DENISE COTE, District Judge.
Plaintiff Maritima de Ecologia ("Marecsa") moves for reconsideration of portions of the April 15, 2011 Opinion and Order granting defendant Sealion Shipping Ltd.'s ("Sealion") motion to stay the above-captioned action pending the London arbitration of claims relating to the parties' prior course of dealing.
The Court assumes familiarity with the April 15 Opinion. On October 27, 2010, Marecsa filed this action (the "October 27 Complaint") to recover fees for services it provided from May 21 to September 24, 2010 in connection with the Deepwater Horizon catastrophe in the Gulf of Mexico ("Gulf") without the benefit of a written contract. On December 7, Sealion served Marecsa with an arbitration demand for alleged breaches of written contracts which had structured the parties' relationship in the context of work performed for Pemex Exploration and Production ("PEP") between June 8, 2003 and March 21, 2010 (the "London Arbitration"). On February 11, 2011, Sealion's motion to compel arbitration and stay the instant litigation pending completion of the London Arbitration became fully submitted.
Marecsa's October 27 Complaint alleges that "[b]y virtue of the parties' course of dealing, SEALION was aware of the approximate fees for MARECSA's services [provided in the Gulf] inclusive of profit margins." Finding that the outcome of the London Arbitration is relevant to determining the "approximate fees . . . inclusive of profit margins" to which Marecsa refers, the April 15 Opinion stayed the above-captioned action.
On April 29, Marecsa moved for reconsideration of the portion of the April 15 Opinion which stayed this action, or in the alternative, for discovery concerning liability while the London Arbitration is pending (the "April 29 Motion"). The April 29 Motion became fully submitted on May 20.
The standard for reconsideration is strict. "Generally, motions for reconsideration are not granted unless the moving party can point to controlling decisions or data that the court overlooked — matters, in other words, that might reasonably be expected to alter the conclusion reached by the court."
Marecsa has not shown that the April 15 Opinion overlooked any of the facts or the legal arguments that were presented to the Court. Marecsa principally makes three arguments in support of the April 29 Motion. First, it contends that the documents setting forth Sealion's case against Marecsa in the London Arbitration, which were submitted in opposition to the motion to stay, demonstrate that the amount of Marecsa's fees under the PEP contracts is not at issue in the London Arbitration. This is, however, a new argument that Marecsa did not set out when it opposed Sealion's motion to stay. In moving for a stay, Sealion quoted the passage regarding fees from the October 27 Complaint that is repeated,
Second, Marecsa contends that a more recent per diem rate for Marecsa's services, which an addendum to one of the parties' agreements contains, makes the London Arbitration less relevant to the determination of a reasonable rate for Marecsa's Deepwater Horizon work. Marecsa, however, did not even refer to the addendum containing the
Finally, Marecsa requests that any stay be modified to permit discovery on the issue of liability while the London Arbitration is pending. It argues that such discovery would minimize future delays in this action. Marecsa did not make this request in opposing Sealion's motion for a stay. Moreover, to the extent that Marecsa's request for some discovery should be understood as a reassertion of its general argument that it will be prejudiced by delay, this argument must fail as an attempt "to relitigate an issue already decided."
Plaintiff's April 29 Motion for reconsideration of the April 15 Opinion is denied.
SO ORDERED: