Stephani W. Humrickhouse, United States Bankruptcy Judge.
This matter came on to be heard upon the motion for summary judgment filed by Curenton Concrete Works, Inc. ("Curenton") regarding the third party complaint of Weaver Cooke Construction, LLC ("Weaver Cooke"), in Raleigh, North Carolina, on March 5, 2014. Although summary judgment is sought on several bases, this order will deal with the issue of whether the statute of limitations bars the negligence and breach of express warranty claims asserted by Weaver Cooke against Curenton.
New Bern Riverfront Development, LLC ("New Bern") is the owner and developer of the SkySail Luxury Condominiums located in New Bern, North Carolina (the "SkySail Project" or the "Project"). On March 30, 2009, New Bern initiated an action in Wake County Superior Court against nine individual defendants related to the alleged defective construction of the SkySail Condos (the "State Action"). The named defendants in the State Action included: New Bern's general contractor, Weaver Cooke; Travelers Casualty and Surety Company of America ("Travelers"); National Erectors Rebar, Inc. f/k/a National Reinforcing Systems, Inc. ("NER")
On November 30, 2009, New Bern filed a petition for relief under chapter 11 of the Bankruptcy Code. The State Action was removed to the United States District Court for the Eastern District of North Carolina on December 16, 2009, and subsequently transferred to this court on February 3, 2010. After voluntarily dismissing its causes of action as to the subcontractors named as defendants in the State Action, New Bern filed its first amended complaint on May 6, 2010, asserting claims against Weaver Cooke; Travelers; National Erectors Rebar, Inc. f/k/a NRS, and the additional parties of J. Davis Architects, PLLC, and Fluhrer Reed, PA.
On May 27, 2010, Weaver Cooke filed an answer to New Bern's first amended complaint and a third-party complaint against Wachovia Bank, National Association and Wells Fargo & Company f/d/b/a Wachovia Corporation. Absent as third-party defendants in Weaver Cooke's original third-party complaint were any of the subcontractors hired by Weaver Cooke during the construction of the SkySail Project.
On June 14, 2012, Weaver Cooke filed its second, third-party complaint asserting claims of negligence, contractual indemnity and breach of express warranty against many of the subcontractors hired during the construction of the SkySail Project, including Curenton. Curenton filed an answer to Weaver Cooke's second, third-party complaint on June 27, 2012, asserting numerous defenses, including the statute of limitations.
On December 20, 2013, Curenton filed a motion for summary judgment regarding all three causes of action alleged by Weaver Cooke. As grounds for summary judgment, Curenton argued: (1) the applicable statute of limitations bars Weaver Cooke's claims of negligence and breach of express warranty; (2) the economic loss rule bars Weaver Cooke's negligence claim; and (3) Weaver Cooke's contractual indemnity claim is barred by N.C. Gen.Stat. § 22B-1. Inasmuch as the resolution of the statute of limitations affirmative defense may dramatically affect the complexion of the litigation, the court has chosen to deal first with that issue as to each third-party defendant.
Simply put, Curenton argues that Weaver Cooke's negligence and breach of warranty claims accrued more than three years prior to the June 14, 2012, filing date of Weaver Cooke's second, third-party complaint. Curenton claims that, due to Weaver Cooke's knowledge of alleged defects attributable to it prior to June of 2009, Weaver Cooke's negligence and breach of warranty claims are time-barred. In response, Weaver Cooke argues that a genuine issue of material fact exists as to when Weaver Cooke discovered the impact of the defects giving rise to its causes of action alleged against Curenton; i.e., Weaver Cooke claims it first discovered the extent of the damage caused by defects attributable to Curenton within three years of its second, third-party complaint.
"[S]ummary judgment is proper `if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.'" Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986) (quoting Fed.R.Civ.P. 56(c)). In making this determination, conflicts are resolved by viewing all facts and inferences to be drawn from the facts in the light most favorable to the non-moving party. United States v. Diebold, Inc., 369 U.S. 654,
With respect to the non-core matter now before the court, there is no dispute as to the relevant facts or applicable law. The court has jurisdiction to enter this order allowing summary judgment, in light of the right of de novo review by the district court. Ward v. United States Dept. of Educ., Case No. 5:13-CV-695-D (E.D.N.C. June 18, 2014), citing Exec. Benefits Ins. Agency v. Arkison, ___ U.S. ___, 134 S.Ct. 2165, 189 L.Ed.2d 83 (2014).
In this proceeding, the court turns to North Carolina state law, and as is typical in this context, the determination of "whether a cause of action is barred by the statute of limitations is a mixed question of law and fact. However, when the bar is properly pleaded and the facts are admitted or are not in conflict, the question of whether the action is barred becomes one of law." Pembee Mfg. Corp. v. Cape Fear Constr. Co., 313 N.C. 488, 491, 329 S.E.2d 350, 353 (1985). North Carolina General Statute § 1-52 provides a three year statute of limitations for actions sounding in tort or contract. N.C. Gen.Stat. § 1-52(1), (5) (2010). Additionally,
N.C. Gen.Stat. § 1-50(a)(5)(f) (2009).
Actions based upon or arising out of the defective or unsafe condition of an improvement to real property include those which seek to "recover damages for breach of a contract to construct or repair an improvement to real property" and those based upon the "negligent construction or repair of an improvement to real property." N.C. Gen.Stat. § 1-50(a)(5)(b) (2009). Curenton argues that, even with the benefit of a discovery rule, which would serve to delay accrual of Weaver Cooke's causes of action against it until the defect became apparent or ought reasonably to have become apparent, Weaver Cooke knew, or reasonably should have known, of defects attributable to Curenton more than three years prior to the filing of the second, third-party complaint.
Specifically, Curenton was responsible for pouring the project's elevated concrete slabs, which included the balcony slabs, the structural post-tension slab for the pool deck and the concrete slabs for the parking deck. The "forms" for Currenton's concrete pours were constructed and removed by another subcontractor, United Forming Incorporated. Weaver Cooke's claims against Currenton relate to the alleged defective construction of the concrete balcony slabs.
To support its argument, Curenton points to the deposition testimony of the management level employees of Weaver Cooke who oversaw and supervised the major construction activities at the SkySail Project. These included Kevin Lloyd, Weaver Cooke's project manager and vice president; Steve Tidey, Weaver Cooke's project superintendent; David Cline, Weaver Cooke's assistant project manager; Raj Garud, Weaver Cooke's project coordinator; and Dan Estes, Weaver Cooke's president. From the record before the court, which includes the depositions of these individuals along with certain affidavits and the parties' pleadings, the following facts may be determined.
First, Weaver Cooke knew about water intrusion at windows and exterior doors, and related damage to condo unit interiors, no later than the spring of 2009.
Second, Weaver Cooke also specifically became aware of the improper balcony sloping and the failure to achieve proper step-downs on the balconies between 2008 and the spring of 2009. Proper balcony sloping and step-downs are intended to provide positive drainage away from the building and its doors; the failure to implement these designs may result in water pooling on balconies. Garud testified that he became aware of improper sloping and water not draining off of the balconies in August of 2008 and that "[e]verybody in Weaver Cooke was aware" of this problem at that time.
However, Weaver Cooke maintains that it was not until March of 2012, when it received the report of the debtor's expert, George Barbour (the "Barbour Report"), that it became aware of the impact of the water intrusion from the balconies. Weaver Cooke argues that this is when the extent of the damages caused by defects attributable to Curenton were first discovered. In addition, Weaver Cooke appears to argue that it was not until it received the Barbour Report, in March of 2012, that it was aware that New Bern sought to hold it liable for work performed by Curenton, and thus, its causes of action against Curenton did not accrue until that time.
The fact that Weaver Cooke may have not known the extent of the damage caused by the water intrusion problem is not material to the legal question of when the statute of limitations with respect to any claim based upon that problem began to run. See Pembee Mfg. Corp. v. Cape Fear Constr. Co., 313 N.C. 488, 329 S.E.2d 350 (1985). In Pembee, the plaintiff had contracted with two parties for the construction of a 30,000 square foot manufacturing plant in July of 1972. Id. at 489, 329 S.E.2d at 351. By January of 1973,
Moreover, Weaver Cooke's argument that it did not know until its receipt of the Barbour Report that it might potentially be held liable by New Bern for alleged defects attributable to Curenton also is not material. The dispositive issue is when Weaver Cooke's own negligence and breach of warranty causes of actions accrued, and that occurred when "the injury, loss, defect or damage [became] apparent or ought reasonably to have [been] apparent." N.C. Gen.Stat. § 1-50(a)(5)(f). Furthermore, New Bern's First Amended Complaint, filed on May 6, 2010, included allegations which put Weaver Cooke on notice that New Bern intended to hold it liable for work performed by Curenton. In its First Amended Complaint, New Bern asserted a breach of contract claim against Weaver Cooke, in which it alleged that:
Plaintiff New Bern Riverfront Development, LLC's First Amended Complaint (Docket Entry 15 at 24-25).
The defects which form the basis of Weaver Cooke's negligence and breach of warranty claims against Curenton are not latent and were known to Weaver Cooke more than three years prior to the filing of its second, third party complaint. Weaver Cooke was aware of water intrusion problems by at least the spring of 2009. Additionally, even though the fact of ponding water on the concrete balconies and water intrusion through the balcony doors, alone, was likely sufficient to put Weaver Cooke on notice of defects attributable to Curenton, Weaver Cooke had actual knowledge of the causes of the water intrusion more than three years before it filed suit. In