PER CURIAM.
These are back-to-back appeals, which we address in a single opinion. In A-4164-09, plaintiffs Larken Associates, L.L.C., JLB Associates, L.L.C. and Readington Commons II, L.L.C. (hereafter, plaintiffs or Larken) appeal from an order of summary judgment, dated April 28, 2010, dismissing plaintiffs' claims against defendants P&H Clinton Partnership, Pulte Homes of New Jersey, L.P. and Pulte Home Corporation of the Delaware Valley (hereafter, P&H) of malicious use of process, malicious abuse of process, tortious interference with economic advantage, and tortious interference with a contractual relationship. Plaintiffs also appeal orders denying their motions to disqualify P&H's counsel, Hill Wallack, L.L.P., and to pierce the attorney-client privilege between Hill Wallack and P&H in order to permit the depositions of certain Hill Wallack attorneys. In A-5344-09, plaintiffs Larken Associates, L.L.C., JLB Associates, L.L.C., Readington Commons II, L.L.C., and Lawrence Gardner, Larken's chief executive officer, (hereafter, Larken or plaintiffs) appeal a May 28, 2010 order of summary judgment dismissing their claims against defendants Hill Wallack, L.L.P. and attorneys Thomas Carroll, III, Stephen Eisdorfer, the Estate of Henry Hill, Esq., and Kenneth Meiser (hereafter, Hill Wallack) for abuse of process, malicious use of process, tortious interference with contractual relations and prospective economic advantage, and legal malpractice. We affirm.
The background to these cases is lengthy and complex. In 1999, Larken contracted to purchase approximately eleven acres of undeveloped land in Readington with the intention of building a multi-use commercial development, called "Readington Commons," and consisting of a child care center, medical and general office buildings, and associated parking. At the time, Readington's sewer capacity, which was managed by the Readington-Lebanon Sewerage Authority (hereinafter, RLSA) was fully allocated, leaving no capacity for Larken's proposed development.
However, in January 1999, the RLSA began construction of a Department of Environmental Protection (DEP)-approved expansion of its sewage treatment facility that would enable it to accommodate an additional 400,000 gallons of sewage per day. As a result, 320,000 gallons per day would be added to Readington's existing allocation, and 80,000 gallons would be added to Lebanon's allocation. In March 2000, Larken paid $143,635.24 to Readington for a specific allocation of Readington's increased municipal capacity, which was deemed ready for use in August 2000.
In early January 2001, Larken hired Hill Wallack attorney, Thomas Carroll, III, for the limited purpose of obtaining preliminary site plan approval for Readington Commons. In that connection, Carroll attended two hearings before Readington's Planning Board on February 13 and April 9, 2001. The Board granted the requested approval on April 9, 2001, and its action was memorialized in a resolution dated May 14, 2001. The attorney-client relationship between Carroll and Larken ended on June 4, 2001 when Larken directed Carroll not to perform any additional legal work for it.
By October 1, 2003, Larken had commenced and was "well into" the construction of site improvements for Readington Commons, having spent $2.94 million on the project. In January and March 2004, Readington issued Larken Uniform Construction Code (UCC) construction permits for some of the proposed buildings.
In the meantime, P&H was planning to build a mixed residential development, called "Windy Acres," in nearby Clinton. The site was listed by Clinton in its substantive certification to the Council on Affordable Housing (COAH) as fulfilling nearly fifty percent of its inclusionary zoning obligation in accordance with the Court's
Because Clinton's sewer capacity had been exhausted, in 1999, the municipality proposed building a new sewage treatment plant near Windy Acres that would discharge effluent into the South Branch, and in February 2000, Clinton and P&H entered into an allocation agreement granting P&H 300,000 gallons per day in sewerage capacity in return for payment, by P&H, of its pro rata share of construction costs. Thereafter, P&H applied to Clinton's Planning Board for preliminary site plan approval. However, following intense opposition to the development, the Board denied P&H's application. That denial was challenged by P&H in an action in lieu of prerogative writs and, accepting a special master's determination that the Board's action was arbitrary, unreasonable and indefensible, the court remanded P&H's application to the Board for further proceedings as to, among other things, potable water and sewerage issues.
In the meantime, opposition was mounted to the construction by Clinton of the sewage treatment plant. In apparent response to that opposition, effective May 2003, the DEP reclassified the South Branch from a Category Two to a Category One waterway, thereby providing heightened protection to the South Branch's water quality and effectively precluding the construction of the plant as the result of the degradation in the quality of the water in the South Branch that would be caused by effluent discharges from the treatment facility. The DEP suggested that connection to a regional sewerage system was one of the alternatives to disposal in the stream.
Although Windy Acres was not within the RLSA's established sewer service area, the trunk line from Lebanon to the RLSA's plant ran immediately adjacent to the Windy Acres site. Thus, P&H requested an allocation from the RLSA of a portion of its sewerage capacity. When the RLSA refused, stating that P&H was not within its service area and its capacity was fully allocated, on July 23, 2003, P&H filed an action in lieu of prerogative writs seeking declaratory and injunctive relief against Clinton, the DEP and the RLSA and its constituent members, Readington and Lebanon, to compel access to and allocation of the RLSA's sewer capacity for Windy Acres. P&H
In that action, P&H alleged that because the DEP had reclassified portions of the South Branch, the only feasible way to construct Windy Acres, which was an integral part of Clinton's plan to meet its
P&H thus requested a declaratory judgment and injunctive relief enforcing the rights that it articulated, regardless of the fact that the development was not within the RLSA's sewer service area. None of the developers or landowners that had purchased or contracted for capacity in the RLSA's expansion was named in the suit.
Following the filing of suit, P&H was granted an order, dated October 1, 2003, requiring that defendants show cause why temporary restraints should not be entered enjoining the RLSA, Readington and Lebanon from permitting new connections or allocations of treatment capacity to any end user without first obtaining court approval, with the exception of developers of affordable housing. The order also required Readington Township and the Lebanon Borough Sewerage Authority to provide notification of the action to individuals and entities that had received an allocation commitment in connection with the expansion of the RLSA treatment facility or had received site plan or subdivision approval or had such approvals pending for developments that would require sewer treatment at the RLSA's facility.
In response, in November 2003, numerous developers, including Larken, then intervened to protect their allocation claims. Thereafter, the RLSA, Readington, Lebanon, and many of the intervenors moved to dismiss P&H's complaint, claiming that the capacity at the RLSA's plant was fully used, allocated or reserved. Additionally Larken moved to disqualify Hill Wallack as counsel for P&H, alleging a conflict of interest and violations of
In an oral decision, placed on the record following argument on December 19, 2003, the court first addressed Larken's motion to disqualify Hill Wallack as P&H's counsel. It found that, although the two matters in which Hill Wallack provided representation were substantially related, Larken had not alleged that Carroll was privy to confidential information. Larken had conceded that it entered into its sewage capacity agreement in March 2000, nine months before Carroll's representation commenced. And "Mr. Carroll certifie[d] that his involvement was strictly limited to the environmental and traffic concerns and had nothing to do with the sewage capacity." Further, the court found that the interests of P&H and Larken were not materially adverse because the second form of order submitted by P&H in its action created an exemption from its effect for property owners that had previously received an allocation of sewer capacity in the RLSA plant and had received final site plan approval and/or subdivision approval and had building permits that allowed commencement of construction — conditions that Larken had met.
Addressing the motion to dismiss P&H's complaint, the court noted that the RLSA plant had a 1.6 million gallon per day capacity, and that the DEP presently authorized discharge flows of up to 1.45 million gallons per day on a staggered basis. Although the current average daily flow ranged from 580,000 to 730,000 gallons per day, usage was trending upward. Further, one report provided that 883,409 gallons per day of unused capacity had been allocated to end users. Thus, very little, if any, unused sewage capacity remained that could be redirected to Windy Acres. In these circumstances, the court maintained, plaintiff could not make the required showing, pursuant to
In reaching that conclusion, the court acknowledged the scarce resources doctrine, recognized in a
In contrast, the
Applying the cited precedent to the present circumstances, the
The
Upon appeal, we affirmed the order of the trial court dismissing the complaint against the intervenors and the DEP with prejudice. We affirmed the dismissal of the complaint against the remaining defendants, but modified the order to render the dismissal "without prejudice to allow [P&H] to reinstate its complaint in the event that COAH determines that Windy Acres is necessary for Clinton's certified affordable housing plan and [P&H] is unable to negotiate a resolution with Clinton and/or RLSA to provide sewer capacity for Windy Acres."
During the period prior to the conclusion of appeals from the trial court's ruling in
Consequently, in mid-2005, Larken filed a complaint and first-amended complaint against P&H Clinton Partnership and associated entities, Pulte Homes of New Jersey, L.P., and Pulte Home Corporation of the Delaware Valley (the underlying action), the dismissal of which forms the basis for one of the present appeals. In it, Larken contended that P&H's prior suit against the RLSA and other entities constituted malicious use of process, malice, tortious interference with economic advantage and tortious interference with contract. A lengthy period of discovery and motion practice followed.
In November 2007, more than two years after Larken filed its first-amended complaint, it moved to disqualify Hill Wallack from its representation of P&H. The motion was heard by Judge Accurso and denied, as was a subsequent motion for reconsideration
Thereafter, Larken filed a second-amended complaint alleging in four counts tortious interference with contractual relations, tortious interference with prospective economic advantage, abuse of process, and malicious use of process. In January 2009, Larken again moved to disqualify Hill Wallack, and in September 2009, it moved to pierce the attorney-client privilege in order to take the depositions of Hill Wallack attorneys. In support of the disqualification motion, Larken submitted as proof of Carroll's knowledge of its sewer capacity allocation the transcript of the February 13, 2001 hearing before Readington's Planning Board. That transcript disclosed that, after the Board determined to carry the Larken matter to April 9, Gardner introduced himself, stated that he had paid approximately $150 thousand for sewer rights,
Judge D'Annunzio determined to defer the disqualification and discovery issues until the parties filed summary judgment motions on the "core issue" of "whether [P&H's] attempt to get relief from the sewer problem was a legitimate reaction [to] the DEP[`s] reclassifying the stream as a Category One stream."
P&H then moved for summary judgment, and Larken filed a cross-motion for "summary judgment on the element of lack of probable cause" in connection with counts three and four of the complaint alleging abuse of process and malicious use of process. In a letter opinion dated March 11, 2010, the court granted summary judgment to P&H on counts three and four, finding that P&H had probable cause to file its underlying lawsuit seeking a sewerage allocation from the RLSA and its participating municipalities.
In doing so, the court discussed
The court then noted that it was unlikely that Windy Acres could be built if it could not obtain capacity from the RLSA. It found that, although a factual issue existed as to whether P&H could have built a DEP-compliant sewage treatment plant, in bringing suit, P&H was nonetheless entitled to rely upon the fact that it reasonably believed it was unable to do so.
An issue in the underlying litigation, the court held, "would have been whether the RLSA had the capacity to serve Windy Acres and, if not, whether a
The court rejected Larken's claim that the trial court's decision dismissing P&H's suit established a lack of probable cause as a matter of law. The court noted that on P&H's appeal of the dismissal of its underlying action, we set aside the trial court's with-prejudice dismissal of the complaint as to the RLSA and its participating municipalities, holding that it should have been without prejudice pending further action by COAH. The court reasoned that, by modifying the trial court's judgment, we "recognized a potential legal and factual basis for the underlying action, contrary to the trial court's statement that it was solely without foundation."
The court also found erroneous the view that the underlying suit was an attempt to permanently seize capacity previously allocated to Larken and others. The court held, "P&H requested no such relief in the complaint, and the injunctive relief sought on the return date of the order to show cause was interim relief to maintain the status quo, but subject to a specifically defined safety valve and the general safety valve of `good cause.'" As a final matter, the court held that we had effectively narrowed
The court ended its opinion by stating:
The court did not address the tortious interference claims directly because of the absence of briefing, but observed that its determination regarding probable cause "would appear to preclude" the remaining claims.
In a supplemental written opinion, dated April 28, 2010, the court granted summary judgment on Larken's remaining claims of tortious interference with business advantage and contract arising out of the underlying action. The court concluded that "1) defendants were privileged to file the litigation; and 2) the court's determination in the malicious process case that defendants were justified in filing the underlying action eliminates the `malice' element of tortious interference." The court thus entered an order of summary judgment in P&H's favor on all four counts. An appeal followed.
While motions for summary judgment in Larken's action against P&H were pending, on December 17, 2009, Larken filed its action against Hill Wallack, alleging abuse of process, malicious prosecution/malicious misuse of process, tortious interference with contractual relations, tortious interference with prospective economic advantage, and legal malpractice.
In lieu of filing an answer, on or about February 18, 2010, Hill Wallack moved to dismiss the complaint. In response, Larken's counsel filed a certification, to which he attached a transcript of the February 13, 2001 public hearing before Readington's Planning Board. That transcript disclosed that, when the Board indicated that it was carrying Larken's application for preliminary site plan approval to April 9, Lawrence Gardner, the chief executive officer of Larken, requested that the Board make a final decision at the April meeting. He disclosed that he had paid "150 some odd thousand dollars to the sewer authority to acquire the sewer for this property" and that he was under a contract to purchase the property that would expire in May. Therefore, timing was of concern to him. According to counsel, this transcript confirmed that Carroll knew Larken was relying heavily on its sewer capacity reservation in seeking site plan approval and purchasing the property for its project.
Although issue was joined, the parties in Larken's action against Hill Wallack agreed to defer Hill Wallack's motion to dismiss until Judge D'Annunzio had issued a final decision in Larken's action against P&H, which occurred on April 28, 2010. Following oral argument before Judge Goodzeit on Hill Wallack's motion against Larken, she granted summary judgment, finding in a written decision dated May 28, 2010, Larken's action for legal malpractice to be barred by the statute of limitations and its remaining causes of action barred by application of collateral estoppel as the result of Judge D'Annunzio's decision. An order dismissing Larken's complaint against Hill Wallack with prejudice was entered on June 21, 2010.
On appeal from the orders for summary judgment, we adopt the same legal standard employed by the trial court.
We first address issues raised in A-4164-09, Larken's appeal from the order of summary judgment in favor of P&H. We commence with the appeal from the dismissal of Larken's claim of malicious use of process, a claim that is disfavored because of its potential to chill free access to the courts.
Determining whether probable cause has been demonstrated is generally an issue for the court, unless the facts giving rise to probable cause are themselves in dispute.
"Malice... is defined as the `intentional doing of a wrongful act without just cause or excuse.'"
Our review of the record in this matter satisfies us that Larken failed to offer evidence that P&H lacked probable cause to bring its action against the parties to that suit. We therefore affirm substantially on the basis of the sound and well-articulated opinion of Judge D'Annunzio. We add only the following to address the particular arguments raised by Larken on appeal.
Larken raises the broad argument that no legal authority supports the trial court's finding that P&H had probable cause to file the underlying action. It supports that position first by reviewing nine COAH rulings reached between 1977 and 1995 and arguing that they demonstrate that not even the agency would order a municipality to give its own developers access to already allocated resources. It also relies on
However, when the
As a consequence, we find the administrative evidence upon which Larken relies to have no relevance in determining the legal issue of whether P&H had probable cause to file the underlying action, which challenged whether a developer of an inclusionary development could demand access to a neighboring community's sewer system. Indeed, as P&H notes in its brief, COAH announced in one of its agency decisions,
Larken argues additionally that no published case supports the premise that a developer, promising to construct affordable housing, can demand sewage capacity in a neighboring municipality that has contractually allocated all or most of its own capacity to local developers, and for that reason, P&H could not have had a reasonable expectation or honest belief that it could obtain that capacity. However, even if we accept the proposition that P&H knew all capacity had been allocated,
We disagree with Larken's position that the remedies available to P&H were limited by the Court's decision in
Additionally, we reject Larken's argument, based on the operation of the doctrines of
We do not regard either doctrine as barring Judge D'Annunzio from opining as he did. P&H's underlying action for non-resident sewer access and Larken's action for malicious use of process cannot be considered the same controversy, or as having the same issues. In P&H's underlying action, which was not filed against Larken, the issue was whether P&H presented sufficient compelling circumstances for a non-resident allocation of the RLSA's sewer capacity and for an order imposing restraints on the RLSA's disposition of scarce sewer resources. Here, the issue is whether P&H had probable cause to commence the action in the first place. Moreover, the fact that P&H lost in the underlying action is not evidence that it brought those proceedings without probable cause to do so.
The court's decision in
In summary, the undisputed evidence demonstrates that, in July 2003 when the underlying action was filed by P&H, its Windy Acres development constituted a major component of Clinton's substantive certification in support of its affordable housing obligation. At that time, no other developer had come forward to propose an alternative to the Windy Acres site that would offer as many affordable housing units. However, because the DEP, seemingly bowing to pressure, determined to raise the water purity classification for the South Branch, it became all but impossible for Clinton to build the sewage treatment plant that was envisioned as the facility that would handle Windy Acres' waste. Acting in accordance with the DEP's recommendation that it connect to a regional wastewater treatment facility as an alternative to disposal utilizing the South Branch, P&H filed suit against the RLSA and its participating municipalities. At that time, although the RLSA's treatment capacity had been expanded, and allocations of that capacity had been made, the plant was not operating at full capacity and, although usage was incrementally increasing, it was not known when or if capacity would be reached.
In these circumstances, we are satisfied, as was Judge D'Annunzio, that, utilizing a reasonably prudent person standard, P&H had a "reasonable belief that there was a good or sound chance of establishing [its] claim to the satisfaction of the court."
We are similarly satisfied that, in seeking a temporary injunction, P&H did not engage in an abuse of process — a claim that, to succeed, requires proof that P&H performed an additional act during the underlying action that represented an illegal, improper or perverted use of legal process, or a use neither warranted nor authorized by that process, and that P&H had an ulterior motive and used its action as a means to coerce or oppress Larken.
Further, because of the uncertain parameters of the law after the Court rendered its decision in
Similarly, we affirm the dismissal of Larken's claims of tortious interference with contract and business relationships, determining that it failed to demonstrate, as it must have shown,
As a final matter in connection with the appeal in A-4164-09, we address Larken's argument that Judge Accurso and Judge D'Annunzio erred in failing to disqualify Hill Wallack from representing P&H in the underlying litigation and that Judge D'Annunzio erred by refusing to grant Larken's motion to pierce the attorney-client privilege between Hill Wallack and P&H before ruling on the parties' cross-motions for summary judgment. Larken alleges that, as the result of Hill Wallack's prior representation of the company, Hill Wallack knew of Larken's sewer capacity reservation and used that "confidential" information against Larken when it represented P&H in the underlying and current actions, creating a conflict of interest in violation of
The issue of Hill Wallack's disqualification was raised by Larken in the underlying action instituted by P&H against the RLSA and others, and the order denying Larken's disqualification motion was the subject of a cross-appeal by Larken in that matter. Larken argued in that connection that Hill Wallack's representation of P&H had violated
In that regard, our review of the record in this matter satisfies us that Judge Accurso did not abuse her discretion in determining, among other bases for denying Larken's motion, that Larken's motion to disqualify Hill Wallack, filed in November 2007, more than two years after it had commenced its suit against P&H and issue had been joined, was not timely filed, and as a result Larken's objections to the representation had been waived. As a consequence of the judge's initial order and subsequent order upon reconsideration after examination of additional evidence, the issue became settled, and there was no reason for its further reconsideration by Judge D'Annunzio in January and September 2009.
As Judge Accurso recognized, Larken had raised the alleged conflict of interest in 2003, and again in its cross-appeal after dismissal of P&H's action. In 2005, Larken instituted its own action, and despite its evident knowledge of conduct that it claimed constituted a conflict of interest, it sat back without objection while Hill Wallack appeared for and actively represented P&H for a period of two years before filing its disqualification motion.
To disqualify Hill Wallack, Larken was required to prove that "the matters between the present and former clients [were] `the same or... substantially related,' and the interests of the present and former clients [were] `materially adverse.'" City of Atl.
Given the nature of the allegations in Larken's suit against P&H, we have difficulty perceiving a basis for Hill Wallack's disqualification. Nonetheless, even assuming a disqualifying conflict existed as the result of Hill Wallack's representation of P&H in this case, we agree that the conflict was waived.
In
Likewise, in
In
Application of the test articulated by the court in
Turning to Larken's final attempts to disqualify Hill Wallack and to pierce the attorney-client privilege, we find Judge D'Annunzio's decision to defer Larken's motions pending a determination of the substantive issues raised by the litigation to have been proper, given Hill Wallack's continuous representation of P&H since 2003 and the imminent filing of dispositive motions. In particular, we note that, pursuant to our prior analysis of the probable cause issue in light of the decisions in
We next address the issues raised in A-5344-09 by Larken in its appeal from the order of summary judgment entered by Judge Goodzeit in favor of the Hill Wallack defendants. In that regard, we agree with Judge Goodzeit that Larken's claims against the Hill Wallack defendants for malicious prosecution/malicious misuse of process, tortious interference with economic advantage and tortious interference with contract were barred by collateral estoppel. The identical issues were decided in Larken's action against P&H; the issues were clearly litigated in that proceeding, resulting in an order of summary judgment in P&H's favor; and the issues were central to the court's determination.
We recognize, as did Judge Goodzeit, that even when, as here, all the essential elements required for the application of collateral estoppel are found to exist, the doctrine should not be applied when it is unfair to do so.
Further, the judge observed, given the length of the previous litigation, it was likely that protracted litigation would ensue here, as well. And given the existence of an attorney-client relationship between P&H and Hill Wallack, the judge would anticipate many assertions of the attorney-client privilege, followed by multiple motions seeking to defeat that privilege. Thus, the invocation of collateral estoppel would not only avoid repetitious litigation, it would conserve judicial resources. Additionally, the judge found that any substantive review of the merits of Larken's non-malpractice claims would require inquiries identical to those already conducted by Judge D'Annunzio.
We concur with Judge Goodzeit's reasoning. We reject Larken's argument that, because summary judgment was entered in its action against P&H before discovery was complete, it was deprived of a full and fair opportunity to litigate its claims against that entity. The issue before Judge D'Annunzio was a purely legal one — whether, judged objectively, P&H had probable cause to commence the underlying action to test the boundaries of the "compelling circumstances" required by
As a final matter, we address the dismissal, by order of summary judgment, of Larken's claim against Hill Wallack of legal malpractice on statute of limitations grounds.
In finding the cause of action to be barred, Judge Goodzeit appropriately applied the six-year statute set forth in
In this matter, Judge Goodzeit properly found that Larken knew or should have known of Hill Wallack's alleged fault at the time that it moved to intervene in the action filed by the firm on behalf of P&H against the RLSA seeking a sewer allocation and potentially threatening the allocation previously given to Larken. At that time, Larken retained counsel, and thus commenced to incur attorney's fees to protect its right to the allocation that it had purchased. Precedent holds that the incurring of attorney's fees, prior to any decision in a matter, constitutes damages sufficient to commence the running of the statute of limitations.
Larken filed its action against Hill Wallack on December 17, 2009. Larken moved to intervene in the P&H matter on December 10, 2003 — a date more than six years prior to Larken's commencement of its action against the firm and its lawyers. As a consequence, we find that Judge Goodzeit properly dismissed Larken's malpractice claim, correctly recognizing that a legal malpractice claim may accrue while the underlying claim is being litigated.
We reject Larken's argument that its cause of action against Hill Wallack did not accrue until P&H's suit was dismissed on January 20, 2004, until we rendered our decision on May 5, 2005, until the Supreme Court denied certification on December 8, 2006, at a later date when Larken received its first building permits, or thereafter when depositions commenced. As we have illustrated, precedent does not support Larken's position.
Moreover, we note that Larken's own allegations in its complaint against Hill Wallack and its admissions in oral argument before the trial court reveal its knowledge of alleged malpractice at the time it intervened in P&H's action against the RLSA. In paragraphs 92 through 94 of its complaint, Larken alleged that as the result of Hill Wallack's representation of it for purposes of preliminary site plan approval, the firm and, particularly, Carroll, were aware that Larken heavily relied upon the 7,628 gallons per day of sewer capacity that it had purchased from the RLSA in obtaining preliminary site plan approval, in determining to purchase the property for $1 million for purposes of development, and in obtaining the governmental approvals necessary to develop Readington Commons. Larken continued:
Later, during oral argument, Larken's counsel declared that "it is very clear... legal malpractice" occurred because Carroll knew that Larken had paid to secure sewer capacity and then "[a]ll of a sudden we have Hill Wallack representing [P&H] to try and take away the very foundation of all the work that they performed for [Larken.]" Thus, it is clear that Larken had knowledge of its alleged injury at the time that it retained counsel for the purpose of intervening in the RLSA matter more than six years before Larken instituted suit against Hill Wallack.
We are therefore satisfied that summary judgment was properly granted dismissing each of Larken's claims in its suits against P&H and Hill Wallack.
Affirmed.