RICHARD F. BOULWARE, II, District Judge.
This matter is before the Court on Motions for Summary Judgment filed by Plaintiff Autotel and by Defendant Bureau of Land Management (BLM). ECF No. 23, 27. In this case, Autotel seeks judicial review under the Administrative Procedure Act, 5 U.S.C. § 701 et seq., of the BLM's denial of its application to build a communications tower on Sunrise Mountain.
Autotel commenced this action on February 1, 2012, following the BLM's rejection in January 2007 of its application to build a tower on Sunrise Mountain and the February 2008 decision of the Interior Board of Land Appeals (IBLA) affirming the BLM's denial. Admin. Record 24-26, 3-7 ("AR"). The following facts are taken from the Administrative Record.
The Federal Land Policy and Management Act of 1976 (FLPMA) directs the Secretary of the Interior to study "those roadless areas of five thousand acres or more" identified as having wilderness characteristics as described in the Wilderness Act, 16 U.S.C. § 1101 et seq., and to make recommendations "as to the suitability or nonsuitability of each such area . . . for preservation as wilderness." 43 U.S.C. § 1782(a); AR 33-34. Until Congress acts on such recommendations, "the Secretary shall continue to manage such lands according to his authority under [the FLPMA] . . . in a manner so as not to impair the suitability of such areas for preservation of wilderness."
The BLM, under the direction of the Secretary, has implemented the FLPMA's mandate by adopting an Interim Management Policy for Lands Under Wilderness Review ("Policy"). AR 31-32. The Policy establishes guidelines for allowing or prohibiting particular uses of land (known as rights of way) in ISAs, including Sunrise Mountain. AR 4-6. Generally, under the Policy, rights of way that existed prior to the enactment of the FLPMA and adoption of the Policy "may be renewed if they are still being used for their authorized purpose." AR 31. Holders of existing rights of way may perform "[n]ecessary and routine maintenance" to keep their facilities "in a safe and reliable condition."
"For a use or facility to be nonimpairing, it must be temporary, must not create surface disturbance, and must be easily and immediately terminated upon wilderness designation." AR 25.
On April 4, 2003, Autotel filed an application with the BLM seeking to obtain a 30-year right of way on Sunrise Mountain. AR 68-79. On July 10, 2003, the BLM returned Autotel's application and accompanying fee and stated that it would not process the application in light of the proposed site's location within the Sunrise Instant Study Area and within the Rainbow Gardens Area of Critical Environmental Concern (ACEC).
Autotel's proposed construction consisted of a 12-by-20 foot metal building, a tower standing 80 feet high, a generator, and a propane tank. AR 68. The application stated that Autotel's tower would require the excavation of approximately 16 cubic yards of rock. AR 69. The building would sit on a concrete slab and the construction would be done with the aid of a helicopter. AR 70. Autotel proposed to build in a previously excavated area approximately 30 feet north of an existing building.
The BLM rejected Autotel's proposal in a written decision dated January 12, 2007. AR 24-26. In its decision, BLM stated that it denied Autotel's application because the proposed facility was within the Sunrise Mountain ISA and did not satisfy the nonimpairment criteria outlined in the Policy. AR 24-25. First, the BLM determined that Autotel's facility was not temporary. The BLM stated that "[t]he proposed facility is intended to accommodate a use that is long term and only made temporary by the caveat that it could be removed if and at the time the area were designated as wilderness." AR 25. Second, the BLM found that the proposed tower would not be easily and immediately terminated upon wilderness designation because if the Sunrise ISA were designated as wilderness, the Wilderness Act would prohibit the use of motorized vehicles and aircraft to break up and transport the building materials.
Autotel appealed the BLM's decision to the IBLA on February 5, 2007. AR 23. Autotel appealed the BLM's decision to the IBLA on three grounds. First, Autotel argued that the BLM erred in finding Autotel's proposed use to not be temporary. AR 19. Autotel claimed that its proposed tower was temporary because Autotel had acknowledged in a letter to the BLM that its right of way would terminate and the tower would be removed if the Sunrise ISA were designated as wilderness.
The IBLA issued its decision on February 1, 2008. AR 3-7. The IBLA affirmed the BLM's decision, finding that Autotel had not met its burden of showing that the BLM committed a material factual error, failed to consider all relevant factors, or failed to provide a rational basis for its decision. AR 6. The IBLA did find that Autotel was correct that the BLM erroneously interpreted the term "temporary" in the Policy.
The BLM filed the Administrative Record with the Court on June 19, 2012. ECF No. 12. On January 2, 2013, Autotel moved to supplement the AR with the records of certain other Sunrise Mountain right of way holders, whom it identified as "Metro," "Crown," and "Frontier."
The BLM filed the Supplemental Administrative Record ("SAR") with the Court on April 23, 2015. ECF No. 54. The SAR consisted of all documents in the BLM's possession relating to the Metro, Crown, and Frontier communication facilities located at Sunrise Mountain from the time it was designated as an ISA to the present. The parties were then permitted to supplement their Motions for Summary Judgment with facts or arguments derived from the SAR. The Court held oral argument on the parties' motions on August 17, 2015, after which it took the motions under submission. ECF No. 61. This Order follows.
Section 706(2) of the APA provides, as relevant here, that an agency action must be upheld on review unless it is "arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law." 5 U.S.C. § 706(2)(A). Under this standard of review, the agency must "examine the relevant data and articulate a satisfactory explanation for its action."
Under the arbitrary and capricious standard of review, "[a]gency action is valid if a reasonable basis exists for [the agency's] decision. A reasonable basis exists where the agency considered the relevant factors and articulated a rational connection between the facts found and the choices made."
Agency action may also be arbitrary if it treats similarly situated individuals differently without adhering to established guidelines or factors.
Finally, in order to be subject to judicial review under the APA, an agency action must be either reviewable by statute or considered a "final agency action for which there is no other adequate remedy in a court." 5 U.S.C. § 704. Here, the parties do not dispute that the IBLA's decision affirming the BLM's denial of Autotel's application was a final agency action.
Autotel's central argument at summary judgment is that the BLM acted arbitrarily and capriciously by treating Autotel differently from other applicants who have been granted rights of way and have built towers on Sunrise Mountain. These users are identified in the SAR as the Las Vegas Metropolitan Police Department ("Metro"), Crown Communications ("Crown"), and Frontier Radio, Inc. ("Frontier"). SAR 0, 449, 1305. After reviewing the AR, SAR, and the parties' arguments made in their briefs and at the August 17, 2015 hearing, the Court concludes that the BLM's decision was not arbitrary or capricious. To the extent that Metro, Crown, and Frontier were similarly situated to Autotel, the BLM did not treat these users differently from Autotel. The Court also concludes that the BLM's decision on Autotel's application itself was not arbitrary or capricious. Thus, the Court grants summary judgment in favor of the BLM and against Autotel.
The Court has reviewed the BLM's decisions on various applications filed by Metro, Crown, and Frontier contained within the SAR. Based upon this review, the Court concludes that there were few instances in which these users could be considered similarly situated to Autotel, and in those instances, the BLM did not treat them differently from Autotel.
The Court finds that Metro, Crown, and Frontier were not similarly situated to Autotel before 1995, when the version of the Policy that governed Autotel's application was adopted.
To the extent Metro, Crown, and Frontier were similarly situated to Autotel after the adoption of the Policy in 1995, the Court finds that they were not treated differently from Autotel. In its briefs, Autotel identifies a list of instances in which it argues the BLM allowed additional activity on Sunrise Mountain by these existing users. Autotel argues that each of these activities constitutes dissimilar treatment of similarly situated users. However, based upon the Court's review, the Supplemental Administrative Record only contains four instances in which additional construction or activity took place that could potentially support Autotel's claims, and in each instance the BLM consistently applied the nonimpairment criteria in the Policy.
First, Autotel argues that the BLM's decision to allow Metro to sublet their right of way in 1996 is evidence of dissimilar treatment. The Court does not agree. The SAR shows that on October 29, 1996, the BLM granted Metro's application "to amend their right-of-way grant to allow subleasing to telecommunication users and to serve as site facility manager." SAR 275. Although the subleasing conditions appear to contemplate the possibility of construction by subtenants, any such plans must first be approved by the BLM. SAR 277. This grant of subleasing authority is consistent with the Policy, which allows existing rights of way to "be renewed if they are still being used for their authorized purpose" and permits "any additional actions authorized in the original permit. . . ." AR 31. Autotel's application, by contrast, was governed by the criteria for new rights of way set forth in the Policy. Therefore, Autotel's application for a new right of way was not similarly situated to Metro's application to permit subleasing on its existing right of way.
Second, Autotel points to Crown's application and construction in 2000 and 2001 of six additional 35-foot pipes to relocate antennas that were located on its existing tower. SAR 1034. The SAR reveals that the BLM never authorized the construction of these additional pipes. The BLM sent a letter to Crown on July 18, 2001 informing Crown that it had constructed the pipes without BLM's approval and demanding an explanation of why six poles were needed instead of one. SAR 1050. Crown responded on August 29, 2001, stating that the poles were added to "mitigate environmental impacts" and because of space restrictions. Crown also stated that the Project Manager for the site left the company and the new manager unknowingly commenced construction without the BLM's permission. SAR 1025. The SAR does not indicate that the BLM ever responded to this communication or that it ever authorized the construction.
While Autotel argues that this construction of six additional poles by Crown constitutes evidence of dissimilar treatment by the BLM, the Court again disagrees. The record does not contain any suggestion that the BLM ever consented to the construction of these poles. Further, the BLM's decision not to require Crown to remove the poles is consistent with its mandate under the FLPMA to preserve the character of Sunrise Mountain for preservation as wilderness and to not allow any activity that would create surface disturbance. Once the poles were constructed (without the BLM's permission), the BLM may have rationally concluded that allowing the poles to remain on the land was less intrusive than requiring their removal. However, the Court need not decide the appropriateness or not of the BLM's response to this unauthorized construction by Crown. The Court simply notes that the BLM did not give permission to Crown to construct these poles. Thus, this sequence of events is quite distinct from the BLM's decision to deny Autotel's proposal for a new right of way to build an entirely new tower. The Court therefore determines that this activity does not amount to dissimilar treatment of similarly situated applicants.
Third, Autotel cites an instance in September 2001 in which the BLM authorized Crown to install new radio cabinets in its existing building, install six new panel antennas on its existing monopole, and perform necessary electrical service. SAR 1021. This activity consists of routine maintenance and upgrades to existing facilities—actions permitted under the Policy for existing right of way holders—and does not appear to have created new surface disturbance. The Court thus concludes that this activity is not similar to Autotel's proposed construction.
Finally, Autotel argues that the BLM treated Metro differently when it permitted Metro to build a new tower in 2008. The SAR indicates that Metro's original 70-foot tower collapsed on May 28, 2008. SAR 60. On May 30, 2008, the BLM gave Metro permission to remove the damaged tower and antennas "and replace [them] with same size tower within the same footprint as consistent with existing authorization." SAR 63. The Court finds that this authorization is not evidence of dissimilar treatment by the BLM. Metro, an existing right of way holder, was given permission to replace a tower that already existed on Sunrise Mountain and had collapsed. The BLM's action is consistent with the Policy, which states that holders of existing rights of way may perform "necessary and routine maintenance" to keep their facilities "in a safe and reliable condition." AR 31. Although Autotel argues that Metro was actually permitted to construct a new tower with a wider base in place of the old tower, the Court has not found any evidence in the SAR—and Autotel was not able to identify any evidence at oral argument—that such a tower was in fact constructed. However, even if a tower with a wider base was constructed, the Court finds that this decision could nonetheless be a rational application of the Policy if it did not violate the nonimpairment criteria and was necessary to keep the facility in a safe and reliable condition.
In sum, Autotel has not identified any instance in which a similarly situated applicant was treated differently from it without a relevant distinction. The activities and construction proposed by Metro and Crown and authorized by the BLM were not similar to the construction proposed by Autotel because they were either for purposes of maintenance and safety or did not involve surface disturbance. The only new construction that resulted in an expansion of facilities was done by Crown in 2001, which appears to have been done without the BLM's permission. And in the remaining instances in the SAR in which Metro, Frontier, or Crown applied to expand their new facilities, the BLM rejected these proposals and explained that the proposed construction would violate the nonimpairment criteria of the Policy.
Turning to Autotel's application, the Court concludes that the BLM's decision was not arbitrary or capricious. In its 2007 decision, the BLM found that Autotel's proposed tower would violate the nonimpairment criteria because it was not temporary, it could not be easily and immediately removed upon designation of Sunrise Mountain as wilderness, and it would create surface disturbance. The Court agrees with the IBLA that the BLM erroneously interpreted the term "temporary" and that Autotel's proposed facility was likely temporary within the meaning of the Policy because Autotel intended for it to remain only until the land was designated as wilderness. Nevertheless, the record shows that the BLM had a rational basis for denying Autotel's application based on its findings that the facility would not be easily and immediately terminated and that it would create surface disturbance.
The BLM analyzed Autotel's proposal under the nonimpairment criteria applicable to new rights of way and found that removal of the planned facility would require the use of helicopters and motorized equipment. This finding was supported in the record by a rational basis, as Autotel's application specifically stated that its facility would be removed using the same means by which it was constructed (i.e., with the aid of a helicopter and four-wheel-drive vehicles). The BLM further found that the facility would necessitate reclamation because the acts of leveling the site and setting a concrete pad would likely disrupt the soil and require the removal of vegetation. Although Autotel argues that it proposed to build its facility in a previously excavated area, it is not the Court's role to second-guess the agency's judgment where it engaged in reasoned decisionmaking. The BLM's Policy, the validity of which Autotel does not dispute, defines surface disturbance as "any new disruption to soil or vegetation." AR 25 (emphasis added). The BLM therefore had a rational basis for its finding that Autotel's facility would violate the requirement that new rights of way not create surface disturbance. Therefore, the Court finds that the BLM considered the relevant factors and stated a rational basis for its conclusions, and its decision was not arbitrary or capricious....
For the reasons stated above,