C. W. HOFFMAN, Jr., Magistrate Judge.
This matter is before the Court on Defendants' Motion to Stay Litigation (#31), filed June 2, 2014; Plaintiff/Counterdefendant KBW Associates, Inc. and Third-Party Defendant International Fidelity Insurance Company's Response (#35), filed June 18, 2014; and Defendants' Reply (#38), filed July 3, 2014.
The complaint in this matter was filed on September 26, 2013. (#1). The allegations are straightforward. In 2009, Defendant Jaynes Corporation, Inc. ("Jaynes") contracted with the United States Army Corps of Engineers ("COE") to construct additions to existing buildings at Creech Air Force Base, located in Indian Springs, Nevada. The construction project was initially scheduled to begin in 2009, with completion scheduled for early 2011. Plaintiff KBW Associates, Inc. ("KBW") began negotiating to construct the metal framing and outer shell of the buildings with Jaynes in May 2011, and entered into a subcontract for the construction of the same on August 11, 2011. See Compl. (#1) at ¶¶ 7-10.
KBW alleges that during the negotiation of the contract Jaynes represented that the contracted work would be performed during the time period of November 2011 through April 2012. Compl. (#1) at ¶ 13. Shortly after entering into the contract, KBW alleges that it procured shop drawings for Jaynes review and approval, but the work was delayed by Jaynes failure to promptly review and approve the shop drawings. Once approved, KBW alleges that it promptly ordered the materials necessary to begin construction but, upon commencement of construction, was delayed by various conditions imposed by Jaynes that were contrary to the terms of the contractual agreement. Id. at ¶¶ 14, 15. The resulting delay is characterized as a "pattern of mismanagement" evidenced by (1) failure to timely approve work, (2) unilateral imposition of work beyond the contractual requirements, and (3) improper work scheduling. Id. at ¶ 16. KBW seeks damages for (1) breach of contract, (2) unjust enrichment, and (3) breach of the implied covenant of good faith and fair dealing. Id. at ¶¶ 20-40.
Jaynes acknowledges that it entered into a contract with the COE for work to be performed at Creech Air Force Base, and that it subcontracted with KBW on the project. (#8) at ¶¶ 7-10. Jaynes denies all allegations that it mismanaged the project or that KBW is entitled to damages or proceeds from the bond. Jaynes asserts several affirmative defenses and has filed counterclaims for (1) breach of contract, (2) breach of the covenant of good faith and fair dealing, and (3) unjust enrichment. The affirmative defenses and counterclaims are based generally on allegations that KBW failed to perform material requirements of the contract, failed to meet construction schedules, failed to perform as directed by the contract, failed to cure deficient work, failed to warranty work, and abandoned the project prior to completion. Jaynes also filed a third-party complaint against International Fidelity Insurance Company ("International Fidelity"), alleging that it issued a performance bond in favor of Jaynes and is obligated to remedy KBW's default and breach, perform KBW's outstanding scope of work, or pay all amounts incurred by Jaynes to remedy the alleged breach.
On December 20, 2013, Jaynes filed a proposed discovery plan and scheduling order requesting an additional six months beyond the standard deadlines to complete discovery. The additional time being necessary to allow Jaynes to negotiate a dispute with the COE regarding a liquidated damages assessment under the prime contract.
Approximately four months after entry of the scheduling order, the parties submitted a stipulation to extend the discovery deadlines. (#29). The basis for the requested extension was the continued attempts to resolve the dispute between Jaynes and the COE. The parties indicated that they were attempting to reach an agreement on a stay to accommodate the ongoing dispute with the COE. Other than initial disclosures made pursuant to Rule 26(a)(1), the parties had not engaged in any substantive discovery at the time the stipulation was filed. The requested extension was approved. (#30).
Shortly thereafter, Jaynes filed its motion to stay the litigation pending resolution of its dispute with the COE. In the motion, the primary basis for the stay is identified as the contract between KBW and Jaynes.
KBW opposes the motion claiming it is based on nothing more than an incorrect, unilateral interpretation of the subcontract. (#35) at 2:22-23. Setting aside the allegedly improper reliance on an allegedly inapplicable contractual provision, KBW asserts that Jaynes did not meet its burden to show that a stay is appropriate. According to KBW, Jaynes is using the Corps litigation as leverage in this dispute without providing any substantive support that the two are related. KBW further asserts that a stay in this litigation in favor of the Corps litigation would be unfairly prejudicial, as KBW is not permitted to participate in the Corps litigation and the request for stay is untimely. Lastly, KBW asserts that there is no basis for a fee award based on the alleged breach of contract.
In reply, Jaynes reiterates its position that KBW is contractually obligated to agree to a stay. Jaynes continues to characterize this litigation and the Corps litigation as "concurrent actions," and argues that KBW's claims will be directly impacted by the outcome in the Corps litigation, which addresses the liquidated damages assessment against Jaynes. The two actions are intertwined, according to Jaynes, because (1) KBW's delays and misconduct in performance of the contract are the reason for the liquidated damages assessment from the COE and (2) KBW's delay damages, if any, were caused by the COE, not Jaynes. Thus, permitting this litigation to continue without a stay would result in the avoidable expenditure of unnecessary and duplicative time, expense, and effort. Whereas, granting the stay would eliminate the potential for conflicting liabilities and damages because Jaynes liability to KBW, if any, cannot be determined until a final determination is made in the Corps litigation. Jaynes does not dispute that it has withheld payment to KBW while awaiting determination of a liquidated damages assessment. Even if the contractual provision to agree to a stay does not apply, Jaynes argues a stay is appropriate as "KBW has not identified any cognizable harm or prejudice from a stay" in permitting the Corps litigation to be resolved before the claims of KBW, a lower-tiered subcontractor, are adjudicated.
A court has broad discretionary authority to control its own docket, which extends to the issuance of a stay. See Landis v. North American Co., 299 U.S. 248, 254 (1936).
The primary argument advanced in support of the requested stay is a contractual provision. The existence of a contractual provision requiring a party to agree to a stay does not, standing alone, require the court to grant the stay because it is the court, not the parties, who determines whether to enter a stay. Nor does a contractual provision requiring parties to agree to a stay minimize the requirement that the moving party meet its burden to show that a stay is warranted. The court would certainly give weight to the rationale offered for entering into such a provision, but that rationale must be made clear through the factors the court weighs in determining whether a stay is appropriate, including factors affecting the court itself.
Even assuming application of the contractual provision advanced by Jaynes, a stay is not appropriate based solely on the contract language. The contractual provision in question provides: "If Subcontractor files a Miller Act suit or other action against the Contractor, its payment bond surety, or both, which may relate in whole or in part to the rights or duties of the Owner as the Subcontractor's work, Subcontractor shall, upon the Contractor's request, consent to a stay of such suit or action
The Corps litigation arises from the prime contract entered into between the COE and Jaynes. The prime contract is subject to the Contracts Disputes Act ("CDA"), 41 U.S.C. §§ 7101 et seq. The CDA provides an administrative claims process for contract-based claims made against the federal government and applies to any express or implied contract entered into by an executive agency for the procurement of property or services. 41 U.S.C. § 7102. Under the CDA, claims are first submitted in writing to the contracting officer, who must issue a decision in writing. 41 U.S.C. § 7103. The time for issuance of a decision by the contracting officer depends upon the monetary value of the claim under consideration. The contracting officer has 60 days to issue a decision on claims for less than $100K. 41 U.S.C. § 7103(f)(1). The contracting officer must issue a decision on claims in excess of $100K within 60 days or notify the contractor of a larger time within which the decision will be reached. 41 U.S.C. § 7103(f)(2). Any extension of the time period for the contracting officer to issue a decision must be within a "reasonable time" subject to consideration of several factors.
The decision by a contracting officer is "final and conclusive," but subject to appeal in the manner authorized by the CDA. See Palafox Street Associates, L.P. v. United States, 114 Fed. Cl. 773, 781 (Fed. Cl. 2014) ("the CDA requires that a contracting officer issue a final decision on the claim before it can be appealed") (citations omitted). Upon receipt of the contracting officer's final decision, the contractor must elect either to appeal the decision to either the appropriate board of contract appeals or the Court of Federal Claims. 41 U.S.C. §§ 7104(a)-(b)(1). Once a contractor chooses the forum in which to lodge its appeal, the choice is binding and the contractor is no longer able to pursue its appeal in the alternative forum. Palafox Street Associate, L.P., 114 Fed. Cl. at 781 citing Nat'l Neighbors, Inc. v. United States, 839 F.2d 1539, 1542 (Fed. Cir. 1988) ("[T]he binding election of forums is an `either-or' alternative, and, as such, does not provide a contractor with dual avenues for contesting a contracting officer's adverse decision."); but see Bonneville Assocs. v. United States, 43 F.3d 649, 653 (Fed. Cir. 1994) (the election doctrine only applies if the forum chosen by the contractor had jurisdiction over the appeal).
It is the undersigned's view that the contract language at issue does not contemplate an agreement to an undefined stay pending final resolution of an appeal of a contracting officer's final decision. Jaynes has made no effort to explain or otherwise brief how the language "exhaustion of procedures for resolution" should be interpreted to mean "final resolution" of any claim, including an appeal. Construed most broadly, the contract language could be extended to the point of election for an appeal of a final decision. The more accurate construction takes into account that the decision issued by the contracting officer is a "final decision" under the CDA. Thus, the term "exhaustion of procedures" is more appropriately viewed as those administrative procedures which must be satisfied
Based on the record before the Court, Jaynes submitted its request for decision (attached as Exhibit 4 to Jaynes' Reply (#38)) contesting the liquidated damages assessment in the Corps litigation on or about May 16, 2014. Absent notice of an extension, the contracting officer's final decision on the claim would have been due in July 2014. Approximately five months have passed since the time a final decision would have been due. Assuming timeliness of a final decision from the contracting officer, the time period for appeal to an agency board under section 7104(a) has likely expired, and there would be less time than appears necessary to complete discovery in this matter to file an appeal under section 7104(b)(1). Consequently, there is no justification for this litigation not to go forward.
Moreover, Jaynes acknowledgment that it believes any stay of this matter should extend through the appeals process underscores an additional, important issue. By its own admission, Jaynes does not know how long such a process could take, but it is not inconceivable that such a stay would be measured in years, not months or weeks. The Ninth Circuit made clear that, while a stay pending resolution of independent proceedings may be appropriate, such a stay "should not be granted unless it appears likely the other proceedings will be concluded within a reasonable time in relation to the urgency of the claims." See Leyva, 593 F.2d at 863. The delay in payment of monies contractually owed to a subcontractor on a construction project, though perhaps not irreparable, still constitutes damage, which increases the longer payment is delayed. Were there any "reasonable time" in which Jaynes could assure the Corps litigation would be resolved, perhaps the Court would be more amenable to the stay. There is, however, no assurance Jaynes can provide that would transform the stay, as requested, into something other than an open-ended stay.
Jaynes also argues that "KBW has not articulated any comprehensible damage or prejudice" that would accrue in event of a stay. This, however, incorrectly shifts the burden to KBW. It is Jaynes, the moving party, who bears the burden of making "out a clear case of hardship or inequity in being required to go forward, if there is even a fair possibility that the stay . . . will work damage to someone else." CMAX, Inc. v. Hall, 300 F.2d 265, 268 (9th Cir. 1962) citing Landis, 299 U.S. at 255.
In reviewing the briefing submitted by Jaynes in support of the request for stay, the undersigned found footnote 3 in Jaynes reply illuminating. It provides: "Jaynes anticipates that resolution of the liquidated damages issue [Corps litigation] will resolve some, but not all of the parties claims and defenses. However, if Jaynes is unsuccessful, Jaynes will be compelled to proceed with this instant action asserting backcharges and offsets against KBW for its delay, and its right to seek indemnification from KBW, pursuant to the parties' contract." Jaynes makes plain that, regardless of the outcome of the Corps litigation, this litigation will not be resolved. Jaynes appears to minimize the impact of the Corps litigation by claiming, for example that: (1) "resolution of the [Corps litigation] will
This position further undercuts Jaynes' argument that a stay is necessary to avoid conflicting or inconsistent decisions, as it acknowledges the reality that this litigation would continue regardless of the outcome in the Corps litigation. The proposed stay is, in the Court's view, an attempt to obtain leverage in the current suit with no guarantee, or even likelihood, that the Corps litigation has any impact on this case. Regardless of the outcome of the Corps litigation, Jaynes will still have to show that delay was caused by KBW. There is nothing before the Court to suggest that KBW is required to adjust its claims based on the outcome of the Corps litigation. This also lessens any concern regarding the potential "duplication" of work, as it is clear that substantial discovery will need to take place regardless of the outcome of the Corps litigation.
Ultimately, the Court does not believe that staying this case for an indefinite period to accommodate the Corps litigation would have any appreciable affect on simplifying the issues. Nor will permitting the cases to go forward simultaneously complicate the issues of proof or questions of law. Discovery should proceed. The parties are instructed to submit a new discovery plan and scheduling order by February 27, 2015.
Based on the foregoing and good cause appearing,