STEPHANI W. HUMRICKHOUSE, Bankruptcy Judge.
The matter before the court is the district court's remand after appeal of this court's order allowing summary judgment for third-party defendant Randolph Stair & Rail Co. ("Randolph Stair") against Weaver Cooke Construction, LLC ("Weaver Cooke") on Weaver Cooke's contractual indemnity claim. For the reasons outlined below, on remand, Randolph Stair's motion for summary judgment on this claim will be allowed.
New Bern Riverfront Development, LLC ("New Bern") is the owner and developer of SkySail Luxury Condominiums ("SkySail Project") in New Bern, North Carolina. Weaver Cooke served as the SkySail Project's general contractor, and Randolph Stair as the subcontractor who installed floorline relief angles, or shelf angles, as a structural component of the brick veneers on the project's exterior walls. New Bern filed a state court action against Weaver Cooke and others in March 2009, and filed a petition for relief under Chapter 11 of the Bankruptcy Code in November 2009. The state court action was removed to the United States District Court for the Eastern District of North Carolina, and subsequently transferred to this court.
With leave of court, Weaver Cooke filed its second third-party complaint on June 14, 2012, asserting claims of negligence, contractual indemnity, and breach of express warranty against many of the subcontractors hired during construction of the SkySail Project, including Randolph Stair. In December 2013, many third-party defendants, including Randolph Stair as well as third-party defendant Stock Building Supply ("Stock Supply"), filed motions for summary judgment on Weaver-Cooke's claims. Randolph Stair filed its motion on December 20, 2013, seeking summary judgment with respect to all of Weaver Cooke's claims against it (D.E. 688, 689), and incorporating by reference the memorandum in support of summary judgment filed by East Carolina Masonry, Inc. ("ECM")
The court subsequently entered orders on summary judgment for other third-party defendants (collectively, the "Related Orders"), including Randolph Stair, allowing summary judgment in whole or part on many of the same bases as in the Stock Indemnity Order. That order, and the Related Orders, were certified as final by both this court and the district court for purposes of appeal. In an order entered on August 12, 2016, the district court affirmed the Stock Indemnity Order in part, reversed in part, and remanded for further proceedings. (D.E. 1326, the "District Court Stock Indemnity Order") The district court decided the appeals of the Related Orders on a similar basis, including Weaver Cooke's appeal of this court's order allowing summary judgment for Randolph Stair on the indemnity claim.
On May 16, 2017, this court held a status conference to consider the parameters of the matter on remand. The parties collectively agreed that counsel for Stock Supply and Weaver Cooke would take the lead in presenting the primary arguments pertaining to the indemnity issue in a subsequent hearing, after which the court would enter an order resolving the matter on remand as between Weaver Cooke and Stock Supply. Weaver Cooke and Stock Supply presented their arguments in a hearing on July 19, 2017, together with arguments on the closely related matter of Stock Supply's motion to exclude the testimony and expert report of Mr. Barbour (the "Barbour Report").
On September 29, 2017, this court entered its Order on Remand Regarding Stock Building Supply Motion for Summary Judgment on Indemnity Claim and Allowing Motion to Exclude Expert Report (the "Stock Indemnity Remand Order)". The court again allowed summary judgment for Stock Supply. (DE 1406). The court excluded Mr. Barbour's report on Daubert grounds, concluding that as to Stock Supply, "[a]t most, the report includes Stock Supply's products and installation as a possible source, and a possible cause, of water intrusion. It establishes no more than that." Id. at 20. Further, the court held that even if the Barbour Report
Id. Finally, the court granted summary judgment to Stock Supply on the alternative ground of Weaver Cooke's contributory negligence vis-a-vis Stock Supply, holding that permitting Weaver Cooke to require Stock Supply to indemnify it "for damages for which Weaver Cooke indisputably was partially responsible would ignore both the language and purpose of §22B-1; indeed, it would be as if the statute, and the public policy it seeks to protect, did not exist." Id. at 23. Weaver Cooke sought to appeal this order, but the court declined to certify it as final, and the appeal was dismissed by the district court.
After entry of the Stock Indemnity Remand Order, the court granted to Randolph Stair and similarly situated parties the opportunity to file short briefs addressing the extent to which the reasoning in that order applied to their particular fact set. Unfortunately, most of the briefs advanced one-size-fits-all "me too" arguments without acknowledging pertinent differences in what the party actually argued in its motion for summary judgment (as opposed to what Stock Supply argued), and without focusing on the existence or lack of undisputed facts that could establish that Weaver Cooke was contributorily negligent or had failed to show proximate cause as to them.
To address the matter on remand, the court examines the initial pleadings, its original orders, and the issues addressed therein with respect to Randolph Stair. The claims asserted by Weaver Cooke against Randolph Stair in its third-party complaint (D.E. 345) arise out of shelf angles allegedly missing from certain areas of the SkySail project. See, e.g., D.E. 756 at 6, D.E. 1324 at 1. Like Stock Supply, and in this instance by specifically adopting the arguments advanced by ECM, Randolph Stair argued in its motion for summary judgment that Weaver Cooke was contributorily negligent in ways that precluded its contractual indemnity claim. ECM's Mem. of Law in Supp. of Its Mot. for Sum. Judg. (D.E. 686) at 19-31. In particular, Randolph Stair adopted ECM's argument that "the uncontroverted evidence demonstrates that, if any defects were present in ECM's work, those defects were caused, at least in part, by Weaver Cooke's negligent management, supervision, and sequencing, thereby precluding its right to indemnity." Id. at 6. Also among the contentions adopted by Randolph Stair: ECM's argument that the language of the subcontract precluded the contractual indemnity claim. Id. at 32-34. Weaver Cooke filed memoranda in response to both Randolph Stair (D.E. 743, 746) and ECM (D.E. 754), and Randolph Stair filed a reply. (D.E. 808)
With regard to Weaver Cooke's contractual indemnity claim, the court entered an order on September 26, 2014, wherein the court allowed Randolph Stair's motion for summary judgment on the same grounds set forth in the Stock Indemnity Order and also "for the reasons set forth in the order of September 26, 2014 granting ECM's motion for summary judgment."
Order on Appeal at 6. In addition, the district court agreed with Weaver Cooke's challenge "to the bankruptcy court's conclusion to award summary judgment to Stock on Weaver Cooke's indemnification claim on the alternative ground of contributory negligence." Id. at 7. Applying the same rationale as before, the district court held that this court erred in "conclud[ing] Weaver Cooke could not seek indemnification from Stock as Stock did not `wholly' cause the damages at issue," and held that neither the statute nor the subcontract "prohibits indemnification where parties in addition to the promisee/subcontractor are negligent." Id. (emphasis added).
Ultimately, the district court reversed the Indemnity Order on grounds that "the provision in this case permits Weaver Cooke to recover in indemnification for damages arising out of Stock's performance of its work and caused by Stock's (or its agents[']) negligence, irrespective of whether other parties were negligent too and contributed to the damages." Id. at 8. The district court remanded the Indemnity Order for further proceedings in accordance with its order. Finally, the district court also noted, in concluding, that
Stock Indemnity Remand Order at 8-9 (construing District Court Stock Indemnity Order).
On Weaver Cooke's appeal of this court's entry of the Randolph Stair Indemnity Order (D.E. 958), wherein the court entered summary judgment for Randolph Stair on the indemnity claim, the district court entered a short order in which it affirmed in part, reversed in part, and remanded based on the reasoning in the District Court Stock Indemnity Order, discussed above. (D.E. 1330) In some of district court's dispositions on appeal, its order included a footnote acknowledging various remaining issues that the parties had brought to its attention as remaining unresolved in the proceedings before this court. With Randolph Stair, the district court's order did not include such a notation.
D.E. 958 at 1 n.1 (emphasis added). On June 26, 2018, this court entered its order on remand allowing summary judgment for ECM on the indemnity claim. ECM Indemnity Remand Order (D.E. 1568). As noted earlier, Randolph Stair has consistently adopted the arguments advanced in ECM's written memoranda as its own. In addition, both Randolph Stair and Weaver Cooke have filed supplemental memoranda responsive to the court's request that they address the indemnity question remanded to this court, and the matter on remand is ripe for disposition.
In both of its supplemental memoranda, and most particularly in its reply memorandum (D.E. 1441), Randolph Stair argued that the contributory negligence analysis as set forth in the Stock Indemnity Remand Order is the basis upon which this court should allow summary judgment in its favor on the remanded contractual indemnity issue. It specifically declined to advance any arguments with respect to proximate cause, and expressly stated in its reply brief that it "does not contend the proximate cause analysis in the Stock Remand Order applies to it, as Weaver Cooke's Response suggests." (D.E. 1441 at 1) The court, however, will allow Randolph Stair's motion on grounds that were discussed in the ECM Indemnity Remand Order and are equally applicable to Randolph Stair: Namely, that the indemnity agreement excludes damages to the subject of the contract, i.e. "the Work."
Randolph Stair is the subcontractor retained by Weaver Cooke to install shelf angles, which are steel angles "attached to a building's floor slabs and integrated into the brick veneer to provide both support for the load of brick veneer and to allow for a gap, or space, between the building and the brick veneer." ECM Indemnity Remand Order (D.E. 1568) at 12 n.5. Randolph Stair's work was closely linked to that of ECM in that the shelf angles installed by Randolph Stair subsequently were used by ECM as a necessary component of its installation of brick ties, and, eventually, the building's brick veneer. According to Weaver Cooke:
Weaver Cooke's Mem. in Response to Randolph Stair Mot. for Sum. Judg. (D.E. 756, "Weaver Cooke Response") at 6 (emphasis added). With regard to Weaver Cooke's claims against Randolph Stair, "the gist of the claims is that Randolph [Stair] failed to install an adequate number of shelf angles as called for in the project's specifications and that this resulted in structural deficiencies in the brick." Order Allowing Motion for ECM for Sum. Judg. on Indem. Claim (D.E. 954) at 25.
As discussed in the ECM Indemnity Remand Order, the district court pointed out in its order remanding as to ECM that this court had not yet addressed the argument, set out in ECM's original motion for summary judgment, that "even if Weaver Cooke's own failure to properly supervise ECM's work does not completely preclude it from receiving indemnity, the damages for which it is entitled to indemnity are limited by the terms of the subcontract." D.E. 1328 at 1 n.1; see also ECM Mem. (D.E. 686) at 32; Randolph Stair Mem. (D.E. 689) (incorporating ECM Mem.). The language to which the district court (and ECM) referred is identical to the language used in the Weaver Cooke-Randolph Stair subcontract, and provides as follows:
D.E. 686, Ex. 1, ¶ 16.2 (emphasis added). The subcontract between Weaver Cooke and Randolph Stair defines the "Subcontractor's Work" in Attachment A-1 to the subcontract, as follows:
Weaver Cooke Response (D.E. 756) at 66 (Attachment A).
Weaver Cooke has acknowledged that the damages it attributes to Randolph Stair are "purely structural" and have nothing to do with water intrusion. The alleged structural damages are those set forth in the Barbour Report, and with regard to Randolph Stair, the report provides that Mr. Barbour observed, from construction phase photos, that "shelf angles were omitted in numerous locations on all building elevations," and that shelf angles "were not mitered and welded at building corners as specified in 2.10.A.1." D.E. 756 at 97 (Attachment G). From site visits, Mr. Barbour concluded that floor line shelf angles "were omitted and/or discontinuous in several observed locations. Furthermore, the shelf angles were not welded at corners and in fact did not extend around corners in any location observed." Id. Based on these observations, along with additional observations pertaining to construction elements within ECM's (not Randolph Stair's) scope of work, Mr. Barbour set forth the following analysis:
Id. at 98.
The question of whether there was damage to property outside the scope of the parties' contract (as opposed to the scope of "the Work") was addressed by the district court in its order affirming this court's order allowing summary judgment for Randolph Stair on the economic loss issue. (D.E. 1373) Interestingly, in that context, it appears that Weaver Cooke advanced the wholly unsupported position
In its original memorandum, Weaver Cooke argued that "[c]ontrary to the assertions of Randolph [Stair], its indemnity obligation is not limited to only claims for "`bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than Subcontractor's Work itself).'" D.E. 756 at 53. As it did in the ECM Indemnity Remand Order, the court disagrees. For the same reasoning set forth in that order, the court concludes that any alleged insufficiency as to the quantity or placement of the shelf angles installed by Randolph Stair is wholly within the scope of Randolph Stair's "Work." "To the extent that Weaver Cooke seeks damages based on alleged injury to these components, that recovery is precluded by the language just discussed." D.E. 1568 at 15. Moreover, the court finds, based on the broader interpretation of "scope of work" used by the district court in its discussion of the economic loss rule, that any damage to the brick veneer (including, in particular, the cracking cited by the district court) also comes within the scope of Randolph Stair's "Work."
The economic loss rule obviously does not, itself, determine the parameters of whether the damages Weaver Cooke attributes to Randolph Stair are within, or outside, the scope of "the Work." Applying the rule, this court already has found that it precluded Weaver Cooke from recovering on the negligence claim because the "installation of shelf angles is integrally related to construction of the brick veneer. Any defect in the installation of shelf angles would necessarily affect the brick veneer." D.E. 934 at 7. "For purposes of the economic loss rule," the court concluded, "the damages alleged to the brick veneer relate to the subject of Randolph Stair's contract, i.e., installation of the anchors for the brick veneer." Id. On appeal, the district court affirmed and took a broader view of what work would be included within a contract's scope of work, as opposed to relating to damage to property other than that which was the subject of the contract. D.E. 1373 at 3-5.
The court finds the district court's analysis of the rule to be both informative and persuasive. Further, the court sees no sound basis upon which it could conclude, using the district court's broader view, that the damages for which Weaver Cooke seeks contractual indemnity (and which must be based on a showing of negligence) are for damage outside the scope of Randolph Stair's "Work." Summary judgment will be granted to Randolph Stair on this basis.
For the foregoing reasons, the court on remand concludes that Randolph Stair's motion for summary judgment on the contractual indemnity claim is
In the Related Orders, the district court cited the District Court Stock Indemnity Order and noted that in it, "the identical indemnification provisions were at issue, and this court held, among other things, neither N.C. Gen. Stat. § 22B-1 nor the contributing negligence of other parties precluded Weaver Cooke's indemnification claim against the subcontractor." See, e.g., Weaver Cooke Constr. LLC v. Curenton Concrete Works, Inc., Order at 1 n.1 (D.E. 1327).
The court entered a separate order allowing Randolph Stair's motion for summary judgment on grounds that Weaver Cooke's negligence claim was barred by the economic loss rule. (D.E. 934) On appeal, the district court affirmed. (D.E. 1373)
In sum, Weaver Cooke's negligence claim against Randolph Stair is no longer viable, but its breach of express warranty claim remains.