CATHARINE R. ARON, Bankruptcy Judge.
THIS CASE is before the Court, sua sponte, with respect to the Court's October 7, 2016 order [Doc. #116] (the "Supplementary Order"). For the reasons as stated below, the Court finds that the Supplementary Order should be amended, and the parties should prepare for trial with respect to whether any of the payments at issue in this case are protected from avoidance under 11 U.S.C. §§ 546(e) or (g).
This Court has jurisdiction over the subject matter of this proceeding pursuant to 28 U.S.C. §§ 1334 and 157(a) and Local Rule 83.11 of the District Court for the Middle District of North Carolina. This is a core proceeding under 28 U.S.C. § 157(b)(2) which this Court may hear and determine. Both parties have consented to entry of final order by the Court. [Doc. #20].
On October 7, 2016, this Court entered an order [Doc. #116] (the "Supplementary Order") which amended two prior orders of the Court, the Summary Judgment Order and the Order Partially Granting and Partially Denying Summary Judgment.
The Court now recognizes that in applying Huston v. E.I. du Pont de Nemours and Co., Inc. (In re Nat'l Gas Distribs., LLC), 556 F.3d 247 (4th Cir. 2009) to Contract 277.2, its analysis should have focused on whether the appropriate maturity date was fixed at the time of contracting. See id. at 260. Moreover, the Court also notes that genuine issues of material fact still exist as to whether payments made pursuant to the remaining Pricing Confirmation Documents constitute payments subject to exception from the Trustee's avoidance powers under 11 U.S.C. §§ 546(e) or (g); the Court relied on the Sales Settlement Sheets to find that forward contracts existed in this case, impliedly finding that the Sales Settlement Sheets contained the fixed quantity and time elements of a forward contract, and erred when it did so.
Therefore, the Court finds it necessary to amend the Supplementary Order to recognize these errors and to instead direct the parties to prepare for trial on whether any payments are subject to exception from the Trustee's avoidance powers under 11 U.S.C. §§ 546(e) or (g). Specifically, the parties should prepare to present evidence to the Court with respect to whether each Pricing Confirmation Document, together with the Feedstock Supply Agreement, contains the elements of a forward contract under Huston v. E.I. du Pont de Nemours and Co., Inc. (In re Nat'l Gas Distribs., LLC), 556 F.3d 247 (4th Cir. 2009).
NOW, THEREFORE, FOR THE ABOVE STATED REASONS, THE COURT HEREBY ORDERS THAT: