The opinion of the court was delivered by
LIHOTZ, J.A.D.
In these appeals, calendared back-to-back and consolidated for purposes of our opinion, we examine several orders, which fix the rights of the parties. Plaintiff EnviroFinance Group, LLC (EFG) provided construction financing to plaintiff Earthmark NJ Kane Mitigation, LLC (Earthmark), the developer of an environmental mitigation project to be built on Bergen County wetlands owned by the Meadowlands Conservation Trust (MCT). The primary contractor of the project was defendant Environmental Barrier Company, LLC, d/b/a Geo-Con (Geo-Con).
When Geo-Con was not paid for its work, it filed two construction liens against Earthmark's leasehold interest in the project. Earthmark and EFG filed this action against Geo-Con, primarily to discharge the construction liens. The motion judge concluded Geo-Con's liens were properly asserted against the private leasehold interest and assets of Earthmark, not against the public realty. Geo-Con requested default and later moved for entry of final default judgment and to fix damages against Earthmark. EFG opposed the motion, asserting a final judgment against Earthmark would impair its collateral interest. Following a hearing, the judge disagreed and found EFG lacked standing to oppose determination of claims between Geo-Con and Earthmark. A final judgment in favor of Geo-Con and against Earthmark was entered. A second order, filed over EFG's objection and without benefit of a testimonial hearing, required Earthmark's payment to Geo-Con of an award of counsel fees, costs and pre-judgment interest. The first appeal, filed by EFG, challenges these two orders (A-2475-12). This court declined to consider, but did not dismiss this appeal, pending the outcome of cross-motions for summary judgment.
Reviewing the summary judgment record, the judge upheld Geo-Con's construction liens. He also determined EFG was liable for cure payments under the terms of its agreement with Geo-Con and assertions made in a February 2011 correspondence, but was not liable for additional
Following our review, of the arguments presented, the record on appeal and the applicable law, we affirm.
MCT owns 587 acres of environmentally sensitive wetlands in the Richard P. Kane Natural Area located in Bergen County. Earthmark was chosen as the successful bidder following the request for proposals to construct an environmental mitigation bank on MCT's land. A mitigation bank is "a wetland, stream, or other aquatic resource area that has been restored, established, enhanced, or (in certain circumstances) preserved for the purpose of providing compensation for unavoidable impacts to aquatic resources permitted under . . . state or local wetland regulation."
Effective January 22, 2009, MCT's Board of Directors entered into a ground lease with Earthmark to construct the project, at Earthmark's sole cost and expense, on a portion of MCT's land. As required by the ground lease and request for proposal, Earthmark, MCT, and the various federal and state agencies comprising the Meadowlands Interagency Mitigation Council, entered into the Richard P. Kane Natural Area Mitigation Bank—Mitigation Bank Instrument (the project). Earthmark contracted with Geo-Con to be the project's primary contractor (construction contract).
The project was financed through a loan from EFG. Earthmark executed a $12 million "Secured Revolving Loan and Security Agreement" (the pledge agreement) on July 13, 2010. To secure repayment of the construction financing, Earthmark executed a "Pledge and Security Agreement" (the loan documents), granting EFG collateral security, which included 100% ownership and membership interests in Earthmark, including its leasehold and proceeds from the sale of mitigation credits generated by the project.
Geo-Con and EFG also entered into a Contractor Consent Agreement (CCA), which collaterally assigned the construction contract between Geo-Con and Earthmark to EFG. The agreement required Geo-Con to provide notice and a cure period to EFG, in the event Earthmark defaulted under the construction contract. Additionally, the CCA precluded amendment or modification of the initial Earthmark-Geo-Con construction contract, without EFG's prior written consent.
Further, EFG alleged Geo-Con and Earthmark designed a separate payment schedule for this additional work, which was sought by, and disguised in, Geo-Con's draw requests to EFG. When EFG learned of the separate agreement to address cost overruns, it declared Earthmark in default in a December 8, 2010 letter.
By January 2011, Geo-Con ceased work on the project because it was not being paid. Geo-Con notified EFG of Earthmark's failure to remit payment of its October and November invoices, and separately sent notice of its intent to stop work, unless EFG cured the default. EFG challenged the work stoppage, advising Geo-Con it was willing to remit cure payments upon receipt of certain documents required under the CCA. Specifically, EFG identified Geo-Con's need to submit engineering approval, and offered to meet to discuss the matter. Geo-Con provided the engineer's certification approving the October and November invoices. Also, Geo-Con rejected EFG's position regarding the work stoppage, as well as its refusal to pay for the additional work, and accused EFG of bad faith. When EFG did not remit cure payments, Geo-Con recorded two construction liens in the Bergen County Clerk's Office against Earthmark's leasehold interest in the project, on March 28, 2011.
EFG and Earthmark initiated this action by filing a verified complaint and an order to show cause, principally seeking to discharge Geo-Con's construction liens. Further, EFG sought damages for Geo-Con's wrongful filing of the construction liens, which it argued violated the Construction Lien Law (CLL), N.J.S.A. 2A:44A-1 to -38, because the liens attempted to attach a public works project in violation of N.J.S.A. 2A:44A-15(a). The complaint also alleged breach of contract, asserting Geo-Con included sums in its liens pursuant to the concealed overrun modification agreement, which were neither approved nor due.
Geo-Con counterclaimed, alleging Earthmark and EFG breached their respective contractual obligations. Geo-Con sought quantum meruit payment from EFG, payment on an open book account against Earthmark, an equitable lien against the assets of Earthmark and EFG, and permission to foreclose the construction liens.
On September 20, 2011, Judge Robert P. Contillo denied EFG and Earthmark's request to discharge the construction liens, finding the cited exception to the CLL inapplicable. Although the project was in the nature of a public works project as it would improve public property, the judge concluded the improvements were not "contracted for and awarded by a public entity," necessary elements for application of the exception. N.J.S.A. 2A:44A-5(b) (emphasis added). The judge determined the relationship from which the proposed liens arose between Geo-Con and Earthmark
Partial summary judgment was later granted dismissing Geo-Con's claim for an equitable lien on mitigation credits generated from the project that were pledged by Earthmark to EFG. Subsequently, counsel for Earthmark requested to be relieved, which was granted. Earthmark did not secure substituted counsel and ceased participation in the litigation. Thereafter, Earthmark entered into a Transition Agreement giving EFG control of the project.
In June 2011, EFG assigned all its interest, including the loan and its security interest in Earthmark and the project, to Kane Mitigation, LLC (Kane). Kane was owned entirely by EFG. In February 2012, Kane became the successor bank sponsor of the project under the authorizing documents with MCT.
Without opposition, Geo-Con moved to dismiss Earthmark's complaint and requested default on its counterclaims against Earthmark. Geo-Con later moved for entry of final default judgment against Earthmark, seeking damages of $5,505,328. EFG opposed that motion and requested "a proof hearing on the validity and amount of Geo-Con's claims against Earthmark." Geo-Con challenged EFG's standing to oppose its motion, to which EFG advanced it held a financial stake in the outcome and judgment would "impair EFG's collateral" and security interest under the pledge agreement.
Following oral argument, Judge Contillo concluded EFG lacked standing to oppose Geo-Con's motion for entry of default judgment against Earthmark, finding EFG had almost two years to exercise its rights under the pledge agreement and failed to do so. Further, the judge determined Geo-Con's claims were advanced solely against Earthmark and did not alter EFG's security interests under the loan and pledge agreements. Earthmark's complaint against Geo-Con was ordered dismissed with prejudice and final judgment was entered on behalf of Geo-Con against Earthmark for $3,811,651, the sums approved for payment by the project engineer for work performed. The order was certified for execution purposes. See R. 4:42-1.
Geo-Con moved for additional compensation in the form of attorney's fees, costs, and pre-judgment interest, pursuant to the Prompt Payment Act (PPA), N.J.S.A. 2A:30A-1 to 2. On March 15, 2013, following oral argument, the judge granted Geo-Con an additional judgment of $1,715,139, which he certified as final.
EFG appealed (A-2475-12). In our October 2, 2013 order, we noted the matter was interlocutory and removed it from our plenary calendar. However, we did not dismiss the appeal pending the outcome of cross-motions for summary judgment, which had been filed.
Following oral argument on the summary judgment motions, Judge Contillo issued a written opinion on July 8, 2013. The judge denied EFG's and granted Geo-Con's motion for breach of contract, awarding Geo-Con, its successors and assigns, $1,354,386.31, which represented agreed cure payments due from EFG under the CCA, following Earthmark's default. Although the judge found Geo-Con breached the CCA by entering into the September 7, 2010 modification agreement with Earthmark without notice to or consent from EFG, he found EFG's claim failed because it did not prove resultant damages, "a[n] essential component of a breach of contract claim."
A final judgment memorializing these decisions was entered on July 12, 2013. The sheriff's sale of the leasehold interest was held on January 17, 2014.
Cross-appeals were filed by EFG and Geo-Con from the summary judgment orders (A-6202-12). We calendared the two appeals back-to-back and now address all issues in one opinion.
In its initial appeal (A-2475-12), EFG argues the judge erroneously denied it standing to challenge Geo-Con's default judgment against Earthmark, emphasizing EFG held a priority security interest in 100% of Earthmark's membership
In our review, we are obligated to defer to a judge's factual determinations when supported by the evidential record. Brunson v. Affinity Fed. Credit Union, 199 N.J. 381, 397, 972 A.2d 1112 (2009). However, we accord no special deference to a trial judge's "interpretation of the law and legal consequences that flow from established facts," Manalapan Realty, L.P. v. Twp. Comm. of Manalapan, 140 N.J. 366, 378, 658 A.2d 1230 (1995), which we review de novo. Dep't of Envtl. Prot. v. Kafil, 395 N.J.Super. 597, 601, 930 A.2d 457 (App.Div.2007).
"[S]tanding is an element of justiciability that cannot be waived or conferred by consent." In re Adoption of Baby T., 160 N.J. 332, 341, 734 A.2d 304 (1999). Rather, it is a threshold inquiry because "[a] lack of standing by a plaintiff precludes a court from entertaining any of the substantive issues for determination." Id. at 340, 734 A.2d 304. In short, the doctrine focuses on whether a party has a legal entitlement to seek relief from the court. Triffin v. Somerset Valley Bank, 343 N.J.Super. 73, 80, 777 A.2d 993 (App. Div.2001). Our Supreme Court has described the essential purposes of the doctrine, which seeks to
In New Jersey, standing is governed by R. 4:26-1, which provides "[e]very action may be prosecuted in the name of a real party in interest. . . ." To have standing in a case, our Supreme Court has held "a party must present a sufficient stake in the outcome of the litigation, a real adverseness with respect to the subject matter, and a substantial likelihood that the party will suffer harm in the event of an unfavorable decision." In re Camden Cnty., 170 N.J. 439, 449, 790 A.2d 158 (2002).
New Jersey courts take a liberal view of standing. Generally, the threshold to prove a party's standing is "fairly low." Reaves v. Egg Harbor Twp., 277 N.J.Super. 360, 366, 649 A.2d 904 (Ch.1994). "A financial interest in the outcome ordinarily is sufficient to confer standing." Strulowitz v. Provident Life & Cas. Ins. Co., 357 N.J.Super. 454, 459, 815 A.2d 993 (App. Div.) (citing In re Camden Cnty., supra, 170 N.J. at 448, 790 A.2d 158), certif denied, 177 N.J. 220, 827 A.2d 288 (2003). "But standing is not automatic, and a litigant usually has no standing to assert the rights of a third party." Bondi v. Citigroup, Inc., 423 N.J.Super. 377, 436, 32 A.3d 1158 (App.Div.2011) (citation and internal quotation marks omitted), certif denied, 210 N.J. 478, 45 A.3d 983 (2012).
EFG argues the necessity to preserve its security interest satisfies these standards. In financing the project, EFG obtained a significant security interest in Earthmark and its interest in the project. In a November 13, 2012 letter opinion, the court acknowledged:
A condition of the loan included Earthmark's pledge of 100% of its membership interest, which
Notably, this litigation was commenced jointly by EFG and Earthmark, showing the alignment of the two entities' interests. Although Earthmark's current status or viability is not certain, its disclosed financial difficulties prevented it from fully participating in the litigation, including challenging Geo-Con's asserted damages claims. EFG argues standing should be granted, otherwise Geo-Con is effectively insulated from substantive challenge to its damage award and the resulting judgment encumbers the value of the project. See e.g., Assocs. Commercial Corp. v. Langston, 236 N.J.Super. 236, 242, 565 A.2d 702 (App.Div.) (allowing the defendant standing to challenge a lien on her house discovered after she sold it, despite the fact that escrowed proceeds would have been given to the plaintiff), certif denied, 118 N.J. 225, 570 A.2d 979 (1989).
EFG fails to cite any authority supporting its position for standing that squarely addresses a relationship matching the one presented in this litigation. EFG is a party-plaintiff in the litigation and its interest in the project was financially intertwined with Earthmark through the pledge agreement and security interest in all of Earthmark's assets, including the project. EFG suggests its interest in the ground lease gives it the right to challenge any attaching lien. This is incorrect, because at all times EFG's interest was that of a secured creditor. Although EFG could have exercised control rights over the ground lease by exercising the provisions of the pledge agreement, it chose not to do so.
EFG's merits brief also offers only general assertions supporting its claim of standing, some of which were not presented to the trial judge. These challenges offer little more than unsupported contentions of financial harm and fail to demonstrate an adverse interest to Geo-Con's claims to payment for services performed under the contract, approved by the project engineer, for which payment was not made.
In its brief under A-6202-12, EFG states the lien was inflated by $2.1 million, a consequence of work performed under the unauthorized modification agreement, and contends if it were given standing it would have defeated the claim as invalid and unenforceable. No evidence supports such an assertion. As noted, EFG declined to exercise its rights under the pledge agreement to essentially step into Earthmark's shoes and advance whatever defenses Earthmark may have to the demanded payment. Likely, EFG chose to avoid this role as it is two-edged: not only would EFG have the right to control the project and Earthmark's assets, but also it would be saddled with the corresponding responsibility to address incurred liabilities, including the debt due to Geo-Con for services rendered. In limiting its role to that of a secured lender for the project, we cannot agree EFG held a stake in any dispute between Earthmark and its vendors. See Stubaus v. Whitman, 339 N.J.Super. 38, 51, 770 A.2d 1222 (App.Div. 2001) (finding a plaintiff must demonstrate harm from a direct injury), certif denied, 171 N.J. 442, 794 A.2d 181 (2002).
We reject EFG's claim the trial judge erred by denying it standing to challenge Geo-Con's judgement against Earthmark. Having essentially made this same analysis, Judge Contillo entered a default judgment
On appeal of that order, EFG argues the entitlement to legal fees is overstated and fees should have been limited to count three of Geo-Con's complaint.
Rule 4:43-2(b) grants a trial court the discretion to require proof of the quantum of damages as well as entitlement to relief, prior to entry of default judgment. Douglas v. Harris, 35 N.J. 270, 276, 173 A.2d 1 (1961). Factual findings must establish the entitlement to relief. See Curtis v. Finneran, 83 N.J. 563, 569, 417 A.2d 15, (1980) ("In a non[-]jury civil action, the role of the trial court at the conclusion of a motion a trial is to find the facts and state conclusions of law.") (citing R. 1:7-4).
When addressing statutorily authorized fee awards for "separate claims in a complaint [which] share a common core of facts with . . . or are based on related legal theories, the trial judge, when awarding fees, must focus on the significance of the overall relief obtained by [the] plaintiff in relation to the hours reasonably expended." Silva v. Autos of Amboy, Inc., 267 N.J.Super. 546, 551, 632 A.2d 291 (App.Div.1993). Certainly, where a party presents "distinctly different claims for relief in one lawsuit, work on those unrelated claims cannot be deemed in pursuit of the ultimate result achieved." Stoney v. Maple Shade Twp., 426 N.J.Super. 297, 318, 44 A.3d 601 (App.Div.2012) (citation and internal quotation marks omitted). "However, when the p[arty]'s claims for relief `involve a common core of facts or will be based on related legal theories,' such a suit cannot be viewed as a series of discrete claims." Silva, supra, 267 N.J.Super. at 556, 632 A.2d 291 (quoting Hensley v. Eckerhart, 461 U.S. 424, 435, 103 S.Ct. 1933, 1940, 76 L.Ed.2d 40, 51 (1983)).
We note, the methodology utilized in addressing a request for statutorily authorized fees must consider the relief obtained, the justification of the fees asserted, see Litton Indus., Inc. v. IMO Indus., Inc., 200 N.J. 372, 386, 982 A.2d 420 (2009), and the reasonableness of the amount sought, Rendine v. Pantzer, 141 N.J. 292, 334-35, 661 A.2d 1202 (1995). These principles are further guided by Rule 4:43-2(b) (addressing the appropriate amount of damages awarded) and R.P.C. 1.5 (assessing the reasonableness of counsel fees requested).
We have considered the written opinion by Judge Contillo and conclude he did not mechanically allocate fees according to various claims, Silva, supra, 267 N.J.Super. at 551, 632 A.2d 291, but thoughtfully followed the above principles in making the fee award. The judge found the claims arose from a common core of facts and were based upon related legal theories, emphasized the complexity of the issues and the interrelation of the facts, and concluded the legal services rendered represented, "all legitimate, appropriate, core work that had to be done." Further, the judge analyzed the fee request against the
"[A] reviewing court will disturb a trial court's award of counsel fees `only on the rarest of occasions, and then only because of a clear abuse of discretion.'" Litton Indus., supra, 200 N.J. at 386, 982 A.2d 420 (quoting Packard-Bamberger & Co. v. Collier, 167 N.J. 427, 444, 771 A.2d 1194 (2001)). We find no basis to intervene.
Notwithstanding entry of this judgment, the contractual dispute between Geo-Con and EFG was thereafter litigated. In the related appeal, EFG challenges the order for summary judgment, maintaining the judge erred in denying summary judgment against Geo-Con for its breach of the CCA by its unauthorized modification to perform extra work. EFG also challenges the awarded judgment to Geo-Con for cure payments as unsupported by the record and contradictory to the judge's prior findings. We are not persuaded.
EFG was afforded the opportunity to prove its claims. The judge agreed Geo-Con breached a material term of the CCA, when it executed the September 7, 2010 side-agreement with Earthmark and failed to provide notice to EFG of the overruns. However, EFG offered no argument or proof it sustained damages by this breach. When specifically asked by Judge Contillo at oral argument whether damages resulted, counsel's response was "no."
To prevail on a breach of contract claim, a party must prove a valid contract between the parties, the opposing party's failure to perform a defined obligation under the contract, and the breach caused the claimant to sustained damages. Murphy v. Implicito, 392 N.J.Super. 245, 265, 920 A.2d 678 (App.Div.2007). EFG's assertion that mere proof of the breach deprives Geo-Con of any payment is legally unsupportable. See Lone v. Brown, 199 N.J.Super. 420, 425, 489 A.2d 1192 (App. Div.) (holding summary judgment on a breach of contract claim was appropriate because grievant could not assert damages), appeal dismissed, 103 N.J. 480, 511 A.2d 657 (1986).
EFG, for the first time on appeal, now lists, as resultant damages, all expenses incurred in the litigation, as well as the loss of the ground lease at sheriff's sale and the possible inability to exercise its unencumbered security interest. The costs of litigation are insufficient to support damage elements of a claim. See Satellite Gateway Commc'ns, Inc. v. Musi Dining Car Co., 110 N.J. 280, 284-85, 540 A.2d 1267 (1988) (holding attorney's fees incurred to prosecute breach of contract claim insufficient to satisfy resultant damages). The other suggested damages were not presented to the trial court. We reject EFG's late attempt to justify its position, noting
Regarding the related challenge to the judge's finding EFG elected to provide cure payments, we recite the relevant terms of parties' agreement. The CCA defines the rights and responsibilities in the event of Earthmark's default, as follows:
We disagree with EFG's assertion that liability for cure payments must be preceded by and is linked to its assumption of the construction contract. There is nothing in the language of paragraphs one and three supporting an interpretation they are interdependent. In paragraph one, which addresses a remedy available to EFG in the event Earthmark defaults under the Loan Agreement, Geo-Con agrees to permit EFG to terminate the construction contract or essentially step into Earthmark's shoes and require Geo-Con to continue performance for EFG's sole benefit. Conversely, paragraph three addresses Earthmark's breach of the construction contract with Geo-Con and affords EFG the "opportunity to remedy or cure [Earthmark's] breach for a period of thirty (30) days after receipt of notice thereof." The plain language of these distinct provisions gives EFG a the right to keep construction on track by making cure payments, while it determines whether to exercise its right to step into the shoes of Earthmark and assume responsibility to complete the construction contract, which may be made after the thirty-day cure period.
In its February 8, 2011 correspondence to Geo-Con, EFG stated it was ready to provide cure payments upon receipt of the engineer's certificate certifying payment, stating:
This determination reflects an effort to keep the project on track, pending EFG's consideration of its options. Judge Contillo agreed with EFG, concluding it had no obligation to satisfy the deferred charges
EFG now suggests other documentation was mandated under the CCA, which Geo-Con failed to provide. However, EFG did not detail what was missing to the trial judge. On appeal, EFG asserts Geo-Con should have delivered lien waivers and withdraw its work stoppage notice in writing. The fact is, no liens were filed at this stage of the dispute and payment was never made by EFG in exchange for discontinuing the work stoppage.
EFG also renews its challenge to the validity of the construction liens, maintaining the judge's statutory interpretation of N.J.S.A. 2A:44A-5(b) was erroneous. The exemption to the CLL states:
EFG reads this provision as exempting any public works project, arguing the provision for "improvements to real property" is not contingent upon a project being "contracted for and awarded by a public entity." We disagree substantially for the reasons set forth in Judge Contillo's September 20, 2011 written opinion. R. 2:11-3(e)(1)(A).
Although the mitigation bank itself fit within the definition of a public works project, the joint public-private venture neither imposed nor required substitute surety assurances, i.e., protections of payment or performance bonds or other guarantees for the benefit of contractors or material suppliers working on public projects, supporting the argument the right to place a lien on the subject property was barred. See N.J.S.A. 2A:44-143(a)(1). This distinction was detailed in the trial judge's opinion, which we conclude correctly decided this issue. R. 2:11-3(e)(1)(A).
We also reject as lacking merit, EFG's challenge to the timeliness of the lien and to its propriety. R. 2:11-3(e)(1)(E).
In the final issue raised, EFG argues the judgment was improperly entered against its successors and assigns. Plaintiff asserts Kane never participated in any of the trial court proceedings and cannot be held liable. We disagree.
Successor liability, which holds one entity accountable for another entity's debts, is an equitable doctrine that requires a case-by-case assessment. Baker v. Nat'l State Bank, 161 N.J. 220, 227-28, 736 A.2d 462 (1999). A successor entity will be held liable for the debts of its predecessor where it is a continuation of the same. Lefever v. K.P. Hovnanian Enter., 160 N.J. 307, 310, 734 A.2d 290 (1999). In this matter, the facts show Kane is 100% owned by EFG and was created for the sole purpose of assuming and succeeding to EFG's rights with respect to the project. EFG's allegation its due process rights were violated because Kane was not a party to the litigation is legally unsupported.
Geo-Con's cross-appeal challenges the trial judge's summary judgment dismissal of (1) its claim for quantum meruit against EFG, as set forth in the July 8, 2013 opinion, and (2) its assertion of an equitable lien on the mitigation credits received
The equitable doctrine of quantum meruit allows "the performing party to recoup the reasonable value of services rendered." Weichert Co. Realtors v. Ryan, 128 N.J. 427, 438, 608 A.2d 280 (1992). Recovery "rests on the equitable principle that a person shall not be allowed to enrich himself unjustly at the expense of another," id. at 437, 608 A.2d 280 (citation and internal quotation marks omitted), and requires proof of "(1) the performance of services in good faith, (2) the acceptance of the services by the person to whom they are rendered, (3) an expectation of compensation therefor, and (4) the reasonable value of the services." Starkey, Kelly, Blaney & White v. Estate of Nicolaysen, 172 N.J. 60, 68, 796 A.2d 238 (2002) (citations and internal quotation marks omitted). Geo-Con cannot meet this test.
Even if the requested compensation for services was reasonable, payment for the work performed under the side-modification agreement was between Geo-Con and Earthmark. Geo-Con ignored its obligation under the CCA to notify EFG. There was no expectation of payment from EFG or demonstrated proof EFG accepted the work and corresponding obligation or actually received a benefit therefrom.
We also reject Geo-Con's claim EFG was unjustly enriched. To demonstrate unjust enrichment, "a plaintiff must show both that defendant received a benefit and that retention of that benefit without payment would be unjust" and that the plaintiff "expected remuneration" and the failure to give remuneration unjustly enriched the defendant. VRG Corp. v. GKN Realty Corp., 135 N.J. 539, 554, 641 A.2d 519 (1994). No evidence to support this position is found within the record.
An equitable lien may lie when unjust enrichment or an express agreement to grant a lien against a specific property is shown. Id. at 546, 641 A.2d 519. Additionally, an equitable lien can be imposed, if based on the "the dictates of equity and conscience . . . a contract of reimbursement could be implied at law." Ibid.
Here, no express or implied agreement was executed to grant a lien on the underlying realty and we find no basis to infer EFG agreed to provide payment for the overrun costs. Also, as noted, there is no evidence of unjust enrichment. The trial judge's written opinion thoroughly considered the law as applied to the facts presented on this issue. We find no flaw in his analysis. R. 2:11-3(e)(1)(A).
To the extent additional arguments had been raised but were not specifically addressed, they were found to lack sufficient merit to warrant extensive discussion in our opinion. R. 2:11-3(e)(1)(E).
Affirmed.