RICHARD G. KOPF, Senior District Judge.
This diversity case is before court on cross-motions for summary judgment. The plaintiff, Jackson Harmon Enterprises, LLC, doing business as Midwest Towing ("Midwest"), seeks to recover damages from the defendant, Insurance Auto Auctions, Inc. ("IAA"), for breach of contract or, in the alternative, unjust enrichment.
IAA is an Illinois corporation engaged in the business of storing automobiles in Douglas County, Nebraska. IAA provides a forum for insurance companies and other vehicle providers to dispose of total loss, theft-recovered, or dealer trade-in vehicles at auction. Upon assignment from a provider, IAA utilizes towers to pick up and deliver vehicles that are assigned to IAA by various vehicle providers. Midwest Towing is a Nebraska limited liability company engaged in the business of towing vehicles in Douglas County, Nebraska.
On March 8, 2010, Midwest and IAA entered into a "Towing Services Agreement," pursuant to which Midwest agreed "to tow vehicles for IAA . . . at the [mileage zone] rates set forth in the [attached] Towing Rate Sheet" (Complaint Ex. A (filing 1-1), ¶ 4.1). The Towing Services Agreement specified: "All additional charges such as two stops, waiting time, and dry runs not authorized by IAA will be absorbed by [Midwest] and not reimbursed by IAA" (id., ¶ 4.2). Regarding such additional charges, the Towing Rate Sheet provided:
(Id., p. 12; filing 89-1, p. 17).
Midwest alleges IAA breached the parties' agreement by not paying a "two stops" charge after Midwest either (a) delivered one or more vehicles from a single load to IAA's lot located on 52nd Street in Omaha, Nebraska, and the balance of the vehicles to a different IAA lot
The first time Midwest requested payment from IAA for deliveries to lots other than 52nd Street was in early 2011. Midwest's manager, Jeff Jackson, told IAA's branch manager, John Williams, that "the change of having to drop cars all over off the same load is starting to really cost me money," and he asked, "will IAA do anything about the fact that we're having do this?" Williams denied the request and responded that IAA's area manager, Dawn Kors, would not approve additional payments. Jackson again approached Williams in mid-2011, and Williams responded that he could not approve payment of additional compensation. Jackson also spoke directly with Kors in October 2011, and she told him the additional compensation Midwest was requesting was "not in the budget." She offered to put the Towing Services Agreement back up for a request for proposals (RFP), but Midwest did not make such a request. Midwest continued to provide towing services to IAA under the Towing Services Agreement through July 26, 2013.
IAA claims Kors told Jackson that dropping vehicles at different locations was not a "two stops" charge. Midwest denies Kors made this statement. Midwest claims Jackson spoke to IAA's transportation manager, Greg Santilli, in November 2011, and was told that dropping vehicles from a single load to different locations warranted a "two stops" charge, which was how Jackson realized for the first time that Midwest could demand additional compensation under the terms of the existing contract. IAA denies Santilli made such a statement.
A court interpreting a contract must first determine as a matter of law whether the contract is ambiguous.
Both parties contend the contract is unambiguous, but their interpretations are quite different. Basically, IAA says its branch manager was required to approve all charges for additional stops, while Midwest says IAA's branch manager only needed to authorize the additional stops, such as by requesting that vehicles be delivered to lots other than 52nd Street.
The court finds that paragraph 4.2 of the Towing Services Agreement and the "Added Stops" language in the "Additional Charges" section of the Towing Rate Sheet are ambiguous, and that there are genuine issues of material fact in the parol evidence which has been presented by the parties. These issues are identified in the parties' briefs and require no additional discussion by the court.
Because this matter will be tried to the court sitting without a jury, and because extensive evidence, including several depositions, has already been presented to and reviewed by the court in connection with the cross-motions for summary judgment, the parties are urged to cooperate in developing a "streamlined" trial plan which will allow each of them to make an adequate record without prolonged live testimony. Accordingly,
IT IS ORDERED:
1. Plaintiff's motion for partial summary judgment (filing
2. Defendant's motion for summary judgment (filing
3. This matter is referred to Magistrate Judge Zwart for progression.