Summary: SECOND AMENDED JUDGMENT HOWARD D. McKIBBEN , District Judge . Pursuant to this court's decision of December 3, 2003 as clarified by this court's order of February 4, 2005 (Docket #465), and this court's orders of October 6, 2011 (Docket #749), January 29, 2014 (Docket #831), May 11, 2015 (Docket #853), and January 25, 2016 (Docket #886), judgment is hereby entered in favor of the United States and the Pyramid Lake Paiute Tribe of Indians and against the Truckee-Carson Irrigation District f
More

SECOND AMENDED JUDGMENT

Pursuant to this court's decision of December 3, 2003 as clarified by this court's order of February 4, 2005 (Docket #465), and this court's orders of October 6, 2011 (Docket #749), January 29, 2014 (Docket #831), May 11, 2015 (Docket #853), and January 25, 2016 (Docket #886), judgment is hereby entered in favor of the United States and the Pyramid Lake Paiute Tribe of Indians and against the Truckee-Carson Irrigation District for excess diversions and spills in the amount of 335,908 acre-feet. All individual water right owners as class defendants are bound by this judgment but shall have no independent individual liability under the judgment. This judgment imposes no individual liability against the Board of Directors of the Truckee-Carson Irrigation District or the State of Nevada through its Department of Conservation and Natural Resources, Division of Wildlife and Division of State Lands.

The excess diversion of 335,908 acre-feet shall be repaid in full by the Truckee-Carson Irrigation District within twenty (20) years of the date of this judgment. Repayment shall be in equal annual amounts, payable each year no later than October 31 unless for good cause shown and after notification and a hearing the court defers all or part of any annual repayment until the following year or years.

Repayment shall be made by the Truckee-Carson Irrigation District through reductions of diversions to the Newlands Project from the Truckee River or through water savings or reductions in demand generated by existing and proposed acquisition programs. The Federal Water Master shall have the responsibility to certify to the court each year that the Truckee-Carson Irrigation District is in compliance with this amended judgment. Such certification shall be made only after the Federal Water Master has conferred with the designated representatives of the Secretary of the Interior, the Pyramid Lake Paiute Tribe of Indians and the Truckee-Carson Irrigation District. The court and the Federal Water Master shall be advised of the names of such representatives within sixty days of the date of this amended judgment.

All of the parties shall bear their own costs and fees.

IT IS SO ORDERED.