ANDREW P. GORDON, District Judge.
A developer agreed to make off-site improvements to public roads and other property in exchange for the City of North Las Vegas ("City") allowing the developer to build a new residential community. The City also required the developer to purchase a bond to guarantee to the City that the developer will complete the off-site improvements (the "Bond"). The Bond was issued by defendant Insurance Company of the West ("ICW")
The developer went bankrupt before it finished building the community or the off-site improvements. Plaintiff Camino Properties, LLC purchased the half-built community and endeavored to finish it. The City assigned its rights under the Bond to Camino, and Camino, in turn, requested that ICW honor the Bond and pay for the off-site improvements. ICW refused.
Camino claims it finished the off-site improvements on its own and brought this lawsuit to collect on the Bond from ICW. ICW moves for summary judgment, arguing that (1) Camino's claims on the Bond are barred by the statute of limitations; (2) only the City, not Camino, can enforce the Bond; and (3) the Bond is discharged because of a failed condition precedent. Camino also moves for partial summary judgment that ICW is liable to Camino under the Bond.
I deny all motions. There are genuine disputes of fact about whether the statute of limitations applies, whether Camino can enforce the Bond, and whether ICW is relieved of its obligations. Summary judgment is thus not warranted.
When a developer seeks to build a new residential community, Nevada law allows cities to require that the developer make off-cite improvements to public property surrounding the new homes, such as road improvements. Cities do this by requiring the developer to enter into an "off-site improvement agreement" with the city. This agreement specifies the improvements the developer must make. The city also may require that the developer buy a performance bond to guarantee that the developer will finish the off-site improvements. If the developer fails to make the improvements, the bond obligates the surety to either complete the improvements or pay for someone else to complete them.
In this case, a developer wished to build a residential community in North Las Vegas. In 2005, this original developer entered into an off-site improvement agreement with the City.
The original developer went bankrupt before it could finish the community and off-site improvements. The City notified ICW of the developer's default, and ICW endeavored to complete the improvements itself (rather than pay out the Bond's penal sum of roughly $750,000).
The following year, Camino purchased the mostly-built residential community and began finishing the project.
Summary judgment is appropriate when "the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law."
If the moving party demonstrates the absence of any genuine issue of material fact, the burden shifts to the nonmoving party to "set forth specific facts showing that there is a genuine issue for trial."
A party must support or refute the assertion of a fact with admissible evidence.
ICW presents three theories for why it should not be liable to Camino on the performance bond: (1) the statute of limitations period has passed, (2) the assignment to Camino is invalid, and (3) the City's failure to notify ICW of defects in their performance relieves ICW of its bond obligations.
The parties dispute both (1) which statute of limitations period applies to Camino's claim on the Bond and (2) the date the limitations period commences.
ICW argues that Camino's claim on the Bond is governed by the three-year limitations period for claims arising from statutory liabilities. NRS §11.190(3)(a). Camino argues the six-year contract limitations period applies because its claim on the Bond is contractual. NRS §11.190(1)(b).
Generally, the nature of the principal's liability (not the surety's liability) defines the applicable limitations period. For example, in Torrealba v. Kesmetis, the Nevada Supreme Court held that the three-year limitations period applied to a claim on a notary's performance bond.
Here, there is no allegation that either the original developer or ICW violated a statute. ICW's liability, if any, arises from the Bond and from the original developer's breach of the off-site improvement agreement. These are contractual claims subject to the contractual limitations period of six years.
ICW argues that Camino's Bond claim is a statutory liability claim because a statute required the developer to buy the Bond. But, as explained above, whether the bond is required by statute is irrelevant; the proper inquiry is whether the principal's liability arose from statute. ICW primarily relies on Torrealba v. Kesmetis, and Sonoma County v. Hall
Unlike in Torrealba and Sonoma, the Bond here guarantees compliance with a contract, not a statute. The terms of the off-site agreement are not prescribed by statute. NRS §278.380 merely allowed the City to require the developer to enter into the off-site agreement and procure a bond. The developer, and ICW, are liable only if the off-site agreement was breached. There is no claim that either violated a statute.
ICW cannot be right that liabilities arising from a contract, where the contract is required by statute, is a "liability by statute." Indeed, drivers in this state are required to enter into a contract for insurance.
The principal's and ICW's liability are thus contractual liabilities with a six-year limitations period.
The general rule in Nevada is that a cause of action accrues on the date a lawsuit could first be brought.
ICW argues it could have been sued on the Bond the day the principal was obligated to complete the off-site improvements, which is March 17, 2007. It argues that March 17, 2007 is the date Camino's bond action accrued. But as ICW notes in other places during its briefing, the Bond specifically gave ICW the option of completing the improvements itself in lieu of paying out the Bond's penal sum. By the terms of the Bond, the City could not have sued ICW until ICW failed to complete the improvements.
The relevant date for the statute of limitations calculation is December of 2007, six years before Camino brought this case. In other words, the statute of limitations bars Camino's claims only if the City could have brought its claim before December of 2007. But ICW has submitted no evidence the City knew of ICW's alleged failure to complete the improvements before December of 2007. Indeed, ICW admits it continued working on the improvements long after then.
ICW elected to conduct the improvements to the property rather than paying out the penal sum. ICW cannot now claim the City sat on its rights by allowing ICW the opportunity to finish the project. ICW's motion for summary judgment based on the statute of limitations is denied.
ICW next argues the City's assignment of the Bond to Camino was invalid and that
Camino therefore cannot enforce the Bond. ICW's sole argument against the assignment is that some courts in other states have held that municipalities may not assign their rights under performance bonds.
But nearly every case after Morro has narrowed its holding. Courts appear to now generally agree that municipalities may assign their rights under a performance bond if the assignment is made for the purpose of completing the improvements in question. These courts reason that a surety like ICW should not "be exonerated . . . simply because the bargained-for improvements were completed by an assignee of the claim by agreement with the municipality. The purpose of the bond, to provide the means by which a municipality may insure completion of a bargained for performance, will be fulfilled" by allowing assignment.
In its reply, ICW appears to now agree the City could assign its right under the Bond if the assignment was for the purpose of completing the improvements. But ICW argues that the City did not assign its rights for the purpose of completing the improvements. Instead, ICW argues, the City assigned its rights "for Plaintiff's sole financial benefit."
Camino has provided evidence raising a genuine dispute about whether the City assigned its rights under the Bond, at least in part, to facilitate completion of the off-site improvements.
Even if Nevada would adopt the assignment rule ICW raises, it has not established it applies here.
A party's contractual obligations may be excused if another party has not satisfied a condition precedent to the obligations. But, contractual promises are not generally interpreted to be conditions to another party's performance "unless it is clear that this is what the parties intended."
ICW argues that its obligations on the bond are "conditioned" on the City notifying ICW before finishing the off-site improvements. ICW points to the Bond which states that "in case of default by Principal, [ICW] may assume and complete or procure completion of the obligations of Principal." Although the City originally informed ICW of the default and allowed ICW to work on the off-site improvements, ICW argues the City should have also informed ICW that the off-site work had not been properly completed before having a third party finish it.
ICW provides no legal authority or analysis to suggest that the City's failure to notify ICW should be read as a "condition precedent" rendering the Bond unenforceable. The City notified ICW of the principal's default as the Bond required. The City gave ICW the opportunity to finish the improvements, as the Bond required. There is no clear language in the Bond suggesting that once ICW had failed to properly finish the project the City again had to notify ICW before finishing it itself. Even if the Bond did require notice, there is no indication the parties intended notification to be a condition precedent to ICW's obligations.
ICW has not provided sufficient evidence or authority for me to find the parties intended notification to be a condition precedent to ICW's obligation. ICW's motion for summary judgment is therefore denied.
Camino asks for partial summary judgment that the Bond was validly assigned and that ICW is liable under the Bond. Camino first argues there is no genuine dispute about whether the City assigned the bond for the purposes of completing the off-site improvements.
Camino also seeks partial summary judgment that ICW is liable for breach of the Bond. As explained above, Camino has not established a lack of genuine dispute about whether the assignment was valid—so it is not entitled to summary judgment on ICW's liability. Regardless, there are genuine disputes about ICW's liability on the Bond. For example, ICW has submitted evidence from which a reasonable jury could find that the City, and therefore its assignee Camino, agreed to relieve ICW of its obligations under the Bond by negotiating and signing off on the improvements ICW completed.
I therefore deny Camino's request for partial summary judgment on whether its assignment is valid and whether ICW is liable for a breach.
ICW moves to strike portions of two affidavits Camino relies on, arguing the affiants have no personal knowledge of the statements they make. In ruling on the parties' motions for summary judgment, I have not relied on most of these disputed statements. The one statement I have considered in ruling on defendants' motion for summary judgment appears to be supported by personal knowledge. I considered Mr. Walter's statement about whether the City assigned the Bond for the purposes of completing the improvements. But Mr. Walters avers that he directly participated in the assignment discussions with the City, and ICW provides no evidence indicating Mr. Walters lacks personal knowledge of these events. I thus deny ICW's motions to strike.
IT IS THEREFORE ORDERED that defendant's motion for summary judgment (Dkt. #33) is DENIED.
IT IS FURTHER ORDERED that plaintiff's motion for summary judgment (Dkt. #44) is DENIED.
IT IS FURTHER ORDERED that defendant's motions to strike (Dkt. ##40, 41) are DENIED.
IT IS FURTHER ORDERED that defendant's motions for oral argument (Dkt. ##56, 57) are DENIED.