MEMORANDUM OPINION
MARY L. COOPER, District Judge.
INTRODUCTION
Defendants, American Security Insurance Company ("ASIC") and Select Portfolio Servicing, Inc. ("SPS") (collectively, "Defendants") separately move for summary judgment in their favor. (Dkt. 52; dkt. 54.)1 Plaintiff, Marius J. Ged ("Ged") opposes those motions. (Dkt. 53; dkt. 56.) The Court, for the reasons that follow, will grant summary judgment in favor of ASIC and SPS.
DISCUSSION
I. FACTUAL HISTORY
A. The Parties
Ged "is a citizen of the State of Florida who . . . reside[s] . . . [in] Parkland, Florida. . . ." (Dkt. 1-1 at 4.) ASIC is "an insurance company or entity duly organized in the State of Delaware, selling and issuing policies of flood insurance within the State of New Jersey." (Id.) SPS "is . . . a corporation engaged in the mortgage servicing business within the State of New Jersey." (Id.)
B. The Property and Insurance Policy
Ged owns a house located at 6 Stoney Road, Point Pleasant Beach, New Jersey (hereinafter "the Property"). (Dkt. 1-1 at 3.) SPS was the designated servicer of the mortgage for the Property on or about December 1, 2011. (Id. at 5.) SPS managed the mortgage under the account number 0012883146. (Id.)2
ASIC issued a residential flood insurance policy ("the Policy"), bearing the number FLR0755826688, to SPS on February 29, 2012. (Dkt. 52-12 at 1.) The Policy covered the Property, and identified SPS as the "Named Insurance Mortgagee[.]" The Policy also listed Ged as "an additional insured[.]" (Id.) ASIC mailed a copy of the Policy to Ged at an address in Plantation, Florida. (Dkt. 52-11 at 9.)
SPS, as a Named Insured Mortgagee, paid the Policy's annual premium of $1,816.20 in monthly installments. (Dkt. 52-12 at 2.) The following terms governed cancellation of the Policy:
1. Cancellation
a. Coverage under this Policy shall automatically and without prior notice, cancel when the named insured no longer has an interest in the described location or when the named insured has been provided with another policy that meets the requirements of the named insured as set forth in the mortgage agreement applicable to the described location.
b. This Policy may also be cancelled by the named insured by returning it to us or notifying us in writing of the date cancellation is to take effect.
c. We may cancel this Policy by mailing notice of cancellation to the named insured at the address shown on the Additional Insured Endorsement or by delivering the notice not less than 30 days prior to the effective date of cancellation.
(Dkt. 52-10 at 17 (emphasis omitted).)
Pursuant to the terms of the Policy, SPS, as the Named Insured Mortgagee, was "authorized to act for . . . Additional Insured(s) in all matters pertaining to [the] insurance including receipt of Notice of Cancellation. . . ." (Dkt. 52-10 at 6.)
C. Short Payoff Settlement
Ged and SPS negotiated a short payoff settlement of the mortgage on the Property from January 2012 through July 2012. (Dkt. 54-4 at 4-5.) Ged offered SPS $375,000.00 to satisfy the mortgage via e-mail dated June 8, 2012. (Dkt. 54-3 at 81.) SPS, in response to Ged's offer, sent Ged a proposed Short Payoff Agreement ("SPA") via letter dated July 3, 2012. (Dkt. 54-2 at 27-29.) The SPA advised Ged that SPS "agree[d] to accept [his] proposed Short Payoff [of $375,000.00] and . . . release the lien on the [P]roperty. . . ." (Id. at 27.) The SPA required Ged to pay "an amount not less than $375,000.00 no later than July 23, 2012. . . ." (Id.)
The SPA, which was the only document that governed the short payoff settlement, stated that "[u]pon satisfaction of all terms of this approval, the mortgage [would] be discharged in its entirety with any deficiency rights waived, and a lien release document [would] be forwarded. . . ." (Id. at 28; see also dkt. 54-1 at 16.)
The terms of the SPA did not address the Policy. (Dkt. 54-2 at 27-29.) Ged accepted the terms of the SPA, and paid SPS $375,000.00 shortly thereafter. (Dkt. 54-1 at 17.)
D. Cancellation of the Policy
SPS, upon executing the SPA, informed ASIC that Ged paid his mortgage in full effective July 16, 2012. (Dkt. 52-12 at 2.) ASIC then proceeded to cancel "the Policy in accordance with instructions from SPS[.]" (Id.) ASIC refunded SPS $79.81, as a portion of the unearned premium for the month of July 2012. (Id. at 3.)3
ASIC forwarded a cancellation notice via letter dated July 26, 2012 ("7-26-12 Cancellation Notice"). (Dkt. 52-10 at 6, 29.)4 The 7-26-12 Cancellation Notice read, in relevant part, as follows:
The Named Insured Mortgagee/Lender has requested cancellation of the lender-placed insurance that was issued in compliance with your mortgage/lien agreement. This cancellation is effective at 12:01 a.m. on [07-16-2012]. The reason for this cancellation is:
Named Insured's Request. You have paid off your loan and the mortgagee/lender no longer has an insurable interest in the [P]roperty.
If you have any questions, please feel free to call your mortgage lender. . . . (Dkt. 52-10 at 29.)
E. Superstorm Sandy
The Property sustained flooding damage during Superstorm Sandy on October 29, 2012. (Dkt. 1-1 at 3.) Ged "filed an insurance claim [with ASIC] . . . seeking compensation for direct loss by flood" in February 2013. (Id.; see also dkt. 52-11 at 11.)5 Ged claimed he was "required to demolish the . . . Property and rebuild in order to return the home to pre-loss condition and comply with local zoning requirements." (Dkt. 1-1 at 5.)
ASIC informed Ged "that it was unable to confirm that there was any coverage in force for the Property on . . . October 29, 2012. . . ." (Dkt. 52-11 at 11.) ASIC, upon further reviewing the claim, issued a letter dated February 13, 2013 ("2-13-13 Letter") to Ged. (Id. at 12.) The 2-13-13 Letter informed Ged "that ASIC had been unable to locate any active policy for the reported date of loss of October 29, 2012, given that the Policy terminated before the date of loss upon the short payoff of . . . Ged's loan." (Id.) This action followed.
II. LEGAL STANDARD: MOTION FOR SUMMARY JUDGMENT
Federal Rule of Civil Procedure ("Rule") 56 governs motions for summary judgment. See Fed.R.Civ.P. 56(a). Pursuant to Rule 56(a), a federal district court "shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Id. The movant has the initial burden of proving the absence of a genuinely-disputed material fact regarding the claims at issue. Celotex Corp. v. Catrett, 477 U.S. 317, 322-23, 331 (1986). The nonmoving party, in response, must "go beyond the pleadings and by her own affidavits, or by the depositions, answers to interrogatories, and admissions on file, designate specific facts showing that there is a genuine issue for trial." Id. at 324 (internal citation and quotation omitted). Material facts are those "that could affect the outcome" of the proceeding, "and a dispute about a material fact is genuine if the evidence is sufficient to permit a reasonable jury to return a verdict for the non-moving party." Lamont v. New Jersey, 637 F.3d 177, 181 (3d Cir. 2011) (internal citation and quotation omitted). Summary judgment is "proper if, viewing the record in the light most favorable to the non-moving party and drawing all inferences in that party's favor, there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law." United States ex rel. Kosenske v. Carlisle HMA, Inc., 554 F.3d 88, 94 (3d Cir. 2009).
III. APPLICATION OF LEGAL STANDARD
Ged asserted the following claims against ASIC and SPS in the complaint: (1) "COUNT I — DECLARATORY JUDGMENT"; (2) "COUNT II — BREACH OF CONTRACT"; (3) "COUNT III — FAILURE TO PROVIDE NOTICE"; (4) "COUNT IV — NEGLIGENCE"; (5) "COUNT V — CONVERSION"; (6) "COUNT VI — FRAUD"; and (7) "COUNT VII — NEGLIGENT MISREPRESENTATION[.]" (Dkt. 1-1 at 8-17.) Ged now admits that "he has no evidence to support his claims for conversion, fraud, negligent misrepresentation, and negligence." (Dkt. 53 at 3.) Thus, according to Ged, Defendants are entitled to summary judgment on those claims. (Id. at 11; see also dkt. 56 at 16.)
Ged further concedes that "[t]he sole remaining issues for determination by this Court pertain to the breach of contract and [the] [P]olicy cancellation." (Dkt. 53 at 3; see also dkt. 56 at 3.) Accordingly, the Court will grant summary judgment in favor of ASIC and SPS on Count IV, Count V, Count VI, and Count VII of the complaint. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249 (1986) ("[T]here is no issue for trial unless there is sufficient evidence favoring the nonmoving party for a jury to return a verdict for that party."). The Court now considers the parties' arguments regarding the remaining claims, set forth in Count I, Count II, and Count III of the complaint, below.
A. Ged's Arguments
Ged alleges that Defendants failed to provide: (1) coverage warranted under the Policy; and (2) "proper notice of cancellation[.]" (Dkt. 53 at 3.) According to Ged, "there are genuine factual disputes regarding[:] (a) whether [Ged] is a third-party beneficiary under the Policy issued by ASIC to SPS and, if so, whether [Ged] was entitled to proper notice of cancellation; (b) whether the [P]olicy was properly cancelled; (c) whether [Ged] received proper notice of the cancellation, and if not[;] (d) whether Defendants are estopped from denying coverage." (Dkt. 56 at 5-6.) However, Ged concedes that the SPA "did not confer any rights to him with respect to the Policy." (Id. at 6.) Ged also admits that "there was no contract directly between [himself and] ASIC[.]" (Id.)
Ged contends that the Policy was effective on October 29, 2012 on the grounds that he was: (1) an additional insured under the Policy; and (2) a third-party beneficiary under the Policy. (Dkt. 56 at 6-11.)6 According to Ged, payments made "on the Policy as part of his monthly mortgage payment to SPS . . . . demonstrate that the Policy was intended to confer a direct benefit to him and as such he is entitled to third-party beneficiary status. . . ." (Dkt. 53 at 9.) Ged also argues that ASIC had an obligation to: (1) verify his address; and (2) forward the 7-26-12 Cancellation Notice to his verified address. (Id. at 10.)7 Thus, Ged argues, with respect to the 7-26-12 Cancellation Notice, that "there is a genuine dispute as to whether [Ged] was provided with effective notice" by the cancellation of the Policy. (Dkt. 56 at 11.)
B. ASIC's Arguments
ASIC argues that Ged "cannot maintain a claim for insurance coverage against ASIC . . . because the Policy terminated more than three months before the date of the loss[,]" thereby extinguishing SPS' interest in the Property. (Dkt. 52-11 at 6; dkt. 55 at 4.) With respect to the 7-26-12 Cancellation Notice, ASIC argues, inter alia, that it "fully complied with its notice obligations by sending Confirmation of Cancellation to the named insured, SPS, which had full authority under the Policy terms to receive notices of cancellation on behalf of [Ged], the additional insured." (Dkt. 52-11 at 7.) Thus, according to ASIC, it was relieved "of any obligation to send notice of termination because the named insured, SPS, requested termination of the Policy." (Dkt. 55 at 4.) See also supra Sec.I.B.8 ASIC also cites to the Policy term stating that "[c]overage under this Policy shall automatically and without prior notice, cancel when the named insured no longer has an interest in the described location" to support its argument that the 7-26-12 Cancellation Notice was valid under the terms of the Policy. (Dkt. 52-10 at 17; see also dkt. 55 at 4.) See also supra Sec.I.B. (describing the Policy terms governing cancellation).
C. SPS' Arguments
SPS argues, inter alia, that Ged was not a third-party beneficiary under the Policy because after SPS and Ged executed the SPA, "SPS no longer had an insurable interest in Ged's home. . . ." (Dkt. 57 at 14-15.) According to SPS, "New Jersey law would have prevented SPS (and therefore Ged) from pursuing a claim for the 2012 flood damage to Ged's property, regardless of whether SPS formally cancelled the [P]olicy in July 2012, because SPS ceased to have an insurable interest after the short payoff settlement in July 2012." (Id. at 15.) SPS also argues that "[e]ven if SPS's coverage under the . . . Policy had not terminated as a matter of common law as a result of the short payoff settlement . . . and even if SPS had not sent ASIC a request to cancel the . . . Policy in July 2012, SPS still would not have had coverage under the . . . Policy for a loss in October 2012 based on the unambiguous terms of the [P]olicy." (Id. at 15-16.) SPS, in support of that argument, cites to the Policy term governing cancellation, which states that "[c]overage under this Policy shall automatically and without prior notice, cancel when the named insured no longer has an interest in the described location. . . ." (Id. at 16.) See also supra Sec.I.B. (describing the Policy terms governing cancellation).
D. Analysis
The Court finds no dispute of material fact as to whether the Policy was effective on October 29, 2012, the date of Ged's claimed loss. The Court, upon reviewing the terms of the Policy and giving "the language a rational meaning in keeping with the expressed general purpose" of the Policy, finds that ASIC issued the 7-26-12 Cancellation Notice pursuant to the Policy terms. Conway v. 287 Corp. Ctr. Assocs., 187 N.J. 259, 269 (2006). Moreover, Ged provides no evidence to persuade the Court that: (1) ASIC was required to verify his address pursuant to the terms of the Policy; or (2) he was a third-party beneficiary under the Policy.9 Accordingly, the Court finds no genuine dispute of material fact regarding the claims at issue, and will therefore grant summary judgment in favor of ASIC and SPS on all remaining counts of the complaint. Celotex Corp., 477 U.S. at 322-23, 331.
CONCLUSION
The Court, for the above-stated reasons, will grant summary judgment in favor of ASIC and SPS. The Court will issue an appropriate order and judgment.