SPATT, District Judge.
This is a consolidated proceeding involving two actions arising from the decision by the Defendant United States Army Corps of Engineers (the "Corps") to build a reinforced sand dune on the beach in Montauk, New York with the stated purpose of "addressing the immediate need to reduce risk to life and property that resulted from Hurricane Sandy" (the "Project"). The Project was scheduled to commence on October 1, 2015 and to conclude in February 2016.
In the first action bearing docket number, 15-cv-2349 (the "Removal Action"), the Plaintiffs Defend H20, Kevin McAllister ("McAllister"), Michael Bottini ("Bottini"), Rav Freidel ("Friedel"), Jay Levine ("Levine"), Thomas Muse ("Muse"), Conrad Costanzo ("Costanzo"), Daniel Lester, Paul Lester, and Nat Miller ("Miller") (collectively, the "Plaintiffs") seek to nullify the
In the second action bearing docket number, 15-cv-5735 (the "Federal Action"), the Plaintiffs also seek to nullify the decision to approve the Project under the Federal Administrative Procedure Action, 5 U.S.C. §§ 701-06 (the "APA").
On October 1, 2015, the day that construction on the Project was scheduled to commence, the Plaintiffs filed a motion for a temporary restraining order ("TRO") pursuant to Federal Rule of Civil Procedure ("Fed. R. Civ. P.") 65 to halt construction on the Project until February 15, 2016. By order to show cause, the Plaintiffs also filed a request for a preliminary injunction, also pursuant to Fed. R. Civ. P. 65, seeking essentially the same relief as the TRO.
On October 1, 2015, the Court held a hearing during which it denied the Plaintiffs' request for a TRO and requested further briefing as to whether a preliminary injunction should issue.
On October 2, 2015, the Court referred the matter to United States Magistrate Judge Anne Y. Shields to hold a hearing, if necessary, and for a recommendation as to whether the Court should grant the Plaintiffs' motion for a preliminary injunction.
On October 15, 2015, Judge Shields issued a report and recommendation ("R&R") finding that an evidentiary hearing was not necessary and recommending that the Court deny the Plaintiffs' motion for a preliminary injunction.
Presently before the Court are the Plaintiffs' objections to the R&R.
The Court notes that it has received a number of calls and letters from purported residents of Montauk expressing their opposition to the Project. While the Project has given rise to strong sentiment among some members of the Montauk community, the Court must decide the Plaintiffs' present motion for a preliminary injunction according to the evidence presented by the represented parties in this action. Based on that evidence, the Court finds that the Plaintiffs are not entitled to a preliminary injunction. Therefore, for the reasons set forth below, the Court overrules the Plaintiffs' objections and adopts the well-reasoned R&R issued by Judge Shields in its entirety.
Familiarity with the R&R is presumed. However, the Court finds it necessary to provide a brief overview of the statutory and regulatory framework governing federal activity in coastal zones, such as Montauk, as well as the process followed by the Corps prior to starting construction on the Project.
The "unincorporated hamlet of Montauk... is a major tourist destination with many hotels, restaurants and shops in the downtown area." (Cortes Decl., 15-cv-2349 Dkt. No. 58-2, at 5.). Historically, the "downtown area of the hamlet of Montauk is vulnerable to nor' easters and hurricanes which produce storm surges and waves that historically have caused erosion to the beach and dunes in the ... [a]rea." (Id. at 10.)
To address this problem, on July 14, 1960, as part of Section 101 of the Rivers and Harbors Act, P.L. 86-645, Congress authorized, the Corps to undertake certain coastal storm risk management projects, including the "Fire Island Inlet to Montauk Point, New York, Combined Beach Erosion Control and Hurricane Protection Project" ("FIMP Project"). (Vargas Decl., 15-cv-2349 Dkt. No. 58-8, at ¶ 3.)
On October 29, 2012, Hurricane Sandy hit New York, causing "severe coastal erosion in the shoreline of downtown Montauk" and damage to commercial buildings in downtown Montauk. (
Subsequently, the Corps determined that in addition to the long-term FIMP Reformulation Study, short-term measures were necessary to address the immediate threat posed by future hurricanes to the coastline area from the Fire Island Inlet to Montauk Point. (
One of the short-term projects proposed by the Corps was the construction of a 3,100 foot "reinforced dune," which was to extend "from South Emery Street to Atlantic Terrace motel in downtown Montauk and tapering into existing high dunes at both ends of the project area." (
The Corps planned to construct the dune using "14,175 Geotextile Sand Containers ("GSCs") with filled dimensions of about 5.5 ft long, 3.5 ft wide, and 1.5 ft tall, each weighing 1.7 tons." (
The Court will now discuss the various statutory and regulatory approvals that the Corps was required to comply with according to federal and state law prior to commencing construction on the Project.
In 1972, Congress passed the Coastal Zone Management Act, 16 U.S.C. § 1452 ("CZMA"), to "encourage and assist the states to ... develop[ ] and implement[ ]... management programs to achieve wise use of the land and water resources of the coastal zone."
To achieve this goal, Congress developed "a system of grants and other incentives" to encourage states to develop coastal management programs ("CMP's").
Relevant here, once the Secretary of Commerce approves a state's CMP, the
An agency ensures the consistency of its proposed actions with state approved CMPs by submitting a "consistency determination to the relevant State agency ... no ... later that 90 days before final approval of the Federal activity, unless both the Federal Agency and the State agency agree to a different schedule." 16 U.S.C.A. § 1456(c)(1)(C).
Federal regulation, in turn, defines the term, "consistent to the maximum extent practicable," as "fully consistent with the enforceable policies of management programs unless full consistency is prohibited by existing law applicable to the Federal agency." 15 C.F.R. § 930.32. In that regard:
In addition, a federal agency "may deviate from full consistency with an approved management program when such deviation is justified because of an emergency or other similar unforeseen circumstance (`exigent circumstance'), which presents the Federal agency with a substantial obstacle that prevents complete adherence to the approved program."
However, "[o]nce the exigent circumstances have passed, and if the Federal agency is still carrying out an activity with coastal effects, Federal agencies shall ... ensure that the activity is consistent to the maximum extent practicable with the enforceable policies of management programs."
Once a federal agency has issued its consistency determination, the relevant state agency may concur or object to it.
If the state objects to the federal agency's consistency determination, the federal agency can still proceed with the challenged activity so long as "the Federal agency has concluded that its proposed action is fully consistent with the enforceable policies of the management program" and notifies the state agency in writing before it commences with the project.
In 1981, the New York State Legislature enacted the Waterfront Revitalization of Coastal Areas and Inland Waterways Act, N.Y. Exec. Law § 910, et seq. (the "NYS Coastal and Waterways Act"), which authorized the New York Department of State ("DOS") to establish a CMP pursuant to the CZMA.
On August 13, 1982, the DOS submitted a proposed CMP to the U.S. Department of Commerce for approval.
The New York CMP contains a list of forty-four policy statements intended to "promote[ ] the beneficial use of coastal resources, prevent[ ] their impairment, [and] deal[ ] with major activities that substantially affect numerous resources."
In addition, the NYS Coastal and Waterways Act also encourages local governments to participate in the State's coastal management efforts by submitting local waterfront revitalization programs ("LWRPs") to the Secretary of the DOS for approval.
On December 3, 1999, the Town of East Hampton approved an LWRP covering a coastal area in the Town, which includes an area "along Town's Peconic Estuary shore to Montauk Point."
Thus, it is undisputed that any federal activity in the coastal area along the Montauk shore is required under the CZMA to be undertaken "in a manner which is consistent to the maximum extent practicable" with the East Hampton LWRP. 16 U.S.C. § 1456(c)(1)(A).
In 1970, Congress enacted the National Environmental Policy Act, 42 U.S.C. § 4321 ("NEPA") to "promote efforts which will prevent or eliminate damage to the environment and biosphere and stimulate the health and welfare of man[.]" 42 U.S.C.A. § 4321. To achieve this goal, NEPA requires federal agencies to prepare an environmental impact statement ("EIS") for any major federal action "significantly affecting the quality of the human environment." 42 U.S.C. § 4332(C). The EIS must address:
In addition, the NEPA created the Council on Environmental Quality ("CEQ") to promulgate regulations that supplement the statutory requirements of NEPA.
An EA is a shorter and more concise document than an EIS. The CEQ regulations define an EA as a "concise public document" that "[b]riefly provide[s] sufficient evidence and analysis for determining whether to prepare an environmental impact statement or a finding of no significant impact." 40 C.F.R. § 1508.9.
If an agency determines that an EIS is not required, it must also issue a "finding of no impact" statement ("FONSI"), which "briefly present[s] the reasons why an action... will not have a significant effect on the human environment and for which an environmental impact statement therefore will not be prepared."
On August 11, 2014, Peter Weppler ("Weppler"), Chief of the Environmental Section of the Corps, sent a letter to Jeffrey Zappieri ("Zappieri"), an official at the DOS, stating that the Corps had determined that construction of the Project was consistent with the East Hampton LWRP and the New York CMP. Weppler attached to the letter two separate documents which set forth what the Corps determined were the applicable policies in the LWRP and the New York CMP, and explained how the Project met or advanced those policies. (Cortes Decl., 15-cv-2349, Dkt. No. 25-3.)
On August 26, 2014, the Corps released a draft EA and FONSI statement and made them available for public comment for a period of thirty days. (Cortes Reply Decl., 15-cv-2349, Dkt. No. 41, at ¶¶ 3-4.) The Draft EA noted that prior to Hurricane Sandy, the Corps, as part of the FIMP Reformulation Study, undertook an initial screening of projects intended to address erosion along Montauk Beach. (
However, after Hurricane Sandy, the Corps revisited its plan to "determine if the eroded beach condition and updated costs and benefits warranted selection of a larger alternative plan." (
In addition to studying the long-term benefits of these five alternatives, the Corps also considered whether any of these plans could address the short-term need to repair damage caused by Hurricane Sandy. (
(
In addition to the five alternatives discussed above, the Corps also considered a "No Action Alternative," under which, the Corps and the Federal Government "would take no action to reduce storm damages in the study area," and instead rely on local governments and non-governmental groups to "take actions to protect themselves by undertaking their own construction projects to build up the beach and dune profiles." (
On August 26, 2014, the Corps also released a draft FONSI statement on its website for public comment which concluded that the Project did not constitute "a major federal action significantly affecting the quality of the human environment" and therefore, did not require the preparation of a detailed EIS under NEPA § 102(2)(C). (Cortes Decl., 15-cv-2349, Dkt. No. 41-5, at 3.)
During the thirty-day public comment period, the Corps received comments on its draft EA and FONSI statement from: (i) the Historic Preservation Technician; (ii) Yogi Harper, President of Erosion Control Specialists of North Carolina, Inc.; (iii) several former environmental planners and longtime residents of East Hampton; (iv) the Concerned Citizens of Montauk; and (v) the United States Environmental Protection Agency ("EPA"). (Cortes Decl., 15-cv-2349, Dkt. No. 41-5.) Notably, it is undisputed that the Plaintiffs did not submit written comments.
In October 2014, the Corps finalized the EA, and on November 12, 2014, it finalized the FONSI statement. (Cortes Decl., 15-cv-2349, Dkt. No. 41, at ¶¶ 4-5.) On December 8, 2014, the Corps released both documents on its website.
In the finalized drafts, the Corps made revisions to the EA and FONSI statement based on some of the comments it received on the drafts. (
In response, the final draft EA explains in more detail why the "No Action Alternative" was not a viable option:
(Cortes Decl., 15-cv-2349, Dkt. No. 41-6, at 8.)
In addition, the Corps added a more thorough discussion of what might result if the GSCs deteriorate and the steps the Corps plans to take to "avoid and/or minimize some of the project's impacts to fish and wildlife resources," including:
(
In an October 24, 2014 letter to Weppler, Matthew Millea ("Millea"), the New York Deputy Secretary of State, indicated that the DOS concurred with the Corps' determination that the Project is consistent with the New York CMP and the East Hampton LWRP. (Am. Compl., Dkt. No. 5, Ex. 2.)
On November 3, 2014, Brian Frank ("Frank"), Chief Environmental Analyst for the Town of East Hampton ("East Hampton"), sent a letter to Weppler indicating that the Town also concluded that the Project does not conflict with the East Hampton LWRP. (
In March 2015, the Corps entered into an agreement with H&L Contracting LLC ("H&L Contracting") to construct the Project. (Verga Decl., 15-cv-2349, Dkt. No. 58-8, at ¶ 11.) Under the agreement, H&L Contracting received a total of $8.4 million, of which $600,000 was devoted to costs related to "mobilization" and "de-mobilization." (
According to the Corps, "[m]obilization is the process by which H&L would set up their equipment, machinery, office trailers and everything else needed to commence construction." (Meranda Decl., 15-cv-2349, Dkt. No. 58-9, at ¶ 5.) De-mobilization is "the process by which H&L would remove all of their equipment." (
In order to minimize disruption to the beach season, the Corps and H&L planned to commence mobilization for the project on October 1, 2015 and to begin construction on October 13, 2015. (Verga Decl., 15-cv-2349, Dkt. No. 58-8, at ¶ 12.) The Project was scheduled to be completed by the end of February 2016 before the start of the 2016 beach season. (
On March 19, 2015, the Plaintiffs Defend H20, McAllister, Bottini, Freidel, Levine, and Muse (collectively, the "Original Plaintiffs") commenced the Removal Action in the Supreme Court of the State of New York, Suffolk County seeking a judgment pursuant to Articles 30 and 78 of the CPLR nullifying the decision to approve the Project by the Respondents East Hampton, the County of Suffolk (the "County"), the New York State Department of Environmental Conservation ("DEC"), and the Corps (collectively, the "Removed Defendants").
On April 29, 2015, the Plaintiff filed an amended complaint in the Removed Action, which added Costanzo, Daniel Lester, Paul Lester, and Miller (together with the "Original Plaintiffs," the "Plaintiffs").
The amended complaint describes the Plaintiff Defend H20 as a non-profit organization whose membership consists of individuals who "live, work, or recreate near or at the [P]roject site." (Am. Compl., 15-cv-2349, Dkt. No. 5, at ¶ 12.) The eight individual Plaintiffs are members of H20 who live in the Montauk area. (
On May 23, 2015, the Court so-ordered a stipulation permitting Royal Atlantic Corporation, Royal Atlantic East Condominium Owners Association, Inc., and Montauk Beach Preservation Association, Inc. (collectively, the "Intervenors") to intervene as Defendants in the Removed Action. The Intervenors represent three groups comprised of 110 cooperative unit owners and 5 hotel and motel owners who own a combined "2,900 lineal feet of oceanfront property directly affected by the [Project]." (Intervenors' Answer, 15-cv-2349, Dkt. No. 15, at ¶ 1.)
On June 1, 2015, the Intervenors filed an answer to the amended complaint and a purported counterclaim against the Plaintiffs seeking a judgment dismissing the amended complaint and holding the Plaintiffs "personally liable for any damages that occur, both physical and monetary as a result of loss of income should the planned [P]roject not proceed." (
From June 23, 2015 to July 23, 2015, the Removed Defendants filed four separate motions pursuant to Fed. R. Civ. P. 12 to dismiss the amended complaint.
As noted, on October 1, 2015, the day that the Corps and H&L were scheduled to begin mobilizing construction equipment, the Plaintiffs filed a motion for a TRO pursuant to Fed. R. Civ. P. 65 to prevent construction on the Project from commencing until February 15, 2015. By order to show cause, the Plaintiffs also filed a request for a preliminary injunction pursuant to Fed. R. Civ. P. 65 seeking essentially the same relief as the TRO.
On October 1, 2015, the Court held a hearing during which it denied the Plaintiffs' request for a TRO and requested further briefing as to whether a preliminary injunction should issue.
On October 2, 2015, the Court referred the matter to United States Magistrate Judge Anne Y. Shields to hold a hearing, if necessary, and for a recommendation as to whether the Court should grant the Plaintiffs' motion for a preliminary injunction.
On October 2, 2015, the Plaintiffs Defend H20, Costanzo, Daniel and Paul Lester, and Miller commenced the Federal Action against the Removed Defendants, as well as Col. David Caldwell, in his official capacity as Commander of the New York District of the Corps, and Commissioner Marc Gerstman, in his official capacity as Commissioner of the DEC (together with the Removed Defendants, the "Defendants").
On October 5, 2015, the Plaintiffs in the Federal Action filed an amended complaint incorporating the same facts alleged in the amended complaint filed in the Removed Action. However, they added new claims pursuant to the Federal Administrative Procedure Act, 5 U.S.C. § 701-06 (the "APA"). (
Based on these representations, Judge Shields proposed, and the parties agreed to stipulate to the following:
(
On October 13, 2015, in compliance with the above-Order, the Corps submitted a letter to the Court supplementing its opposition to the Plaintiffs' motion and addressing the Plaintiffs' newly asserted federal APA claims. (Corps' Oct. 13, 2015 Ltr., 15-cv-5735, Dkt. No. 13.)
On October 15, 2015, Judge Shields issued a report and recommendation recommending that the Court (i) direct the Clerk of the Court to close the Removed Action under docket number 15-cv-2349, and terminate, without prejudice, the pending motions to dismiss under docket numbers 19, 21, 25, 26, and 29; (ii) deny the Plaintiffs' motion for a preliminary injunction under docket number 54 in the Removed Action; and (iii) deny the Plaintiffs' request for an evidentiary hearing. (October 15, 2015 Report & Recommendation, 15-cv-2349, Dkt. No. 72 ("R&R"), at 34.)
Judge Shields recommended that the Plaintiffs' motion for preliminary injunction be denied based on the following findings: (i) the doctrine of laches barred the Plaintiff from seeking preliminary relief,
In reviewing a Report and Recommendation, the district court "may accept, reject, or modify, in whole or in part, the findings or recommendations made by the magistrate judge." 28 U.S.C. § 636(b)(1)(C).
The district court "shall make a de novo determination of those portions of the report or specified proposed findings or recommendations to which objection is made." 28 U.S.C. § 636(b)(1). However, "[t]he district court is `permitted to adopt those sections of a magistrate judge's report to which no specific objection is made, so long as those sections are not facially erroneous.'"
A plaintiff seeking a preliminary injunction pursuant to Fed. R. Civ. P. 65 must establish that: (i) "he is likely to succeed on the merits"; (ii) "he is likely to suffer irreparable harm in the absence of preliminary relief"; (iii) "the balance of equities tips in his favor"; and (iv) "an injunction is in the public interest."
As to the first factor, the Second Circuit has adopted a somewhat more flexible standard than "likely to succeed on the merits" — namely, that a party seeking a preliminary injunction must show "(1) likelihood of success on the merits or (2) sufficiently serious questions going to the merits to make them a fair ground for litigation and a balance of hardships tipping decidedly toward the party requesting the preliminary relief."
However, as Judge Shields correctly noted, the Second Circuit has held that the less rigorous "fair ground for litigation" standard is not available where, as here, "the moving party seeks to stay government
Thus, in order to obtain a preliminary injunction, the Plaintiffs must show that they are likely to succeed on the merits of their claims, in addition to the other three elements of the preliminary injunction standard.
As an initial matter, the Court notes that at the October 7, 2015 conference, Judge Shields proposed, and the parties agreed to: (i) close the Removed Action, 15-cv-2349; (ii) terminate without prejudice the Defendants' motions to dismiss pending in the Removal Action; and (iii) stay the time in which the Defendants were required to file an answer or otherwise move in the Federal Action until thirty days after service was made, or thirty days after a decision on the motion for preliminary injunction, whichever is later. (
The reason that Judge Shields proposed this stipulation was to avoid the unnecessary cost and delay that would likely result from proceeding with both the Federal Action and the Removal Actions when the Federal Action alleges APA claims based on the exact same set facts that the Plaintiffs allege in the Removal Action.
In light of the parties' stipulation and in the interest of efficiency, the Court finds no clear error in the recommendation by Judge Shields to close the Removal Action and terminate the pending motions to dismiss without prejudice and with leave to refile in the Federal Action. Accordingly, the Court adopts this recommendation in its entirety.
The Court further notes that the termination of the Removal action will also result in the dismissal without prejudice of the counterclaim filed by the Intervenors against the Plaintiffs. (
Judge Shields also found that no evidentiary hearing was necessary because the Plaintiffs failed to raise a dispute of fact as to any of the four elements of the preliminary injunction standard. (
"On a motion for preliminary injunction, where `essential facts are in dispute, there must be a hearing ... and appropriate findings of fact must be made.'"
However, "[i]t is not a rigid requirement that oral testimony be taken on a motion for a preliminary injunction."
Here, the Plaintiffs' motion for a preliminary injunction is premised on their claims that the Corps violated the APA in determining that (i) the Project was "consistent to the maximum extent practicable" with the East Hampton LWRP and (ii) issuing a FONSI statement under NEPA in which it concluded that the construction of the Project would result in no significant adverse environmental impacts. (
On the other hand, the Corps offered documentary evidence, including, drafts and final versions of the EA and FONSI statements; copies of the public comments to those documents; and the determinations by the Corps, the DEC, and East Hampton that the Project was consistent with the East Hampton LWRP. As is explained in detail below, the Court finds that these documents clearly show that the Corps followed the required procedures under the CZMA and NEPA. (
In addition, the Corps offered the declarations of (i) Frank Verga ("Verga"), a Project Manager at the Corps responsible for the Project; (ii) Kevin Merenda ("Merenda"), a Resident Engineer at the Corps who also works on the Project; and (iii) Susan D. McCormick, P.E., ("McCormick"), the Chief of the Coastal Erosion Management Program for the DEC. (
Judge Shields concluded that the Corps' determination that the Project was consistent with the East Hampton LWRP and did not result in significant impacts to the environment. As explained below, the Court finds this conclusion to be well-supported by the undisputed documentary evidence in the record. Thus, the Court agrees with the conclusion by Judge Shields that the Plaintiffs' allegations, supported only by the McAllister affidavit, were not sufficient to create a dispute of fact as to any of the elements of the preliminary injunction standard, and thus did not merit a separate evidentiary hearing.
In their objections, the Plaintiffs attempt to create an issue of fact by offering additional evidence in the form of (i) an unsworn letter by Steven Resler ("Resler"), a Coastal Resource Specialist at the DOS and purported expert in "coastal management"; and (ii) what the Plaintiffs call "pre-filed" testimony by Resler from a 1995 case, which the Plaintiffs contend is "factually similar" to the instant case. (
As is explained more fully below, the Court finds this additional evidence to be improper and not persuasive when viewed
Accordingly, the Court, upon a de novo review of the evidence, finds the decision by Judge Shields to deny an evidentiary hearing to be entirely correct, and adopts her recommendation on that issue.
The Plaintiffs object to Judge Shields' finding that laches bars their claim for preliminary relief.
"Laches is an equitable defense which bars injunctive relief where a plaintiff unreasonably delays in commencing an action."
In cases where a plaintiff alleges that a defendant failed to comply with NEPA, courts have stated that "laches is a doctrine of equity that is only rarely invoked in environmental cases, on account of the strong public interest in effecting compliance with NEPA."
In such cases, "[t]he Second Circuit test is whether the plaintiff's delay in bringing the suit has resulted in construction proceeding `to a point where any significant environmental damage has already been done' and whether, in the alternative, `construction may have gone so far that for economic reasons it would be impracticable or impossible to alter much of the basic plan.'"
For example in
By contrast, in
Similarly in
On April 24, 2015, the Corps filed a letter with the Court on ECF clearly representing, "The construction work on the Beach Stabilization Project is not scheduled to commence until the Fall of 2015." (Apr. 24, 2015 Ltr., Dkt. No. 2.) Further, on August 24, 2015, the Plaintiffs filed a motion pursuant to Fed. R. Civ. P. 15 for leave to amend the Removal Action complaint for a second time. (
Judge Shields' finding as to the second element of laches — namely, the plaintiff inexcusably delayed in taking action — is also well-supported by the record. There is no question that the Plaintiffs' sat on their rights for at least five months and waited until October 1, 2015, the day that construction on the Project was scheduled to commence, to make a motion for preliminary injunction.
In that regard, the Court finds significant the undisputed fact that the Plaintiffs failed to make their objections to the Project known to the Corps by participating in the administrative approval process in September 2014, when the Corps released the draft EA and FONSI for public review. Had they done so, it is possible that the Corps could have addressed some of the Plaintiffs' objections prior to undertaking the extensive preparation efforts described below. Instead, the Plaintiffs did not participate in the public comment period or try to resolve their objections without litigation; waited six months to initiate suit against the Corps; and then waited another five months to request preliminary relief. These undisputed facts weigh heavily in favor a finding of laches.
The Plaintiffs made various assertions before Judge Shields to excuse their delay. They asserted, without providing any evidence, that "the first time [the] Plaintiffs received the Corps' Consistency Statement using the LWRP policies was on July 23, 2015." (
They also attempted to excuse their delay by making unsupported statements in their legal memorandum that the Defendants failed to properly respond to their apparent November 24, 2014 requests under the Freedom of Information Law ("FOIL") for information related to the Project. (
In their objections, the Plaintiffs also attempt to excuse their delay because they assert that "[t]his is a complicated matter involving four distinct government agencies, at four different levels of government... [and] has required significant litigation to fend off Motions to Dismiss from each of the four agencies." (The Pls.' Objections, Dkt. No. 75, at 18-19.)
The Plaintiffs cite to no legal authority holding that a litigant can be absolved from the consequences of a significant delay in requesting preliminary relief because the matter is "complicated," and the Court declines to adopt such an argument. Almost every litigation involves complicated questions. Were the Court to recognize the supposed complicated nature of a case as an excuse for a plaintiff to make an eleventh hour request for preliminary relief, it would render laches inapplicable in almost every case and severely prejudice defendants who may have already taken costly actions to proceed with the challenged activity during the period of the plaintiff's delay. Thus, the Court finds the excuse offered by Plaintiffs to be unpersuasive.
Finally, the Plaintiffs assert that their delay should be excused because they "were still trying to resolve this at the administrative level in later September, through the County Legislature." (The Pls.' Objections, Dkt. No. 75, at 18-19.) Again, the Court declines to find this unsupported and vague allegation to be a valid excuse for the Plaintiffs' delay.
Accordingly, the Court concludes, upon a de novo review, that Judge Shields' finding that the Plaintiffs satisfied the first two elements of laches — namely, that they knew of the defendant's misconduct and inexcusably delayed in taking action — to be well-supported by the record in this case.
The Plaintiffs do not object to the finding by Judge Shields that the Defendants were prejudiced by the Plaintiffs' delay and therefore, satisfied the third element of the Laches defense. Thus, the Corps contends that the Plaintiffs waived any objections to this finding. (
The Court need not decide the question of waiver as it finds that even under de novo review, Judge Shields' finding of prejudice was clearly supported by the record. Specifically, the Defendants offer a declaration by Meranda, who, as noted above is the Resident Engineer and Administrative Contracting Officer for the Project, in which he stated that H&L Contracting has already mobilized its equipment and begun construction on the Project.
Therefore, any attempt to stop construction at this point would potentially waste the more than $600,000 the Corps has already spent to date on the Project. (
Based on this undisputed evidence, the Court finds that construction on the Project has gone far enough that for economic reasons, it would be impractical and wasteful to delay it any further by granting the Plaintiffs' request.
In sum, the Court concludes that (i) the Plaintiffs were aware as early as April 2015 that construction on the Project was scheduled to commence in October 2015 and waited until October 1, 2015 to make their motion for a preliminary injunction to stop construction; (ii) the Plaintiffs offered no legitimate excuse for their delay; and (iii) the Corps was unduly prejudiced by the Plaintiffs' delay because by the time the Plaintiffs moved for preliminary relief, the Corps had entered into an agreement with a contractor; the contractor had mobilized their construction equipment on the beach; and the Corps has paid the contractor more than $600,000 which is not refundable. Therefore, the Court adopts Judge Shields' recommendation and finds that the Plaintiffs' motion for a preliminary injunction is barred by laches.
As noted earlier, in deciding a motion for a preliminary injunction, "the court must consider whether the plaintiff will suffer irreparable harm in the absence of a preliminary injunction, and the court must assess the balance of hardships between the plaintiff and defendant."
"A showing of irreparable harm is `the single most important prerequisite for the issuance of a preliminary injunction.'"
Before Judge Shields, the Plaintiffs asserted that construction of the Project would cause them irreparable harm because its construction would "render[] the entire beach of downtown Montauk unusable and unenjoyable" and cause "permanent and irreversible" effects to the environment. (The Pls.' Mem. of Law, 15-cv-2349, Dkt. No. 54, at 17-18.)
The only evidence that the Plaintiffs offered in support of this assertion was a declaration filed by McAllister, whose qualifications include a Master's of Science Degree in Coastal Zone Management and having participated in drafting the East Hampton LWRP. (McAllister Decl., 15-cv-2349, Dkt. No. 54-3, at ¶¶ 1-5.) In his declaration, McAllister states that the construction of the Project will, among other things, harm: (i) "environmental interests because it will disrupt natural processes that are most effective in preventing erosion and flooding"; (ii) "aesthetic interests" by "[r]eplacing the beach and dune system with 14,000 geobags"; (iii) "ecological interests" by eliminating "nearshore habitat essential to some avian and aquatic species"; and (iv) "economic interests" by causing property values to decrease near the Project and affecting individuals whose occupations rely on the beach area adjacent to the Project. (
Judge Shields found the opinions offered by McAllister were insufficient to demonstrate irreparable harm because the Plaintiffs failed to show that McAllister was qualified to give an opinion as to either coastal management or economic harm. (R&R at 32-33.) Further, she found that even if McAllister was qualified to render an opinion as to the economic and environmental effects of the Project on Montauk beach, his opinion did nothing more than express disagreement with the well-supported opinion offered by the Corps. (
In addition, Judge Shields found that the Plaintiffs' five month delay in seeking preliminary relief weighed heavily against a finding of irreparable harm. (
Although not entirely clear from the Plaintiffs' brief, it appears that they object to Judge Shields' finding that the Plaintiffs did not establish irreparable harm because they assert that her conclusion "misses the broader negative socioeconomic effects of replacing Montauk's premier attraction white sand beaches, in its downtown area, with 14,000 geo-bags." (The Pls.' Objections at 18.) The Plaintiff further asserts that Judge Shields erred in rejecting the Plaintiffs' claim that the Project would render the beach unusable. (
The Plaintiffs' objections largely reiterate the arguments made to, and rejected by, Judge Shields. Thus, the Court reviews for clear error the determination by Judge Shields that the Plaintiffs failed to show irreparable harm and that the balance of equities weighs heavily in favor of a preliminary injunction.
After reviewing the record, the Court finds that there was no clear error, and Judge Shields' conclusions were entirely correct.
First, Judge Shields correctly attached only slight weight to the declaration filed by McCallister. McAllister had no personal involvement with the Project and fails to explain how he came to his conclusions or why the fact that he has a Master's in Science qualifies him to make judgments about the economic effects of the Project on the Montauk community.
Second, as Judge Shields noted, even if the Court were to credit the opinion of McAllister, his opinions are contrary to the conclusions reached by the Corps that the Project would have no significant impact on the environment and would not impede the public's access to the beach, which were based on a study in coordination with federal and state agencies as well as public comments. (
Therefore, at most, the opinions offered by McAllister suggest the "mere possibility" of harm to the beach, which falls manifestly short of the standard required for preliminary injunctive relief.
Third, Judge Shields correctly noted that in addition to the complete lack of evidence supporting the Plaintiffs' claim of irreparable harm, the undisputed fact that they waited five months before making a motion for a preliminary injunction also weighs heavily against a finding of irreparable harm. That is because "[p]reliminary injunctions are generally granted under the theory that there is an urgent need for speedy action to protect the plaintiff's rights," and "[d]elay in seeking enforcement of those rights ... tends to indicate at least a reduced need for such drastic, speedy action."
"Where there is a good reason for it," courts have found short delays by plaintiffs in moving for preliminary relief do not bar a finding of irreparable harm.
Here, the Plaintiffs provide no "good reason" for why they waited five months from when they initiated the Removal Action to seek preliminary relief. Indeed, as explained earlier, all the evidence suggests that despite being aware that construction of the Project was scheduled to commence in the Fall of 2015, they waited until the day that construction was to start to make their motion. This fact alone supports the denial of their motion.
Finally, the Court finds no error in Judge Shields' finding that the balance of the equities weighs heavily against granting a preliminary injunction. That is because the Plaintiffs have shown little more than the possibility that the Project would harm the Beach. On the other hand, the Corps has offered undisputed evidence, which, as discussed earlier, shows that the Corps will have to pay H&L Contracting $6,700 per day during any halt of construction, $600,000 to the extent that H&L Contracting is required to remove their equipment from Montauk beach, and an additional $500,000 if they are forced to re-mobilize their equipment after the injunction ends. The possibility that the Corps would have to pay upwards of $1.1 million in costs as a result of the injunction establishes clear and substantial prejudice, which weighs against granting the Plaintiffs' motion.
Further, and perhaps more importantly, the Corps has also offered substantial evidence suggesting that in the wake of Hurricane Sandy, Downtown Montauk is in need of immediate flood control measures. In particular, in the final EA, the Corps concluded, after undertaking an extensive study of the Montauk beach conditions, that the Project "is required to provide adequate protection from severe storms and address the vulnerability of the project area." (The Final Report, Dkt. No. 41-6, at 9-10.) Further, both Verga and McCormick, the Chief of Coastal Erosion Management Program for the DEC, stated that even a short-term delay in the Project is an unacceptable result because "[w]ithout this project, Montauk's residents, businesses, and infrastructure will be more vulnerable and will likely sustain greater damages when the next hurricane or major storm hits Long Island." (McCormick Decl., 15-cv-2349, Dkt. No.58-10 at ¶ 8;
Indeed, the Intervenors, which represent the owners of approximately 2,900 lineal feet of oceanfront property directly affected by the Project and a majority of
When viewing this evidence against the unsupported suppositions of the Plaintiffs and McAllister, the Court finds that Judge Shields was entirely correct in finding that the public interest weighs heavily against even a short-term delay of the Project.
Accordingly, the Court finds no clear error in the conclusion by Judge Shields that the balance of equities weighs heavily against granting a preliminary injunction to halt construction on the Project.
Judge Shields recommended that the Court deny the Plaintiffs' motion for a preliminary for the additional reason that the Plaintiffs failed to establish that their APA and Article 78 claims against the Corps are likely to succeed.
The Court will now address the Plaintiffs' objections with respect to each claim.
Article 78 of the CPLR is a state statute that authorizes proceedings in state court against state or local bodies and officers.
Judge Shields concluded that the Plaintiffs' Article 78 claim against the Corps was not likely to succeed because Congress has not waived its sovereign immunity for the United States or it agencies to be sued under Article 78, and therefore, "Article 78 is the wrong procedural vehicle for obtaining review of a decision of the Federal government or any agency thereof." (R&R at 22.)
The Plaintiffs do not object to this finding. Thus, the Court reviews it for clear error. It is well-established that `"[a]bsent a waiver, sovereign immunity shields the federal Government and its agencies from suit[.]'"
Here, the Plaintiffs point to no legal authority suggesting that Congress has waived sovereign immunity for the United States or its agencies, such as the Corps, with regard to Article 78 claims. Indeed, at least one court in this Circuit has concluded that there has been no such waiver and as a result, dismissed an Article 78 claim against a federal agency.
Courts have also declined to entertain Article 78 claims on supplemental jurisdiction grounds because they have concluded that "an Article 78 proceeding is best brought in the state court," and thus, it is improper for a federal court to entertain such claims.
Therefore, the Court finds no clear error in the determination by Judge Shields that the Plaintiffs' Article 78 claim against the Corps is not likely to succeed based on their failure to establish that the Corps waived its sovereign immunity from such claims or, in the alternative, that supplemental jurisdiction would be appropriate over their claim.
The APA provides that "[a] person suffering legal wrong because of agency action, or adversely affected or aggrieved by agency action within the meaning of a relevant statute, is entitled to judicial review thereof." 5 U.S.C.A. § 702 (West). "Pursuant to the APA, courts review contested agency action to determine if it is `arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.'" 5 U.S.C. § 706(2)(A). The standard of review is narrow and deferential: "a court is not to substitute its judgment for that of the agency."
However, although this standard is "highly deferential," the Second Circuit has stated that it "does not equate to no review."
The Court will review, in turn, the Plaintiffs' objections with respect their APA claims arising from (1) the Corps' August 11, 2014 consistency determination pursuant to the CZMA; and (2) the Corps' issuance of an EA and FONSI statement pursuant to NEPA on December 8, 2014.
As discussed earlier, the CZMA requires that "[e]ach Federal agency activity within
An agency ensures the consistency of its proposed actions with approved state coastal management programs, by submitting a "consistency determination to the relevant State agency ... no ... later that 90 days before final approval of the Federal activity, unless both the Federal Agency and the State agency agree to a different schedule." 16 U.S.C.A. § 1456(c)(1)(C).
Once a federal agency has issued its consistency determination, the relevant state agency may concur or object to it. 15 C.F.R. § 930.41(a).
On August 11, 2014, the Corps issued a consistency determination to the DOS, the state agency responsible for administering the New York State CMP, stating that the Project was consistent with the CMP and the East Hampton LWRP. (Cortes Decl., 15-cv-2349, Dkt. No. 25-3.)
On October 24, 2014 and November 3, 2014, respectively, the DOS and East Hampton issued separate letters concurring with the Corps' consistency determination. (Cortes Decl., 15-cv-2349, Dkt. No. 5, Exs. 2, 6.)
The amended complaint alleges that the Corps' August 11, 2014 consistency determination was "arbitrary and capricious" in violation of the APA because the Project was not consistent to the "maximum extent practicable" with "44 policies of the [East Hampton] LWRP in 29 different ways." (Am. Compl., 15-cv-5735, at ¶ 79.)
Although they nominally reference other policies, the Plaintiffs' APA claim arises principally from the Corps' determination that the Project was consistent with Policy #17, which provides:
(
The Corps found that the Project was consistent with Policies 17 and 17A because:
(
The amended complaint asserts that this determination was arbitrary and capricious in violation of the APA because the 14,000 GSCs that the Corps plans to use to construct the Project are structural, and therefore, violate Policy 17 and 17A of the East Hampton LWRP. (Am. Compl. at ¶ 82.)
In response, the Corps asserts that the Plaintiffs' APA claim fails because (i) DOS and East Hampton concurred with the
In the R&R, Judge Shields agreed with the Corps as to the first argument and did not reach the question of standing. (
In addition, Judge Shields found that even if the Court were to rule that the Plaintiffs' APA claim was not moot, the claim was still unlikely to succeed because the August 11, 2014 Consistency Determination did address the policy in the East Hampton LWRP against using structural measures on the Montauk beach by deciding to use GSCs instead of hard structures. (
The Plaintiffs object to the R&R by asserting that: (i) Judge Shields ignored New York regulations which make clear that the GSCs are structural measures,
As an initial matter, the Court notes that the Second Circuit has suggested, but not decided, that "the only possible private right of action under the Act would be against the federal government through the Administrative Procedure Act."
Based on the Court's own research, other circuit and district courts have recognized APA claims premised on the violation of the consistency provision set forth in the CZMA. However, those courts have done so on a limited basis, particularly in cases where, as here, the relevant state agency has concurred with the consistency determination of the federal agency. For example, in
The Ninth Circuit upheld the decision by the district court dismissing the plaintiffs' CZMA claim, reasoning that "the Alaska Division of Governmental Coordination and the Postal Service agreed that the Project was consistent with the [local coastal management] Plans, and we will not set aside that agreed conclusion without a `compelling reason.'"
By contrast, in
Even if their claim is not moot, the Plaintiffs provide "no compelling reasons" why the Court should overturn the Corps' consistency determination. For example, the Plaintiffs do not provide evidence that the Corps ignored relevant policies of the East Hampton LWRP or rendered its determination based on stale data that did not account for significant changes to the Montauk community, as was the case in
Indeed, quite the opposite appears to be true. The Corps rendered its consistency determination after undertaking an extensive study of the Montauk area utilizing information from the FIMP Reformulation Study, as well as assessing the Pre-Sandy and Post-Sandy conditions on Montauk beach. (Cortes Decl., 15-cv-2349, Dkt. No. 58, Ex. 1, at i.) The Corps also analyzed six different design alternatives based on factors, such as, "general design requirements, costs, and local acceptability." (Cortes Decl., 15-cv-2349, Dkt. No. 41-6, at 8.) Based on its analysis of these alternative, the Corps determined that a reinforced dune using GSCs was the best plan to address the short-term need for a stabilization measure along Montauk beach while the Corps reviewed the viability of measures intended to protect Downtown Montauk from future storms on a long-term basis. It also worked with state and local agencies in developing a plan that was "consistent to the maximum extent practicable" with the East Hampton LWRP and the CMP.
Based on this evidence, there is no question that the Corps' determination that the Project was "consistent to maximum extent practicable" with the East Hampton LWRP was the result of a thorough and reasonable analysis of the relevant factors and different alternatives available.
However, the Plaintiffs assert that the August 11, 2014 consistency determination was "arbitrary and capricious" based primarily on their contention that Corps conclusion that the Project was "non-structural." (The Pls.' Objections, 15-cv-2349, Dkt. No. 75, at 2.) To support this assertion, the Plaintiffs first point to a document, dated August 11, 2014, that they allege was prepared by the DOS containing its comments to the August 11, 2014 consistency determination. With respect to Policy 17 of the East Hampton LWRP, this document states, "DOS has always considered geotextile bags a structural measure, which are not consistent with this policy. Please address." (Am. Compl., 15-cv-2349, Dkt.
The Plaintiffs provide no context or explanation as to who at DOS prepared these August 11, 2014 comments, nor whether DOS ever provided them to the Corps. (
Next, the Plaintiffs offer an unsworn letter, dated October 22, 2015, by Resler, who purports to be a top expert in the coastal management field, to the Plaintiff's counsel, as well as testimony by Resler in an unrelated case from 1995. (
First, as the Corps correctly notes, the Plaintiffs did not offer Resler's October 22, 2015 letter, nor his 1995 testimony, before Judge Shields. Courts in this Circuit have often held that "[a]bsent a most compelling reason, the submission of new evidence in conjunction with objections to the Report and Recommendation should not be permitted."
Second, and more importantly, even if it considered the Resler's October 22, 2015 letter and 1995 testimony, the Court finds those documents do not raise a factual issue as to whether the Corps' consistency determination was "arbitrary and capricious." In that regard, the Court attaches no weight to the Resler's testimony from a 1995 case because the Plaintiffs fail to explain what that case was about, nor why the Court should consider testimony relating to a twenty-year old case involving a different project as relevant to the instant case. (
With respect to the October 22, 2015 letter, Resler offers his opinion that GSCs are structural within the meaning of New York state regulation, and therefore, the Project is "not consistent to the maximum extent possible" with the East Hampton LWRP. (
The Plaintiffs also assert that the Corps' consistency determination was arbitrary and capricious because they contend that the Corps ignored New York state regulations and the East Hampton LWRP that define GSCs as "structural" measures. (The Pls.' Objections 7-8.) Here again, the Court disagrees.
The East Hampton LWRP does not explicitly define the difference between structural and non-structural measures. It merely states that "non-structural measures... shall
In asserting that New York regulations define GSCs as structural, the Plaintiffs rely on regulations promulgated by the DEC for the approval of permits in coastal erosion hazard areas. 6 CRR-NY 505.1(a). The Plaintiffs' APA claim against the Corps does not raise any issue with the approval by the DEC of coastal management permits. Rather, the claim arises from their contention that the Corps misinterpreted the word "structure" as it is used in the East Hampton LWRP, which does not incorporate or refer to the DEC regulations. Therefore, the DEC regulations do not appear to be applicable in interpreting the word, "structure," as it is used in the East Hampton LWRP.
Even if the DEC regulations were applicable to interpreting the term, "structure," in the East Hampton LWRP, the regulations do not explicitly define GSCs as structures. In particular, under the DEC regulations, "erosion protection structure" is defined as "a structure specifically designed to reduce or prevent erosion, such as a groin, jetty, seawall, revetment, bulkhead, breakwater, or artificial beach nourishment project." 6 CRR-NY 505.2(p). In addition, "structure" is defined as:
The Plaintiffs contend that the Project is a "revetment" and therefore, falls under the above-definition of structure. (The Pls.' Objections, 15-cv-2349, Dkt. No. 75, at 7-11.) However, "revetment" is not defined by these regulations, and the Plaintiffs provide no reason other than their unsupported assertions for why the Court should consider the Project to be a "revetment." Thus, the Court finds that the Plaintiffs' contention that the Corps' conclusion that
The Plaintiffs also assert that Judge Shields applied the wrong standard when construing whether the Project violated the CZMA. (The Pls.' Objections, Dkt. No. 72, at 24.) They contend that Judge Shields statement, "the standard requires only conformance `to the maximum extent practicable,'" was incorrect as a matter of law. (The Pls.' Objections, 15-cv-2349, Dkt. No. 75, at 5.) Again, the Court finds the Plaintiffs' objection is without merit.
As noted, the CZMA requires that "[e]ach Federal agency activity within or outside the coastal zone that affects any land or water use or natural resource of the coastal zone shall be carried out in a manner which is
Finally, the Plaintiffs contend that Judge Shields erred by holding that the "exigent circumstances" exception applied to exempt the Corps from complying with the CZMA. (The Pls.' Objections, 15-cv-2349, Dkt. No. 75, at 6.) CEQ regulations provide that a federal agency "may deviate from full consistency with an approved management program when such deviation is justified because of an emergency or other similar unforeseen circumstance (`exigent circumstance'), which presents the Federal agency with a substantial obstacle that prevents complete adherence to the approved program." 15 C.F.R. § 930.32(b). Therefore, under this regulation, "exigent circumstances" only become relevant if the agency explicitly determines that its project is not "fully consistent" with an approved state or local management program.
In this case, the Corps determined that the Project was fully consistent with the East Hampton LWRP and CMP, and therefore, did not invoke the "exigent circumstances" exception. As Judge Shields determined that the Corps' consistency determination was supported by substantial evidence, she did not reach or apply the "exigent circumstances" exception, as the Plaintiffs contend. Therefore, the Plaintiffs' objection that Judge Shields misapplied the "exigent circumstances" exception is also without merit.
In sum, after a de novo review of the record, the Court finds that the Plaintiffs' APA claim that the Corps' August 11, 2014 consistency determination was "arbitrary and capricious" is not likely to succeed.
As discussed earlier, NEPA requires federal agencies to prepare an EIS for any major federal action "significantly affecting the quality of the human environment." 42 U.S.C. § 4332(C). The EIS must address: (i) the environmental impact of the proposed action, (ii) any adverse environmental effect which cannot be avoided should the proposal be implemented, (iii) alternatives to the proposed action, (iv) the relationship between local and short-term uses of man's environment and the maintenance and enhancement of long-term productivity, and (v) any irreversible and irretrievable commitments of resources which would be involved in the proposed action should it be implemented.
If an agency is uncertain as to whether a proposed action rises to the level of "a major federal action" requiring an EIS, the agency can prepare a shorter document called an EA, which is released to the public and provides "evidence and
On August 26, 2014, the Corps released drafts of the EA and the FONSI statement on its website and made them available for public comment for a thirty day period. The Corps received a number of comments from agencies and citizens, and incorporated some of those comments into the final EA and FONSI statement.
In the amended complaint, the Plaintiffs assert that the "Corps' FONSI determination violates the requirements of NEPA and is therefore irrational, arbitrary, and capricious." (Am. Compl. at ¶ 97.) In particular, the Plaintiffs assert that the Corps failed to take account of:
(
Judge Shields found that the Plaintiffs' APA claim arising from the Corps' NEPA determinations was not likely to succeed because (i) the Plaintiffs failed to object the draft EA and FONSI statement when they were available for public comment, and therefore, waived their claim; and (ii) even absent waiver, the EA and FONSI statement considered a number of alternatives based on a number of factors, and therefore, was not "arbitrary and capricious" under the APA. (The R&R at 27-29.)
The Court agrees with Judge Shields as to the second issue, and therefore, need not reach the issue of waiver. NEPA imposes only procedural requirements to "ensur[e] that the agency, in reaching its decision, will have available, and will carefully consider, detailed information concerning significant environmental impacts."
Because the statute is procedural in nature, once an agency follows the process provided for by NEPA, a court's review of the agency's decision is limited: "`[t]he only role for a court is to insure that the agency has taken a `hard look' at environmental consequences; it cannot `interject itself within the area of discretion of the executive as to the choice of the action to be taken.'"
Here, there is no question that the Corps took a hard look at the environmental consequences of the Project. It prepared a sixty-one page draft EA that directly addressed nearly all of the issues raised by the Plaintiffs in the amended complaint. With respect to the Plaintiffs' concerns about public access to the beach, the draft EA concluded that any impact on recreation would be temporary and limited because the Project area includes only a
Further, the Court noted that the Project would also greatly benefit public access to the beaches because it "would prevent the loss of beaches in the project area." (
Further, the FONSI statement also addressed the environmental impacts discussed above and concluded that they would be "minor in scope and temporary in duration." (Cortes Decl., 15-cv-2349, Dkt. No. 41, at Ex. 6.)
The Corps reached the conclusions described in the EA and FONSI statement after conducting an extensive study, informing agencies and stakeholders of the proposed work and the environmental evaluation contained in the draft EA, and, importantly, providing an opportunity for them to publicly comment on drafts for a period of thirty days. In addition, the Corps did alter the EA and FONSI statements in response to comments from some stakeholders, such as the EPA.
Based on this record, the Court finds that the Corps clearly took a "hard look" at the environmental consequences of the Project and that its conclusions were not arbitrary and capricious.
In their objections, the Plaintiffs argue that the EA and FONSI statements are inadequate because they did not address the effect of the Project on "stormwater" management. (The Pls.' Objections, Dkt. No. 75, at 17.) However, the Plaintiffs provide no evidence suggesting that the Project would have a negative effect on "stormwater" management other than their unsupported conclusory assertions. Nor do they explain why "stormwater" management is relevant to the environmental impact of the Project. Therefore, the Court finds the Plaintiffs' objection to be without merit.
In sum, the Court adopts the findings of Judge Shields and holds that the Plaintiffs have failed to satisfy any of the elements required for the issuance of a preliminary injunction halting construction on the Project.
For the foregoing reasons, the Court adopts the R&R in its entirety, and as a result, the Court hereby orders that:
(i) the Plaintiffs' request for an evidentiary hearing is denied; and that
(ii) the Plaintiffs' motion for a preliminary injunction is denied; and that
(iii) the Clerk of the Court is directed to close the Removal Action and terminate without prejudice the Defendants' motions to dismiss pending in the Removal Action; and that
(iv) the Intervenors may move to intervene in the Federal Action; and that
(v) the Defendants in the Federal Action have thirty days from the date of this Order, or thirty days after service of the amended complaint, to answer or otherwise move in the Federal Action.