argument, Kiln cites Leamington Co. v. Nonprofits' Insurance Association, 661 N.W.2d 674 (Minn.Ct. App.2003). In Leamington, a tortfeasor paid property owners for damage caused to the property. Id. at 676. The property owners then sued the tortfeasor's insurance company to recover for the same damages. Id. The district court held that the money received from the tortfeasor would be credited against any settlement or judgment the property owners obtained from the insurance company. Id. The court of appeals affirmed and began by recognizing the common-law collateral source rule, which provides that "money or services that a plaintiff receives `in reparation of the injury from a source other than the tortfeasor' will not be `credited against the tortfeasor's liability' even though they may partially or completely reimburse the plaintiff for damages suffered." Id. at 678
The Court concludes that Leamington's holding has no bearing on the issues before the Court for several reasons. First, unlike Leamington, the dispute in this case is between an insured and insurer who have a contractual relationship that defines their responsibilities to one another, therefore resort to the common law of torts in order to ascertain Kiln's payment obligations is both unnecessary and inappropriate. Minnesota law is clear that "the rights of an insurer and an insured are established as of the time of the [loss], and those rights are not affected if the insured eventually is compensated for the loss from another source." Bd. of Trs. of First Congregational Church of Austin v. Cream City Mut. Ins. Co. of Milwaukee, Wis., 255 Minn. 347, 96 N.W.2d 690, 696 (1959). Therefore "[t]he recovery of an insured will not be diminished because of the fact that he might have collateral contracts with third persons which operate to relieve the insured from the loss for which the insurer agreed to compensate him." Id. Kiln has pointed to no language in the Policy that relieves it of its obligation to pay for covered losses if Plaintiffs first obtain coverage of a different loss, insured by a different insurance company, which affects the same part of the Property as the covered loss under the Kiln Policy.
Second, unlike Leamington there is no relationship between Kiln and the entities involved in the Stucco litigation and the water intrusion insurance claim. Therefore, there is no possibility that Plaintiffs will "obtain a double recovery from essentially the same source." Leamington, 661 N.W.2d at 679. Finally, Kiln has presented no evidence that the settlements obtained by Plaintiffs in the prior lawsuit and insurance claim were compensation for the
Plaintiffs and Kiln both move for summary judgment on Plaintiffs' claim that Kiln breached the terms of the Policy by refusing to submit to a second appraisal. Plaintiffs argue that, under the Policy, they are entitled to a second appraisal to determine the amount of loss related to building code upgrades and material unavailability.
In determining the amount of loss suffered to property, depending upon the valuation measures provided in the insurance policy, appraisers are sometimes required to determine the availability of replacement materials. See QBE Ins. Corp. v. Twin Homes of French Ridge Homeowners Ass'n, 778 N.W.2d 393, 396, 398 (Minn.Ct.App.2010). For example, with respect to roofs, if the shingles used on the original roof are no longer available, in determining the amount of loss, an appraisal panel will often need to consider the cost of obtaining other, similar shingles. Id. at 396.
Plaintiffs base their request for a new appraisal regarding material unavailability on the comment in the appraisal award stating: "Material availability not considered." (Second McColgan Aff., Ex. 14 at 2.) In particular, Plaintiffs appear to be arguing that because the original shingles were unavailable to repair the roof, they are entitled to coverage for the cost of replacing the entire roof with different shingles. The Court finds that Plaintiffs request for a second appraisal is improper because Plaintiffs failed to provide the appraisal panel with a fair opportunity to make a factual determination regarding material unavailability and because Plaintiffs failed to identify any language in the Policy that entitles them to recover the cost of replacing the entire roof even if the original shingles are unavailable and therefore failed to show that the appraisal panel was required to consider material unavailability.
As an initial matter, the Court notes that the Policy specifies that if the parties disagree on "the amount of loss," then "either may make written demand for
Here, the Court concludes that Plaintiffs failed to present sufficient evidence at the appraisal hearing to adequately raise the issue of material availability and provide the appraisal panel with a fair opportunity to decide questions of amount of loss related to material unavailability. The only mention Plaintiffs made at the appraisal hearing regarding materials used to repair the roofs was Irmiter's statement that "it's our contention that because the shingle is no longer manufactured we can't replace just half a
The single statement by Irmiter that he believed the entire roof needed to be replaced because the original shingles were unavailable did not provide the appraisal panel with sufficient information or evidence to make a determination regarding material availability and how any availability issues affected the amount of loss. Plaintiffs do not contend that the appraisal panel prevented them from presenting appropriate evidence to support their contention that the original shingles were unavailable and therefore replacement of the entire roof was warranted. Instead, Plaintiffs now essentially ask the Court to allow them a do-over, and an opportunity to present issues of amount of loss related to the hail damage to an appraisal panel. Allowing plaintiffs to initiate a new appraisal process or challenge the appraisal panel's determination of amount of loss any time the plaintiffs failed to present adequate evidence of a particular loss suffered at an original appraisal hearing would undermine the purpose of appraisal panels as providing "the plain, speedy, inexpensive and just determination of the extent of the loss." Quade, 814 N.W.2d at 707 (internal quotation marks omitted).
Furthermore, the Court finds that a second appraisal proceeding is particularly inappropriate where, as here, Plaintiffs have not identified a single provision of the Policy supporting their contention that a determination of material availability is a necessary part of determining amount of loss under the Policy. In other words, Plaintiffs have pointed to no part of the Policy which would entitle them to the replacement cost of the entire roof in the event that the original shingles are unavailable. In the absence of any argument from the parties, the Court will not speculate as to the application of the Policy and its many potentially relevant provisions to these circumstances. Therefore, Plaintiffs have failed to demonstrate that the appraisal panel's determination of amount of loss — after concluding that material availability was not an issue — was inappropriate as a coverage matter. Accordingly, the Court finds that Plaintiffs had identified no reviewable errors in the appraisal panel's determination and are not entitled to a second appraisal proceeding.
Plaintiffs also argue that a second appraisal panel is warranted to consider portions of the amount of loss from the hail storm that relate to expenses associated with updating the buildings on the Property to bring them into compliance with applicable building codes. The Court finds that the preceding analysis applies with equal force to the issue of code upgrades. At the appraisal hearing, Irmiter testified generally that certain costs of repair to the Property were required by city and zoning regulations. When asked by appraiser Herzog whether he had any documentation from his discussions with the building official regarding the work to the Property mandated by city and zoning regulations, Irmiter indicated that he believed the information was confidential and did not have any of that material with him, but could provide additional information to the panel if necessary. (Tr. 31-32.) Herzog noted in his affidavit that Irmiter provided no citations to the relevant building codes and no documentation of the upgrades that were performed on the Property allegedly related to code upgrades. As with the issue of material availability, the Court finds that Plaintiffs' presentation at the appraisal hearing was insufficient to demonstrate any entitlement to an award based on code upgrades. Accordingly, the appraisal panel did not err in failing to award any damages based on this general testimony and Plaintiffs are not entitled to reargue the issue of code upgrades before a new appraisal panel.
Finally, Plaintiffs have again cited to no provision of the Policy in support of their argument that code upgrades are an essential part of the amount of loss or that the appraisal panel somehow made a determination of amount of loss that cannot be awarded under the Policy due to its failure to award damages for code upgrades.
Finally, Kiln argues that summary judgment should be granted in its favor with respect to Creekwood's claims because Creekwood lacks standing. Specifically, Kiln argues that Creekwood lacks an insurable interest in the Property, and therefore is not entitled to recover on a breach of insurance contract claim. "[A]n insurable interest exists where the insured can suffer a loss if the subject property is damaged." Nw. Nat'l Bank v. Maher, 258 N.W.2d 623, 624 (Minn.1977) (internal quotations omitted). "[I]t is not necessary that the insured should have an absolute right of property, and ... he has an insurable interest if, by the destruction of the property, he will suffer a loss, whether or not he has or has not any title to, lien upon, or possession of the property itself." Crowell v. Delafield Farmers Mut. Fire Ins. Co., 463 N.W.2d 737, 738 (Minn.1990) (internal quotation marks omitted). "[A]ny limited or qualified interest, whether legal or equitable, or any expectancy of advantage, is sufficient to constitute an insurable interest." Id. at 739 (internal quotation marks omitted). A mere expectation of a property interest may be insufficient to constitute an insurable interest. See Anderson v. State Farm Fire & Cas. Co., 397 N.W.2d 416, 418 (Minn.Ct.App. 1986) (finding no insurable property interest where "[a]lthough William Anderson hoped to purchase the property someday and had been using the property for a substantial amount of time, his claim to the garage was only an expectancy. Consequently, he did not have a risk of
The record contains undisputed evidence that Creekwood executed lease agreements with tenants for the townhomes on the Property during the time period in which the hail storm occurred. (Lewandowski Dep. 12:18-13:12.)
Based on the foregoing, and all the files, records, and proceedings herein,
1. Plaintiffs' Motion for Summary Judgment [Docket No. 239] is
2. Defendant's Motion for Summary Judgment [Docket No. 244] is
3. Judgment shall be entered against Defendant in the amount of $151,178.46.