The opinion of the court was delivered by
ST. JOHN, J.A.D.
This appeal concerns, among other issues, whether summary judgment on the issue of a breach of contract was proper. Plaintiff, Verge Properties Urban Renewal, LLC (Verge), was granted summary judgment against defendant, The Union County Improvement Authority (UCIA), based upon a breach of a redevelopment contract concerning a project in The City of Linden (City). Upon our review, in light of the record and governing law, we reverse and remand for further proceedings.
We adduce the following facts and procedural history from the record, viewed in a light most favorable to the non-moving party.
On March 26, 2001, Dennis Valvano, III, representing a limited liability company yet to be formed, submitted a proposal to develop the Project. Valvano had experience in the City constructing homes and office buildings, including the financing thereof, but had never undertaken a redevelopment project. The expected cost of acquiring the Land and preparing it for construction was anticipated to be $4.472 million, which did not include environmental remediation. Valvano estimated the construction cost for the Project to be $16 million and the construction schedule to be one year.
In October, Valvano formed Verge, and on November 21, 2001, the City awarded Verge the Project. In 2003, Verge's certificate of formation was amended to an urban renewal entity in order to receive a tax abatement pursuant to the Long Term Tax Exemption Law.
The UCIA was created pursuant to the County Improvement Authorities Law,
The City, UCIA and Verge entered into a Redevelopment Agreement dated August 15, 2003 (the Agreement). The Agreement provided that the redevelopment would occur in three phases. UCIA would convey the Land for the three phases to Verge as unimproved vacant land, with any necessary environmental remediation completed. Within three months of the date of the Agreement, UCIA was responsible for initiating the process. Within six months of the date of the Agreement, UCIA was to complete the Phase I Land acquisition either through negotiation or by eminent domain. If necessary, UCIA could obtain a three-month extension to acquire the Phase I Land, ending on May 15, 2014.
The Agreement provided that after UCIA had acquired, cleared and remediated the Land, Verge was to purchase it and develop the Project. Verge's aggregate fixed purchase price for the Phase I, II and III Land would be no more than $3 million to be paid as follows: Phase I — $1.1 million, Phase II — $.95 million and Phase III — $.95 million. In addition to the cost of purchasing the Land for resale to Verge, UCIA would incur costs for demolition, environmental remediation, legal fees and relocation of residents and businesses.
Of pertinence to this dispute, Section 2.06 of the Agreement stated:
There is no dispute that UCIA issued $3.5 million of bonds backed by the City's obligation to fund the debt service.
The Agreement set forth time periods for Verge's obligation to commence and substantially complete each phase of the Project. It was obligated to "use its best efforts to comply with the commencement dates and substantial completion dates for" each phase subject to the UCIA granting reasonable extensions as a result of adverse conditions affecting the real estate market. The Agreement also contained an expansive delay provision, which in essence provided that a party is not in default as a result of an enforced delay arising from causes beyond its reasonable control.
If the UCIA defaulted in its obligations under the Agreement prior to conveyance of property for any particular phase, within thirty days of receiving written notice from Verge, UCIA shall "proceed to cure or remedy such default or breach." If the cure is not diligently pursued or not cured within a reasonable time, Verge may institute such proceedings desirable in its opinion to cure and remedy the default. Section 3.22 required Verge to annually deliver a statement to the City and UCIA as to whether any condition or event existed which violated the Agreement.
Sections 4.02 and 4.03 of the Agreement addressed environmental testing and remediation of the Land.
The UCIA tried, unsuccessfully, to acquire the Phase I properties through negotiation. Consequently, on November 3, 2004, UCIA filed a condemnation complaint. Environmental testing disclosed significant problems necessitating remediation. In early 2005, the City granted Verge site plan approval even though the Land had not yet been acquired. Extensive litigation ensued among the UCIA and the Phase I hold-out property owners, which was resolved by consent in 2007. On July 7, 2005, in response to a request from Verge, UCIA provided a breakdown of project costs. At that time, of the original $3.5 million, only $190,000 remained. Although, as of that date, UCIA had not conveyed the Phase I Land to Verge nor fully funded the $6.5 million of costs, Verge did not send any notice of default to UCIA or the City.
Thereafter, the UCIA continued to attempt to acquire and remediate the Land. Discussions ensued between UCIA and Verge concerning demolition and remediation work in which UCIA requested Verge to undertake some of the work and accept a credit against the purchase price for the Phase One properties. In early 2006, the UCIA proceeded with the relocation of tenants and disconnection of utilities in the Phase One properties. Verge did not agree to perform the demolition work, but agreed to procure three bids from other contractors to do the work.
In August 2006, the UCIA recognized that the cost for the acquisition of the Land was likely to increase beyond the original estimate of $6.5 million. The UCIA requested a discussion with Verge, concerning who would pay the excess beyond the $6.5 million, and a revision to the Project schedule. In October, UCIA and the City agreed in principle to fund an additional $3 million, which did not materialize. The UCIA requested additional financial information from Verge, which was not provided. At this point, it was evident that the Land costs would substantially exceed the original estimates.
In January 2007, Verge applied for an extension of its site plan approval. In a February 2, 2007 email to Verge, UCIA stated that it was time to determine whether the Project would move forward and requested that Verge agree to amend the Agreement. The City extended Verge's site plan approval on March 13, 2007. In April, UCIA notified Verge that it was commencing demolition and remediation of the Phase One properties.
Verge, through its counsel, by letter dated May 23, 2007, sent a notice of default to UCIA and the City. Verge does not contend, and the record does not support, that Verge at any time prior to this notice sent UCIA any other notice of default. In the May notice, Verge asserted "the failure to timely complete the demolition and remediation of the Phase I Property has been caused by the [UCIA's] and the City's failure to finance and fund the Linden Redevelopment project pursuant to the Agreement." It further contended that the Agreement required the UCIA to fund all project costs in the amount of $6.5 million. Verge asserted because "acquisition and demolition was to occur within six months of August 15, 2003, and in no event beyond the ninety-day extension period, funding of $6,500,000 should have been completed by May 15, 2004." Further, "not only has the Authority failed to obtain any additional funding for the payment of Project Costs, but it cannot do so in the time required under the Agreement, and it cannot cure the default under the Agreement."
On May 31, 2007, UCIA responded that Verge had failed to comply with the Agreement because it had not provided a notice of default on each anniversary of the Agreement. Moreover, UCIA also informed Verge that the Project costs would exceed $6.5 million and that Verge could exercise its right to continue the Project if it assumed responsibility for the additional expenses. UCIA offered to have the Phase I properties ready for construction by the summer of 2007. On August 11, 2008, UCIA purportedly terminated the Agreement on the basis that Verge did not agree to undertake the additional costs beyond the $6.5 million.
In July 2007, Verge filed an amended complaint against UCIA and the City alleging breach of contract (Count I), breach of the duty of good faith and fair dealing (Count II), and other claims. On December 23, 2008, Verge filed a second amended complaint against UCIA and the City.
On December 17, 2010, Verge, UCIA and the City each moved for summary judgment. On March 2, 2011, the court, in a written opinion, determined that UCIA breached the Agreement. The court concluded,
Verge contended UCIA breached the Agreement by failing to timely initiate and complete the acquisition of the Phase I properties. The judge held that "a question remains for the jury as to whether the breaches were excusable under the circumstances." Verge also asserted UCIA failed to timely complete the relocation, demolition and clearance of the Phase I properties, but the court determined this issue must be decided by the jury. The court granted summary judgment to Verge on defendant's defense of promissory estoppel and to the City because there was no evidence that the City had breached the Agreement.
However, in the last paragraph of the opinion, the judge stated:
On March 16, 2011, UCIA filed for reconsideration and requested a determination that Verge was prohibited from seeking lost profits. Verge sought reconsideration of the court's grant of summary judgment to the City. On April 21, 2011, the court refused to reconsider its determination regarding the City, partially granted reconsideration to UCIA and determined that Verge could not seek lost profit damages.
The matter was tried before a jury for six days in December 2012. In both his opening statement and summation, Verge's counsel advised the jury UCIA had the obligation to fund the $6.5 million. In his summation, counsel indicated "[t]he court has already decided the [UCIA] had the obligation to fund the $6.5 million." The judge's instructions to the jury provided:
Likewise, the first sentence of the verdict sheet stated, "[t]he court has already decided that the UCIA breached the Redevelopment Agreement because the UCIA failed to fully fund $6,500,000 pursuant to the Redevelopment Agreement."
On December 5, the court denied defendant's motion to dismiss Verge's claims. The jury returned a verdict in favor of Verge and awarded damages. The court denied UCIA's motion for a judgment notwithstanding the verdict (JNOV) or a new trial. UCIA filed a notice of appeal, and Verge filed a notice of cross-appeal.
On appeal, UCIA asserts the trial court erred in its pretrial ruling that it breached the Agreement by failing to fund $6.5 million. It further contends it was error for the court to not grant a JNOV on certain issues and a new trial based on other issues. In its cross-appeal, Verge contends the trial court erred in ruling that it could not seek lost profit damages.
We review the trial court's entry of summary judgment in accordance with the standard set forth in
Contractual interpretation is a legal matter ordinarily suitable for resolution on summary judgment.
To the extent any ambiguity exists, that is, to the extent that a contractual term is susceptible of more than one reasonable interpretation,
Applying these principles, we conclude the language used in Section 2.06 of the Agreement concerning the timing of the UCIA's funding obligation was sufficiently ambiguous to preclude summary judgment. First, the language did not expressly require UCIA to fund by a date certain. It required "all Project Costs will be funded by the Authority to an amount not to exceed the sum of Six Million Five Hundred Thousand Dollars ($6,500,00.00) to be offset in part by reimbursement from [Verge] upon payment of the purchase price set forth in Section 2.05 herein." UCIA's funding obligation arises at the time that Project Costs become due and payable. Therefore, if the Project is delayed, and such delay is not a default by UCIA, the funding obligation would also be delayed. Further, the Agreement could reasonably be construed to allow UCIA to use payments by Verge for Project Costs. As an example, had the UCIA been able to purchase the Phase I properties from third parties for an aggregate amount of $1.1 million or less, it would not have been a breach of the Agreement for the UCIA to schedule simultaneous purchase closings and a sale closing to Verge, and use Verge's payment to pay the sellers.
UCIA contends it is entitled to a new trial because the court improperly instructed the jury that it had breached the Agreement "by failing to fund $6.5 million to acquire, relocate, demolish and remediate the land." Verge responds that because no objection to the charge was raised by UCIA, our standard of review should be plain error.
A proper jury instruction provides "`an explanation of the applicable legal principles and how they are to be applied in light of the parties' contentions and the evidence produced in the case.'"
With these principles in mind, we must consider whether the jury charge and verdict sheet, and statements during the trial that UCIA had breached the Agreement, warrant reversal. We conclude the statements, jury instruction and verdict sheet are of such a nature as to have been clearly capable of producing an unjust result, and therefore we are constrained to reverse and remand for a new trial. Given our decision, we need not address the other issues raised by UCIA in its appeal or the issue asserted by Verge in its cross appeal.
Reversed and remanded for further proceedings consistent with this opinion. We do not retain jurisdiction.