JOHN R. TUNHEIM, Chief District Judge.
In a May 13, 2015 Order, this Court granted plaintiff Richland/Wilkin Joint Powers Authority's ("JPA") motion for a preliminary injunction. (Prelim. Inj. Order, May 13, 2015, Docket No. 193.) The Order enjoins ongoing construction on a ring levee being constructed around the North Dakota communities of Oxbow, Hickson, and Bakke ("OHB ring levee"). Intervenor defendant Fargo-Moorhead Flood Diversion Board of Authority ("Authority") now brings this motion to clarify the preliminary injunction. See Steahr v. Apfel, 151 F.3d 1124, 1125-26 (8th Cir. 1998). Intervenor defendant City of Oxbow ("Oxbow") also joins in the motion. They ask the Court to clarify that the preliminary injunction only enjoins "physical construction on the OHB Ring Levee itself, or physical construction necessary to make the OHB Ring Levee functional." (Authority Mem. in Supp. of Mot. to Clarify Prelim. Inj. at 11, June 25, 2015, Docket No. 241.) The parties dispute whether the injunction encompasses a variety of ongoing activities — which are separate from construction of the OHB ring levee itself — including construction of homes that must be moved due to the OHB ring levee; additional utility and infrastructure construction; and relocation work on the Oxbow Country Club. (Decl. of Eric Dodds ("Dodds Decl.") ¶¶ 2-15, June 25, 2015, Docket No. 242.)
The Court will grant the intervenor defendants' motion and clarify that the injunction's scope is limited to construction on the OHB ring levee itself. The Court's preliminary injunction Order explicitly stated that the injunction's scope was "narrow," and that "it applie[d]
In its memorandum opposing the motion to clarify, the JPA targets the housing construction specifically. It argues that because the homes are being moved due to the construction of the OHB ring levee, the construction is inextricably tied to the levee and the reasoning that supports enjoining the levee equally supports enjoining the home construction. The JPA contends that the Authority's reimbursement of homeowners for the relocation means that the Authority is effectively in charge of the home construction and has the authority to halt the construction. Finally, the JPA cites the agreements signed by the homeowners regarding replacement home construction to argue that the agreements themselves call for homeowners to put off relocation until the levee is completed. (See, e.g., Decl. of Valerie Brazfield ¶ 7, July 6, 2015, Docket No. 269.)
The JPA correctly notes that the home construction, utility work, and country club relocation activities, are tied in perceivable ways to the construction of the OHB ring levee. But an order enjoining construction to allow time for environmental review could theoretically touch many activities that are related to the ultimate project at issue. Those connections do not justify an exceedingly broad injunction, however. Instead, the scope of an injunction "should be limited in scope to the extent necessary to protect the interests of the parties." Garrido v. Dudek, 731 F.3d 1152, 1159 (11th Cir. 2013) (internal quotation marks omitted). Moreover, as the Authority points out, an injunction is limited to the parties to the litigation and, in this case, the Authority does not have direct control — and instead only has reimbursement power — over the home construction, and other activities, at issue. (Dodds Decl. ¶¶ 12-14.) Here, the JPA has not shown why it is necessary — in order to protect its interests — to broaden the scope of the injunction, especially given that the entities and individuals who are most directly engaged in this additional construction are not directly controlled by the Authority and are not parties to this case. An injunction that halts construction on the OHB ring levee itself is sufficient to protect the JPA's interests. As a result, the Court will grant the Authority's motion and modify the injunction in order to clarify its language and scope.
Based on the foregoing, and all the files, records, and proceedings herein,
The Preliminary Injunction entered against the Authority on May 13, 2015 [Docket No. 193] is