SOTELO-HOLGUIN v. NORTHRIDGE CONSTRUCTION, INC., CV 16-130-M-DWM. (2017)
Court: District Court, D. Montana
Number: infdco20170622d40
Visitors: 18
Filed: Jun. 21, 2017
Latest Update: Jun. 21, 2017
Summary: ORDER DONALD W. MOLLOY , District Judge . The parties have filed a stipulation of dismissal with prejudice of all claims, third-party claims, and cross claims. (Doc. 32.) Accordingly, IT IS ORDERED that the above-captioned cause is DISMISSED WITH PREJUDICE, each party to pay its own costs and attorney's fees. All pending motions are MOOT and all deadlines are VACATED.
ORDER
DONALD W. MOLLOY, District Judge.
The parties have filed a stipulation of dismissal with prejudice of all claims, third-party claims, and cross claims. (Doc. 32.)
Accordingly, IT IS ORDERED that the above-captioned cause is DISMISSED WITH PREJUDICE, each party to pay its own costs and attorney's fees. All pending motions are MOOT and all deadlines are VACATED.