Summary: STIPULATION AND ORDER TO EXTEND BRIEFING SCHEDULE ON CUSTOM STUD, INC.'S. MOTION FOR PARTIAL JUDGMENT ON THE PLEADINGS (DKT. 172 RICHARD F. BOULWARE, II , District Judge . Plaintiff ClarkWestern Dietrich Building Systems LLC d/b/a ClarkDietrich ("ClarkDietrich") and Custom Stud, Inc. ("Custom Stud"), by and through their respective counsel, hereby stipulate and agree that the time for ClarkDietrich to file its response to Custom Stud's Motion for Partial Judgment on the Pleadings (Dkt. 172)
More

STIPULATION AND ORDER TO EXTEND BRIEFING SCHEDULE ON CUSTOM STUD, INC.'S. MOTION FOR PARTIAL JUDGMENT ON THE PLEADINGS (DKT. 172

Plaintiff ClarkWestern Dietrich Building Systems LLC d/b/a ClarkDietrich ("ClarkDietrich") and Custom Stud, Inc. ("Custom Stud"), by and through their respective counsel, hereby stipulate and agree that the time for ClarkDietrich to file its response to Custom Stud's Motion for Partial Judgment on the Pleadings (Dkt. 172) ("Motion") filed on August 6, 2015 shall be extended from August 24, 2015 to September 8, 2015. The parties further agree that Custom Stud's reply in support of the Motion shall be due no later than September 25, 2015. ClarkDietrich respectfully requests a short extension to respond to the issues raised in the Motion and Custom Stud similarly requests additional time to file its reply. This is the parties' first request.

The undersigned represent this stipulation is not intended for purposes of delay.

IT IS SO ORDERED.