STEPHAN, J.
L.G. Barcus & Sons, Inc. (Barcus), was held liable to the Village of Hallam under the One-Call Notification System Act (the Act)
Hallam is a village incorporated under Nebraska law. It operates a sanitary sewer system within its boundaries. On May 22, 2004, a tornado destroyed more than 150 homes and businesses in Hallam, including grain storage facilities owned by Farmers Cooperative, Inc. (Farmers).
After the tornado and before Farmers began rebuilding its facilities, Hallam hired a company to inspect its sanitary sewer system and determine whether it had been damaged by the tornado. The company lowered a video camera into manholes throughout the village and produced videotapes showing the interior of all sewer lines owned and operated by the village. The inspection was completed on June 26, 2004. Tyler L. Hevlin, a civil engineer, reviewed the inspection video and advised Hallam that the portion of its sewer which lay beneath the Farmers property was unobstructed and not in need of repair.
In June or July 2004, Farmers entered into separate contracts with McPherson Concrete Storage Systems, Inc. (McPherson), and Frisbie Construction Co., Inc. (Frisbie), to construct two cylindrical concrete grain storage bins and related structures. Under the contracts, McPherson was responsible for the concrete construction and Frisbie was responsible for the "millwright work," which included metal legs and other structures attached and adjacent to the concrete structures. Hallam issued a building permit for the construction of the bins.
In mid-June 2004, a firm identified in the record as "Terracon" conducted soil testing for the project through a series of soil "borings." The president and chief executive officer of Farmers testified that Terracon notified the one-call center before performing the borings, and Frisbie's operations manager believed that the people conducting the soil boring would have called the one-call center, but he had no personal knowledge on this point. The record provides no other information regarding communication between Terracon and the one-call center.
McPherson entered into a subcontract with Barcus to install an "AugerPile" foundation for the grain bins. The subcontract stated that Barcus' prices did not include the cost of
An AugerPile foundation is constructed using an auger to drill a hole in the ground, and then the hole is filled with grout as the auger is withdrawn. The grout used in this process is a substance similar to concrete but does not contain rock. The "augered cast pile[s]" (AugerPiles) were separately numbered so that Barcus could maintain a record of its work. On the Farmers project, Barcus was to install a total of 204 AugerPiles, each 16 inches in diameter. Two hundred of the AugerPiles were to serve as the foundation for the grain bins, and four were to be the foundation for a "bulkweigher," which is used to load grain into railcars. Frisbie was to construct the bulkweigher for Farmers at an unspecified future date. Barcus' role in the project was limited to installation of the AugerPile foundation.
Barcus arrived at the jobsite on July 20, 2004, and began installing AugerPiles on July 23. McPherson marked the locations for the 200 AugerPiles which would form the foundations of the bins, and a Frisbie employee marked the locations for the four AugerPiles which would form the foundation for the bulkweigher. Barcus employees did not notify the one-call center before commencing installation of the AugerPiles, because they did not consider such notification to be within the scope of their work. Rather, they considered such notification to be the responsibility of the general contractor, which in this case was McPherson. The Barcus foreman testified that he had "no idea" whether any other contractor notified the one-call center, but he observed no markings indicating the existence of underground facilities in the area where the AugerPiles were to be driven.
Barcus installed the four AugerPiles for the bulkweigher on July 30, 2004. Each of the four AugerPiles was 72 feet long and placed in a hole drilled to a depth of 73 feet, so that the top of each of the AugerPiles was beneath the surface of the ground. Barcus completed its work on the project and left the jobsite on August 10. Barcus' foreman recalled that one of the AugerPiles on the Farmers project required more grout than usual, but he testified that this was not uncommon and could have been caused by several factors.
On or about August 23, 2004, Hallam began receiving reports that sewage was backing up into homes and businesses located west of the Farmers site. An attempt to clear the sewer obstruction with water jet flushing was unsuccessful, so a camera inspection was undertaken. The inspection video revealed that the blockage was caused by concrete and broken sewer pipe.
Hallam then consulted Hevlin's firm, an engineering and architectural consulting group, to develop a plan for repairing or replacing the damaged portion of the sewer line. Hevlin determined and advised Hallam that because of the nature and extent of the blockage, the sewer line could not be repaired and would need to be rerouted. Hallam accepted Hevlin's advice and rerouted the sewer system based upon plans and specifications developed by Hevlin. Hallam incurred fair and reasonable costs in the amount of $96,007.74 as a consequence of the damage to its sanitary sewer.
Hallam filed suit to recover these costs against Farmers, McPherson, Barcus, and Frisbie in the district court for Lancaster County. It alleged that all four of the defendants were negligent and that Barcus and McPherson were strictly liable under the Act because they failed to notify the one-call center before installing the AugerPile foundation. In its answer, Barcus denied any liability on its part and affirmatively alleged that Hallam was contributorily negligent in several respects, including
Hallam retained Hevlin as an expert witness regarding the cause of the obstruction of its sanitary sewer in 2004. Based upon excavations undertaken in 2008, Hevlin determined the location of the four AugerPiles installed by Barcus as the foundation for the bulkweigher, the location of the pit constructed by Frisbie, and the location of the sewer line as it existed in 2004. Drawings prepared under Hevlin's supervision show two of the AugerPiles and one corner of the pit near the underlying sewer line. Based upon this information and his review of discovery documents from the litigation, Hevlin opined to "a reasonable degree of certainty as a professional engineer" that the auger used by Barcus during the installation of the AugerPiles damaged the sewer line and introduced grout which caused the obstruction. Hevlin further opined, to the same degree of certainty, that Frisbie's construction of the pit did not cause the damage, because the elevation of the bottom of the pit was higher than the sewer line.
Hallam moved for summary judgment on its strict liability claim against Barcus. The motion was supported by Hevlin's affidavit stating the opinions summarized above and other affidavits, depositions, and documents produced during discovery. The district court sustained the motion and entered judgment against Barcus in the amount of $96,007.74. The court determined that Barcus was an "excavator" as defined by the Act and that its installation of the AugerPiles constituted an "excavation" as defined by the Act.
The Nebraska Court of Appeals dismissed Barcus' appeal from the district court's order, and this court denied a petition for further review. Following remand, the action was dismissed as to Farmers, McPherson, and Frisbie pursuant to a stipulation. Subsequently, the district court determined that Hallam's damages were subject to pro tanto reduction in the amount of $30,000, and it entered final judgment against Barcus in the amount of $66,007.74. Barcus appealed, and we granted its petition to bypass.
Barcus assigns, summarized and restated, that the district court erred in (1) its construction and application of the Act, (2) not concluding that Hallam was barred as a matter of law from asserting a remedy through its own noncompliance with the Act, (3) receiving Hevlin's affidavit without sufficient foundation, and (4) concluding that there was no genuine issue of material fact regarding the proximate cause of Hallam's claimed damages.
Summary judgment is proper if the pleadings and admissible evidence offered at the hearing show that there is no genuine issue as to any material facts or as to the ultimate inferences that may be drawn from those facts and that the moving party is entitled to judgment as a matter of law.
Statutory interpretation presents a question of law. When reviewing questions of law, an appellate court resolves the questions independently of the conclusions reached by the trial court.
A trial court's ruling in receiving or excluding an expert's opinion which is otherwise relevant will be reversed only when there has been an abuse of discretion.
Barcus argues that Hallam had no remedy under the Act as a matter of law, because it had not complied with the provisions of the Act applicable to operators of underground facilities. Familiar general principles guide our analysis of this issue. Statutory language is to be given its plain and ordinary meaning, and our duty in discerning the meaning of a statute is to determine and give effect to the purpose and intent of the Legislature as ascertained from the entire language of the statute considered in its plain, ordinary, and popular sense.
The Act states that it was intended "to establish a means by which excavators may notify operators of underground facilities in an excavation area so that operators have the opportunity to identify and locate the underground facilities prior to excavation."
The Act defines "excavator" as "a person who engages in excavation in this
The Act defines "underground facility" as "any item of personal property buried or placed below ground for use in connection with the storage or conveyance of ... sewage, ... including ... sewers."
Persons are required by the Act to give notice to the one-call center at least 2 full business days but no more than 10 business days before commencing any excavation, and such notice "shall be deemed notice to all operators."
The liability provisions of the Act pertinent to this case are set forth in the first two sentences of § 76-2324:
Barcus argues that Hallam cannot be considered an "operator" within the meaning of these provisions, because it had not complied with the provisions of the Act requiring operators of underground facilities to "become members of and participate in the statewide one-call ... center."
The answer is apparent from the plain language of § 76-2324. The first sentence unambiguously states that an excavator who does not give notice of an excavation as required by § 76-2321 is strictly liable for damage to an underground facility caused by the excavation. The second sentence states that an excavator who gives the required notice of an excavation may be liable for damage to an underground facility, unless the damage was due to the operator's failure to identify and mark the underground facility. Thus, the statute provides a defense based upon the facility operator's failure to comply with § 76-2323. Reading these two sentences together, it is clear that an operator's noncompliance with § 76-2323 is a defense available to an excavator who gives the required notification, but not to the excavator who fails to give notice required by § 76-2321.
This construction is entirely consistent with the Legislature's intent "to establish a means by which excavators may notify operators of underground facilities in an excavation area so that operators have the opportunity to identify and locate the underground facilities prior to excavation."
Barcus also argues that in accordance with "the custom and practice of the construction industry," it complied with the Act by delegating its duty to notify the one-call center of its proposed excavation to others.
Barcus provides no authority for its premise that a party can avoid a statutory duty by delegating it to another in accordance with the custom and practice of an industry. But even if the premise is
The Act places the duty to notify the one-call center squarely on the "excavator" whose work could damage an underground facility. Frisbie was the excavator of the pit, and Barcus was the excavator with respect to the AugerPiles. Barcus cannot rely on Frisbie's compliance with the Act to excuse its own noncompliance.
At the summary judgment hearing, Hallam offered the affidavit of Hevlin, an engineer who had provided professional services to Hallam since 1998. Barcus objected to paragraph 21 of the affidavit as an opinion for which there was insufficient foundation. In that paragraph, Hevlin stated:
The district court took the objection under advisement. Although we find no subsequent ruling on the objection, the district court referred to the substance of the opinion in its order, noting that the affidavit included "detailed statements regarding the information which [Hevlin] relied on in forming his opinion, and the basis for his opinion." We therefore assume that the district court overruled the objection and received the opinion, and we turn to Barcus' argument that the court abused its discretion in doing so.
An expert's opinion is ordinarily admissible under Neb.Rev.Stat. § 27-702 (Reissue 2008) if the witness (1) qualifies as an expert, (2) has an opinion that will assist the trier of fact, (3) states his or her opinion, and (4) is prepared to disclose the basis of that opinion on cross-examination.
Hevlin is a professional civil engineer licensed in Nebraska and several other
Barcus did not assert a Daubert/Schafersman
Barcus contends that there was a genuine issue of material fact as to the cause of the obstruction. A prima facie case for summary judgment is shown by producing enough evidence to demonstrate that the movant is entitled to a judgment in its favor if the evidence were uncontroverted at trial.
The evidence reflects that the damage to the sanitary sewer occurred sometime between June 26, 2004, when the inspection revealed that the sewer in the
Barcus argues that an inference can be drawn that Frisbie was negligent in marking the location of the AugerPiles for the bulkweigher. Assuming that is so, it does not negate the evidence showing that Barcus' excavation damaged the sewer line, which is all that is necessary to establish liability under the Act where the excavator has not given the required notification prior to commencing excavation. Barcus also argues that it could not have caused the damage to the sewer, based upon the distance between the AugerPile excavations and the point at which the obstruction was eventually discovered. But even if we accept Barcus' calculations as to this distance, there is no evidence regarding its significance to the issue of causation. On this record, we agree with the district court that there is no genuine issue of material fact as to the cause of the damage to the sewer line.
For the reasons discussed, we find no merit in any of the assignments of error and therefore affirm the judgment of the district court.
AFFIRMED.
WRIGHT, J., not participating.