Stephani W. Humrickhouse, United States Bankruptcy Judge.
The matter before the court is the district court's remand after appeal of this court's order allowing summary judgment for third-party defendant East Carolina Masonry, Inc. ("ECM") against Weaver Cooke Construction, LLC ("Weaver Cooke") on Weaver Cooke's contractual indemnity claim. For the reasons outlined below, on remand, ECM's motion for summary judgment on this claim will be allowed.
New Bern Riverfront Development, LLC ("New Bern") is the owner and developer of SkySail Luxury Condominiums ("SkySail Project") in New Bern, North Carolina. Weaver Cooke served as the SkySail Project's general contractor, and
With leave of court, Weaver Cooke filed its second third-party complaint on June 14, 2012, asserting claims of negligence, contractual indemnity, and breach of express warranty against many of the subcontractors hired during construction of the SkySail Project, including ECM. In December 2013, many third-party defendants, including ECM as well as third-party defendant Stock Building Supply ("Stock Supply"), filed motions for summary judgment on Weaver-Cooke's claims. ECM filed its motion on December 20, 2013, seeking summary judgment with respect to all three of Weaver Cooke's claims against it. The court ruled on these motions by entering groups of orders pertaining to each of these three primary claims, and, with respect to its order on contractual indemnity, designated the Stock Supply order as the "lead order." On August 22, 2014, the court entered an order granting summary judgment in favor of Stock Supply on the indemnity claim, which was Weaver Cooke's only remaining claim against Stock.
The court subsequently entered orders on summary judgment for other third-party defendants (collectively, the "Related Orders"), including ECM, allowing summary judgment in whole or part on many of the same bases as in the Stock Indemnity Order. That order, and the Related Orders, were certified as final by both this court and the district court for purposes of appeal. In an order entered on August 12, 2016, the district court affirmed the Stock Indemnity Order in part, reversed in part, and remanded for further proceedings. (D.E. 1326, the "District Court Stock Indemnity Order") The district court decided the appeals of the Related Orders on a similar basis, including Weaver Cooke's appeal of this court's order allowing summary judgment for ECM on the indemnity claim.
On May 16, 2017, this court held a status conference to consider the parameters of the matter on remand. The parties collectively agreed that counsel for Stock Supply and Weaver Cooke would take the lead in presenting the primary arguments pertaining to the indemnity issue in a subsequent hearing, after which the court would enter an order resolving the matter on remand as between Weaver Cooke and Stock Supply. Weaver Cooke and Stock Supply presented their arguments in a hearing on July 19, 2017, together with arguments on the closely related matter of Stock Supply's motion to exclude the testimony and expert report of Mr. Barbour (the "Barbour Report").
On September 29, 2017, this court entered its Order on Remand Regarding Stock Building Supply Motion for Summary Judgment on Indemnity Claim and Allowing Motion to Exclude Expert Report (the "Stock Indemnity Remand Order). The court again allowed summary judgment for Stock Supply. (DE 1406). The court excluded Mr. Barbour's report on Daubert grounds, concluding that as to Stock Supply, "[a]t most, the report includes Stock Supply's products and installation as a possible source, and a possible cause, of water intrusion. It establishes no more than that." Id. at 20. Further, the court held that even if the Barbour Report
Id. Finally, the court granted summary judgment to Stock Supply on the alternative ground of Weaver Cooke's contributory negligence vis-a-vis Stock Supply, holding that permitting Weaver Cooke to require Stock Supply to indemnify it "for damages for which Weaver Cooke indisputably was partially responsible would ignore both the language and purpose of § 22B-1; indeed, it would be as if the statute, and the public policy it seeks to protect, did not exist." Id. at 23. Weaver Cooke sought to appeal this order, but the court declined to certify it as final, and the appeal was dismissed by the district court.
After entry of the Stock Indemnity Remand Order, the court granted to ECM and similarly situated parties the opportunity to file short briefs addressing the extent to which the reasoning in that order applied to their particular fact set. Unfortunately, most of the briefs advanced one-size-fits-all "me too" arguments without acknowledging pertinent differences in what the party actually argued in its motion for summary judgment (as opposed to what Stock Supply argued), and without focusing on the existence or lack of undisputed facts that could establish that Weaver Cooke was contributorily negligent as to them.
To address the matter on remand, the court examines the initial pleadings, its original orders, and the issues addressed therein with respect to ECM. In its third-party complaint, Weaver Cooke alleged that ECM caused injury to it by reason of: "(1) improper brick tie installation; (2) lack of a soft joint (i.e. horizontal expansion joint) below steel shelf angles; (3) lack of mastic applied to laps and terminations in self-adhered flashing membrane; and (4) improper installation of mortar nets," all of which were identified in the Barbour Report and the report of Sutton-Kennerly & Associates as issues requiring correction. D.E. 686 at 10. In its motion for summary judgment, ECM argued that the applicable statute of limitations barred Weaver Cooke's claims of negligence and breach of express warranty, that the economic loss rule barred Weaver Cooke's negligence claim, and that Weaver Cooke's contractual indemnity claim was barred by N.C. Gen. Stat. § 22B-1. Like Stock Supply, ECM argued that "the uncontroverted evidence demonstrates that, if any defects were present in ECM's work, those defects were caused, at least in part, by Weaver Cooke's negligent management, supervision, and sequencing, thereby precluding its right to indemnity." Id. at 6. And, ECM raised the issue of whether Weaver Cooke could satisfy the proximate cause component of its contractual indemnity claim, arguing that these reports "identify only alleged defects in ECM's work and the potential that water damage to the SkySail [Project] might have resulted from such defects." Id. at 11. Weaver Cooke filed a memorandum in response, and ECM filed a reply. (D.E. 754, 809)
With regard to Weaver Cooke's contractual indemnity claim, the court entered an order allowing ECM's motion for summary judgment
Indemnity Remand Order at 8-9 (construing District Court Stock Indemnity Order).
On Weaver Cooke's appeal of this court's entry of the ECM Indemnity Order (D.E. 954), wherein the court entered summary judgment for ECM on the indemnity claim, the district court entered a short order in which it affirmed in part, reversed in part, and remanded based on the reasoning in the District Court Stock Indemnity Order, discussed above. (D.E. 1328) In addition, the district court noted in a footnote that
Id. at 1 n.1 (emphasis added). Both ECM and Weaver Cooke have filed supplemental memoranda addressing the indemnity question remanded to this court, as well as the particular arguments noted by the district court, and the matter on remand is ripe for disposition.
In both of its supplemental memoranda, ECM focused on the contributory negligence issue, to the exclusion of the first issue cited by the district court. D.E. 1413, 1509. Weaver Cooke did the same. D.E. 1436, 1518. The court will, however, address both of those issues, as well as the related question of proximate cause.
The specific damages that Weaver Cooke alleges ECM to have caused are set out in the Barbour Report, wherein Mr. Barbour opines that ECM failed to:
ECM Mem. in Support of Sum. J. at 4-5 (D.E. 686) ("ECM Mem."). In addition, Mr. Barbour faulted ECM for allegedly installing brick veneer where shelf angles were missing.
Id. at 7.
Before the court now are issues raised in ECM's initial motion for summary judgment, and noted by the district court as remaining unresolved and therefore potentially viable on remand: First, whether, under the specific terms of the subcontract, Weaver Cooke is entitled to seek indemnity from ECM for injury or damage to ECM's own work; specifically, the masonry work. For the reasons set out below, the court will enter summary judgment for ECM on this ground. To the extent that Weaver Cooke theoretically could still pursue its contractual indemnity claim for water intrusion damages outside the scope of ECM's work, the court will enter summary judgment for ECM on the alternative ground originally raised in ECM's summary judgment motion, which is that Weaver Cooke failed to establish the element of proximate cause. Finally, the district court observed that the question of whether ECM and Weaver Cooke are in pari delicto—i.e., whether Weaver Cooke was contributorily negligent with respect to the specific damages at issue vis-a-vis ECM—also remained open for disposition. Because the contractually indemnity claim is fully resolved by the court's conclusions as set out below, the court need not, and does not, consider the issue of contributory negligence.
The district court pointed out in its order that this court had not yet addressed ECM's argument, set out in its original motion for summary judgment, that "even if Weaver Cooke's own failure to properly supervise ECM's work does not completely preclude it from receiving indemnity, the damages for which it is entitled to indemnity are limited by the terms of the subcontract." D.E. 1328 at 1 n.1; see also ECM Mem. (D.E. 686) at 32. The language to which the district court and ECM refer provides as follows:
D.E. 686, Ex. 1, ¶ 16.2 (emphasis added). The subcontract between Weaver Cooke and ECM defines the "Subcontractor's Work" in Attachment A-1 to their subcontract, as follows: "Work includes furnishing and installing brick, concrete masonry units, cavity insulation, joint reinforcing, wall ties, grout, thru-wall flashing, preformed control joints, dove tail anchors, mortar stop, dampproofing, clean up, mortar, sand, supervision, labor, equipment, and taxes." D.E. 686-1, at 4.
It is evident that ECM's unique fact set is such that there are two separate "kinds" of possible damages—those allegedly caused by leaking water, and, those damages Weaver Cooke attributes purely to the brickwork not being properly done, per the expert reports upon which Weaver Cooke relies. Here, it is abundantly clear that only "the issues with the through-wall flashing and mortar netting are related to water intrusion." Weaver Cooke Response at 7. The remainder "are structural in nature and have nothing to do with water intrusion." Id. It is readily apparent that the alleged "structural" damages come squarely within the scope of ECM's "Work" and, for that reason, they are specifically and wholly excluded from the scope of damages for which Weaver Cooke may endeavor to seek indemnification.
Moreover, with respect to these remaining potential damages in connection with thru-wall flashing and mortar netting, notwithstanding Weaver Cooke's contention that there are defects in these construction elements that are in some way "related to water intrusion," that position in no way changes the fact that thru-wall flashing and mortar netting also are specifically and wholly within ECM's scope of work. Again, per the language of its own subcontract, Weaver Cooke may seek indemnity for those damages "arising out of or resulting from Subcontractor's performance of Subcontractor's Work, provided that such claim, damage, loss or expense is attributable to . . . injury to or destruction of tangible property (other than Subcontractor's Work itself)." D.E. 686, Ex. 1, ¶ 16.2 (emphasis added). To the extent that Weaver Cooke seeks damages based on alleged injury to these components, that recovery is precluded by the language just discussed. In contrast, to the extent that Weaver Cooke seeks to argue that deficiencies in ECM's installation of the thru-wall flashing and mortar netting ultimately caused water intrusion damages to the SkySail Project—i.e., damages to tangible property other than ECM's "Work itself"—then that argument would be viable, in theory. In practice, however, for the reasons set out below, that argument is
In its original motion for summary judgment, ECM argued that Weaver Cooke's "catch-all inclusion of whatever defects and damage plaintiff or any experts may assert" rests on the Barbour Report and Sutton-Kennerly & Associates reports, which "identify only alleged defects in ECM's work and the potential that water damage to the SkySail [Project] might have resulted from such defects." D.E. 686 (ECM Mem in Supp. of Sum. J.) at 11. The "proximate cause argument also relates to the remanded indemnity issue because § 22B-1 is a negligence-based statute, such that traditional negligence analyses apply." Stock Indemnity Remand Order (D.E. 1406) at 9. Under the language of the contractual indemnity provision as discussed above, the only damages potentially recoverable by Weaver Cooke would be those caused by, but outside the scope of, ECM's "Work"—i.e., water intrusion damages.
In its memorandum, ECM noted that "[w]hen asked in discovery what such injuries were proximately caused by ECM's negligence, Weaver Cooke Pointed to only the four defects in ECM's work alleged by Mr. Barbour and the potential of damage to SkySail." ECM Mem. (D.E. 686) at 10 (emphasis added). Specifically, in response to ECM's interrogatories asking Weaver Cooke to "describe with specificity the basis of Weaver Cooke's determination [that] the alleged problems, defects or issues, were caused by ECM," Weaver Cooke replied:
Id. On that basis, ECM maintained that Weaver Cooke failed to make a sufficient showing of proximate cause.
Weaver Cooke's memorandum in response to ECM's motion for summary judgment provides, in relevant part, as follows:
D.E. 754 at 8-9 (citations to Estes and Connor affidavits omitted). Addressing the question of proximate cause, Weaver Cooke responded that "there is a genuine dispute of material fact pertaining to causation" in that
Id. at 21; see also Weaver Cooke Response to ECM Mem. in Response to [Stock Indemnity Remand Order] (D.E. 1436) at 10-11 (citing this paragraph in response to the court's request to bring forward the bases upon which the analyses contained in the Stock Indemnity Remand Order do, or do not, pertain as to Weaver Cooke v. ECM).
The court has not ruled on this question in the Weaver Cooke-ECM context, though, to be sure, the parties should be expecting it. Weaver Cooke maintained in its first supplemental memoranda to the court that there remains a "genuine issue of material fact pertaining to causation, the second element needed to establish contributory negligence." D.E. 1436 at 10. As Weaver Cooke knows, causation also is a
In establishing the elements of negligence, made necessary here by the contractual indemnity provision requiring such a showing, the burden in the summary judgment context was and is on Weaver Cooke as the proponent of its claim to put forth admissible, relevant evidence sufficient to establish the existence of genuine issues of material fact as to whether the acts or omissions it attributes to ECM proximately caused the water-related damages of which it now complains.
Unfortunately, Weaver Cooke didn't address the matter with specificity in its initial memorandum in response to ECM's motion for summary judgment, and also failed to address it in either of its two supplemental responses, other than to contend that "the only issues available to ECM on remand are those specifically identified by the District Court." D.E. 1436 at 6. The Barbour testimony appended by Weaver Cooke to its responsive memoranda does not speak to whether any of the flaws Mr. Barbour perceived in ECM's work caused actual water intrusion and/or actual water damage. Weaver Cooke has not cited to this court any specific language from the Barbour Report, or the Sutton-Kennerly & Associates report, that could support this crucial factor in Weaver Cooke's claim.
For the foregoing reasons, the court on remand concludes that ECM's motion for
SO ORDERED.
In the Related Orders, the district court cited the District Court Stock Indemnity Order and noted that in it, "the identical indemnification provisions were at issue, and this court held, among other things, neither N.C. Gen. Stat. § 22B-1 nor the contributing negligence of other parties precluded Weaver Cooke's indemnification claim against the subcontractor." See, e.g., Weaver Cooke Constr. LLC v. Curenton Concrete Works, Inc., Order at 1 n.1 (D.E. 1327).
Further, the bankruptcy court denied ECM's motion for summary judgment on grounds that Weaver Cooke failed to state a claim for breach of express warranty. The court concluded that the claim was in essence a breach of contract claim, and that Weaver Cooke had presented sufficient evidence to create a genuine issue of material fact with respect to whether ECM had breached the contract and was responsible for the ensuing damages. (D.E. 969 at 6-7) ECM moved for reconsideration, which the court denied. (D.E. 1133) On appeal, the district court affirmed both orders, agreeing that the allegations sufficiently alleged a breach of contract claim. (D.E. 1318)
Finally, the court entered a separate order specifically addressing ECM's contributory negligence defense, which it had asserted as a bar to Weaver Cooke's negligence claim. (D.E. 961) In that order, the court concluded that "genuine issues of material fact still exist as to whether Weaver Cooke was negligent in failing to identify the defects in ECM's work of which it now complains," and denied the motion on that basis. Id. at 7.
Order [Denying] Summary Judgment Regarding Statute of Limitations Defense Asserted by Randolph Stair and Rail Co. at 7 (August 27, 2014) (D.E. 905).