CHARLES S. MILLER, JR., Magistrate Judge.
Before the court are the following motions:
Unless otherwise indicated, the following facts have either not been reasonably controverted or are stated most favorably for Estvold.
Estvold is an oilfield services company that is headquartered several miles east of New Town, North Dakota, where it has a number of building and other structures at several rural locations all within several miles or less of each other. Relevant to this case, these include:
For ease of reference, these locations may be referred to as the 84th Ave., the 4211 Hwy 8, and the 39th St. locations, respectively.
This case arises out of a fire that occurred at the 39th St. location in May 2016, which Hanover, Estvold's property insurance carrier, refused to cover because the 39th St. location was not listed on the schedule of insured locations in its policy. In this action, Estvold sues Hanover on several different theories claiming that the structure at the 39th St. location was included in the policy but was erroneously listed as being at the 4211 Hwy 8 location, which was also erroneously described as being near Richardton, N.D. and not New Town. Estvold also sues PayneWest, its insurance broker, on several different theories alleging that PayneWest was responsible for the mistakes in its policy and Hanover's refusal to cover the loss.
Prior to January 2015, Estvold used Leavitt Great West Insurance Services ("Leavitt") as its broker for the procurement of insurance. In late 2014, PayneWest, a competing broker, made a sales call upon Estvold for the purpose of securing its business. In January 2015, Estvold decided to switch it business and entered into an agreement with PayneWest for brokerage services. For a flat fee of $60,000 per year, PayneWest would (1) place the coverages elected by Estvold after obtaining PayneWest's advice on what coverages were available and would be appropriate, and (2) provide a number of additional ancillary services. While the language of the written contract is somewhat general, PayneWest represented to the North Dakota Insurance Department in securing its approval of the agreement that PayneWest would be providing the following services to the Estvold:
On January 14, 2015, there was an in-person meeting in one of Estvold's shops at the 84th Ave. location to discuss a proposal that PayneWest would submit to various insurance carriers to obtain quotes for the upcoming policy year beginning January 31, 2015. Attending the meeting from Estvold were Mike Borgschatz, who was taking the lead in procuring the insurance on behalf of Estvold, and Chander Rush, who had a much lesser role. The persons attending on behalf of PayneWest included Brady Hoiness and his brother Devon Hoiness who were the PayneWest principals responsible for the engagement.
At that point, PayneWest's draft proposal was incomplete in terms of the property to be covered. What was discussed during the meeting with respect to what additional property Estvold wanted covered and where it was all located is disputed. Relevant to what follows, Borgschatz testified in his deposition that he advised PayneWest that one of the additional properties Estvold wanted covered was a building Estvold was in the process of constructing located less than a mile away and kitty-corner from the shop at which they were meeting. Borgschatz testified there was some discussion about the advisability of the contractor having builder's risk insurance on the property, but that he wanted Estvold to have its own coverage up to a million dollars. He testified that Brady Hoiness asked about the address and he (Borgschatz) told him that a street address had not yet been assigned to the rural lot that ultimately became 8449 39th St. Borgschatz testified that Brady Hoiness assured him this would not be a problem.
Following this meeting, PayneWest revised the proposal one or more times before soliciting its final quote from Hanover to include additional properties. It is not clear whether the proposal as finally revised and sent out for quote to Hanover's broker was forwarded to Estvold prior to PayneWest binding coverage with Hanover for the policy period beginning January 31, 2015 and ending January 31, 2016.
The following are the locations that were ultimately included in the Hanover policy as covered locations. While in a slightly different format, the information is the same as set forth in the policy:
It appears that the locations added to PayneWest's proposal prior to obtaining the final quote from Hanover were numbers 2-2, 3-1, 4-1, 4-2, and 4-3. In obtaining the final quote from Hanover, PayneWest did not deal directly with Hanover. Rather, it worked with Hanover's broker, Sloan Mason.
After PayneWest submitted its revised proposal to Sloan Mason that included the additional properties, Sloan Mason responded that more information was required for the properties listed in the proposal for purposes of Hanover's underwriting. It appears that PayneWest then obtained, from sources not entirely clear at this point, the additional information with respect to the properties, including that which was listed in the Hanover policy as Loc. No. 4-1. The additional information with respect to location 4-1 was that it was an 11,000 sq. ft. steel building along with a date of 2011. While this additional detail was not specifically set forth in the final policy, it appears to have been provided by PayneWest to Sloan Mason prior to coverage being bound. This is because Hanover's quote stated in relevant part with respect to Loc. No. 4-1:
In other words, to put a finer point on it, this is the information that Hanover had when it agreed to provide coverage for the building at Loc. No. 4-1.
Estvold claims in this case that PayneWest made two errors in the information it provided to Sloan Mason and upon which Hanover scheduled its coverage that are material to this case. The first is that since Estvold had no property in the vicinity of Richardton, N.D., the information that PayneWest provided and that resulted in the policy listing Loc. Nos. 4-1, 4-2, & 4-3 as being at 4211 Hwy 8, Richardton, N.D. was erroneous to that extent. The proper address for Loc. Nos. 4-2 and 4-3 is 4211 Hwy 8, New Town, N.D. With respect to Loc. No. 4-1, the situation is more complicated and will be returned to in a moment.
For those readers of this order not familiar with North Dakota geography, New Town is located on the north side of Lake Sakakawea on the Fort Berthold Indian reservation in Mountrail County. It is in heart of the active oilfield operations. Richardton, on the other hand, is located along I-94 some 75 miles south of New Town in Stark County. It is well south of the Fort Berthold Indian Reservation and on the periphery of active oilfield operations.
It is clear from the record that the "wrong city" mistake was initially made by Brady Hoiness. When Sloan Mason asked for specific addresses for the property in the PayneWest proposal, Brady Hoiness had 4211 Hwy 8 as a location for certain of the additional property. Hoiness testified in his deposition that to get more detailed information he inputted that address into Google Earth and the only location that popped up was 4211 Hwy 8, Richardton, North Dakota, so he provided that address to Hanover's broker by email for the property at Loc Nos 4-1, 4-2, & 4-3. Notably, he did not check with Estvold, apparently not curious as to why Estvold had locations in a City different from what had been discussed up to that point and different from Estvold's principal base of operation, which was New Town. Brady Hoiness's "wrong city" mistake was further compounded by PayneWest when his brother Devon Hoiness discovered the mistake and provided the correct address to other PayneWest personnel who then failed to input the corrected address into its system. The net result was that the final proposal printed out from PayneWest's system and sent to Sloan Mason for quote referenced Richardton for the 4-1, 4-2, and 4-3 locations and not New Town.
The second mistake that Estvold claims that PayneWest made is that it has only two buildings at the 4211 Hwy 8 location and those are the buildings that were scheduled in the Hanover policy as Loc. Nos 4-2 and 4-3. Estvold claims that the building that was scheduled as Loc. No. 4-1 at 4211 Hwy 8 was the building that it had under construction at the 39th St. location less than a mile from its main shops where the January 2015 meeting with PayneWest took place and several miles south of the buildings at the 4211 Hwy 8 location.
What is not clear from the record presently before the court is how Loc. No. 4-1 got into the policy and whether PayneWest intended Loc. No. 4-1 to be the 39th St. building that was under construction and that ultimately suffered the fire loss. There is some evidence that PayneWest took the 4-1, 4-2, and 4-3 locations at 4211 Hwy 8 off a competing proposal made by Leavitt, but the circumstances under which it may have done so remain murky and leave a number of unanswered questions. These include: What, if anything, did PayneWest do to confirm the information it used from the Leavitt proposal? Assuming PayneWest was told by Estvold that it wanted the building that was under construction to be covered, how and why did PayneWest assume that the new building was located at 4211 Hwy 8, Richardton, North Dakota if it was told it was being constructed less than a mile from Estvold's main shops just outside of New Town? Or, did PayneWest forget about the building under construction (again assuming it had been told about it) and then assume there were three other buildings that needed to be covered at the 4211 Hwy location?
As noted earlier, it is not clear what, if any, of PayneWest's last minute changes to the property being included for coverage were contemporaneously communicated back to Estvold. Also, it is not clear whether Estvold was given Hanover's written quote prior to coverage being bound. Finally, it is not clear what was provided to Estvold immediately after coverage was bound, if anything, other than confirmation that coverage had been secured and a bill. There is some evidence which suggests that the actual policy (which a carrier usually does not send out until sometime after coverage is bound) was not physically delivered to Estvold until months later when PayneWest had another in-person meeting with Estvold on September 30, 2015, to address topics of safety and during which PayneWest claimed it reviewed coverages with Estvold.
Prior to the September 30, 2015 meeting, Estvold decided it was going to expand the building that was under construction at the 39th St. location and, in April 2015, entered into a contract for the expansion or addition, depending upon how it is viewed. There appears to be little or nothing in the record addressing whether the expansion/addition was discussed with PayneWest during the September 2015 meeting.
In January 12, 2016, there was another in-person meeting in one of Estvold's shops at the 84th Ave. location to discuss the upcoming renewal of the Hanover policies for the 2016-17 policy year, beginning January 31, 2016. Present at the meeting were Borgschatz and Rush from Estvold and Brady and Devon Hoiness from PayneWest. During the meeting, a property schedule was reviewed but the claimed errors discussed above were not recognized or corrected by either Estvold or PayneWest.
More specifically, Devon Hoiness, who had attempted to correct the "wrong-city" error a year earlier in an email to PayneWest staff that was not acted on, did not recall or notice the error during the meeting. Further—and what a jury might find troublesome—after more than a year and PayneWest having billed $60,000 for its services and on the cusp of billing another like amount, is Brady and Devon Hoiness apparently not knowing enough about their customer's business (particularly given the scope of services PayneWest was providing) to be aware of: (1) the building that Estvold had under construction at the 39th St. location, which appears to be located just off the road that they undoubtedly had traveled several times to get to the 84th Ave. location; and (2) the fact that a substantial amount of the property listed in its proposal for renewal was not in Richardton but rather was in the immediate vicinity of where they were meeting.
Also, apart from this, Borgschatz claims he took Brady and Devon Hoiness to the 39th St. location when they met to discuss the renewal of the policy on January 12, 2016 to show them what the building was going to be used for. He testified that, although Estvold was in the process of putting equipment into the building, he was able to explain how it was going to operate and that Brady and Devon were impressed. Brady and Devon Hoiness both deny they ever were at the 39th St. location. Chander Rush testified that he recalled at least one instance when everyone went to the 39th St. location but could not recall which of the in-person meetings it was.
Equally troubling, on the other hand, is the explanation given by Borgschatz for why he did not catch the errors that Estvold now claims as the basis for its action. Borgschatz's explanation was that he simply looked to see whether all of the building that Estvold wanted coverage for were listed without focusing upon the particular addresses. A jury might find that explanation wanting after listening to that explanation and comparing it to the document he likely reviewed. Also, there is no evidence at this point that Borgschatz expressed any concern about the insured amount for the 39th St. location being sufficient going into the next policy year with the expansion or addition.
The Hanover policy was renewed at the end of January 2016 for the policy year extending from January 31, 2016 to January 31, 2017. There were no changes to the scheduled property from the previous policy.
On May 13, 2016, there was a fire at the 39th St. location. The original building for which construction began in late 2014 or early 2015 suffered damage primarily to one wall. There is some evidence that the estimate for the repair of the wall was approximately $190,000. The expansion or addition was a total loss, but the amount of the loss is not reflected in the current record.
While not entirely clear, there is evidence that, when the fire occurred, the building for which construction began in late 2014 or early 2015 had been substantially complete for some time, but, perhaps, not fully complete because of the expansion or addition. Also, there is evidence that, even with the expansion or addition, the construction was basically complete and the only thing that remained was any "punch list" work that may have been required.
There is some evidence, albeit circumstantial, which suggests that the original building as constructed was approximately 11,000 sq. ft. There is also some suggestion in the record that Estvold attempted to secure coverage for an 18,000 sq. ft. reconstructed building(s) at the 39th St. location, but that this square footage may not be an accurate reflection of what the combined square footage of the original building and the expansion or addition was prior to the fire because Estvold made some changes during the reconstruction.
Following the loss, PayneWest submitted a claim to Hanover on behalf of Estvold and urged it to cover the loss. In connection with that effort, Devon Hoiness submitted the following information to Sloan West:
Grant—
In addition, the North Dakota Insurance Commissioner's office also urged Hanover to cover the loss.
As noted earlier, Hanover refused to cover any portion of the loss. However, it did offer to return a portion of the premium if Estvold demonstrated there was not a building at the 4-1 location.
The law governing summary judgment is well known to the court and need not be repeated here.
In North Dakota, reformation of a contract is governed by N.D.C.C. § 32-04-17, which provides:
In addition, the North Dakota Supreme Court has stated the following with respect to a claim for reformation that is based upon mutual mistake:
Estvold argues that both it and PayneWest intended that the building described in the Hanover policy as Loc. No. 4-1 was the building at the 39th St. location and that the description of the building as being located at 4211 Hwy 8, Richardton, N.D. was a mutual mistake. For purposes of its claim against Hanover, Estvold argues that PayneWest's knowledge and intentions are imputable to Hanover, contending that PayneWest was acting as Hanover's agent.
The indisputable evidence, however, is that PayneWest was acting as Estvold's broker and agent—not Hanover's. In fact, Hanover employed its own broker. Under these circumstances, PayneWest's knowledge and intentions cannot be imputed to Hanover for purposes of Estvold's claim for reformation.
Estvold argues that Hanover made a mistake by insuring a building described in its policy as Loc. No. 4-1 because there was no building of that description at the address indicated. Hanover denies there was any mistake on its part and that it at all times intended to insure a building described in the policy as Loc. No. 4-1 and located at 4211 Hwy 8, Richardton, N.D. While it may simply be a matter of semantics, it appears there was a mistake on Hanover's side of the ledger, so to speak, unless one assumes it is a normal business practice for Hanover to collect premiums upon and insure non-existent buildings.
In the court's view, the real issue with respect to Estvold's claim for reformation is whether there was a mutual agreement to insure the building that suffered the loss, such that the policy should be reformed to conform to that agreement. And with respect to this point, Estvold has not come forward with sufficient evidence to demonstrate there is a triable issue in light of the evidence to the contrary.
More particularly, the evidence (including particularly Hanover's 2015 quote) is that Hanover agreed to insure a building identified in its policy as Loc. No. 4-1 at 4211 Hwy 8, Richardton, N.D. and not a building located some 75 miles away in a different county. Further, even if one was to overlook this geographic difference, the evidence before the court (again which has Estvold has failed to sufficiently dispute for purposes of summary judgment) indicates there were other differences in what the parties separately intended. Hanover's 2015 quote reflects with respect to the building scheduled as Loc. No. 4-1 an intent to insure an existing (2011) steel building approximately 11,000 sq. ft. in size—not a building that was under construction and substantially bigger if one includes the addition, which is what Estvold claims it intended that the policy cover.
Under North Dakota law, the court can only reform an agreement based upon mutual mistake when the parties intended to agree to the same thing but the mistake prevented that agreement from coming to fruition. In this case, Estvold has failed to come forward with sufficient evidence to create a triable issue over whether there was a mutual understanding between Hanover
Estvold has no claim for breach of contract unless the contract was to be reformed. This is because the unambiguous language of the policy covers only property at scheduled locations. As for Estvold's claim for declaratory relief, anything the court could declare is already addressed by its rulings on the claims for reformation and breach of contract.
PayneWest argues that Estvold cannot make out a prima facie case for negligence on PayneWest's part without expert testimony that would establish the standard of care for an insurance broker acting under the same circumstances and then whether that standard of care was breached. In support, PayneWest cites to North Dakota cases holding that expert testimony with respect to both matters was required to sustain a claim for professional negligence on the part of attorneys or doctors. PayneWest argues that the same proof is also required as a practical matter to demonstrate whether PayneWest breached its contract with Estvold. Finally, from these points, PayneWest argues that Estvold's claims for negligence, malpractice, and breach of contract must be dismissed because Estvold failed to disclose the requisite expert opinions within the time period allowed by the court's progression order.
The court rejects PayneWest's argument that it is entitled to summary judgment on these grounds. While it is true that North Dakota law requires expert testimony to establish both the standard of care and whether that standard was breached to make out a prima facie case of professional negligence in many cases, expert testimony is not required when the wrongfulness of the conduct involved is within the common knowledge of laypersons.
In this case, even if the court was to assume that all of the alleged wrongful acts or failures to act on the part of PayneWest involved professional as opposed to run-of-the-mill commercial services, the court concludes expert testimony is not required for at least some of what Estvold appears to be claiming that PayneWest did wrong. This includes any mistakes that PayneWest made in describing the property to be insured as well as the issue of whether PayneWest failed to secure coverage on a building at the 39th St. location that Estvold claims it specifically requested. These are matters that a jury can understand and fairly decide without the assistance of an expert.
PayneWest contends it was never put on notice that Estvold was making a claim for breach of the brokerage agreement that it had with PayneWest. After carefully reviewing the complaint, the court disagrees. Estvold pled sufficient facts in the complaint to make out a cognizable claim for breach of the brokerage agreement.
PayneWest also contends that Estvold has no claim for reformation of Hanover's policy as to it as well as for the companion request for declaratory judgment. The court agrees. The only viable claims that Estvold has at this point are claims for breach of contract, negligence, and malpractice, with the latter two being essentially the same thing. With respect to these claims, the court concludes there are material facts in dispute that require a trial.
The court denies Estvold's motions to enlarge the time periods set forth in the court's progression order for completion of fact discovery and for disclosure of expert testimony. The deadlines for completing this work passed and the court finds lacking Estvold's reasons for why the time periods should be enlarged, including why it did not request relief earlier than it did, to be insufficient. While the court makes its decision for this reason, it appears unlikely that the additional discovery with respect to Hanover's potential liability would have produced information on beyond what is already known that the court would consider material to the claim for reformation, particularly given the court's reasons for denial of the claim. Also, with respect to the motion to now add an expert, the court has concluded an expert is not necessary for at least a significant amount of what Estvold wants to present. In fact, expert testimony on matters that do not require an assistance of an expert may be of questionable admissibility.
Finally, with respect to the motion to disclose an expert, the court understands that PayneWest also did not disclose testimony from a retained expert—or at least did not do so within the time permitted by the court's scheduling order. What is sauce-for-the-goose is sauce-for-the-gander. However, if both parties come to an agreement and decide they want to proceed with retained experts, the parties are to contact the court within the next five days to further discuss this matter, including whether a continuance would then be required.
Based on the foregoing, the court: