Summary: ORDER FOR EXTENSION OF DEADLINE TO SUBMIT PRE-TRIAL ORDER KENNETH J. GONZALES , District Judge . THIS MATTER, having come before the court upon the "Joint Motion for Extension of Time to Submit Pre-Trial Order" and the Court having considered the motion and being otherwise fully advised in the premises, FINDS that the grounds for relief requested by Plaintiff and Defendant is well taken and should be adopted as the order of this court. IT IS THEREFORE ORDERED that the deadline for submissi
Summary: ORDER FOR EXTENSION OF DEADLINE TO SUBMIT PRE-TRIAL ORDER KENNETH J. GONZALES , District Judge . THIS MATTER, having come before the court upon the "Joint Motion for Extension of Time to Submit Pre-Trial Order" and the Court having considered the motion and being otherwise fully advised in the premises, FINDS that the grounds for relief requested by Plaintiff and Defendant is well taken and should be adopted as the order of this court. IT IS THEREFORE ORDERED that the deadline for submissio..
More
ORDER FOR EXTENSION OF DEADLINE TO SUBMIT PRE-TRIAL ORDER
KENNETH J. GONZALES, District Judge.
THIS MATTER, having come before the court upon the "Joint Motion for Extension of Time to Submit Pre-Trial Order" and the Court having considered the motion and being otherwise fully advised in the premises, FINDS that the grounds for relief requested by Plaintiff and Defendant is well taken and should be adopted as the order of this court.
IT IS THEREFORE ORDERED that the deadline for submission of the Pre-Trial Order to the Court is extended and shall be determined after a ruling on the motions for summary judgment filed in this case.