VINCENT L. BRICCETTI, District Judge.
The Court presided over a bench trial in this matter from June 17 to June 21, 2019. On July 22, 2019, the Court issued a bench ruling (i) holding that Hilt Construction & Management Corp. ("Hilt") was entitled to judgment on its breach of contract claim and awarding Hilt $75,000 in damages; (ii) dismissing The Permanent Mission of Chad to the United Nations in New York's (the "Mission") breach of contract counterclaim; and (iii) holding that the Mission was entitled to judgment dismissing Hilt's quantum meruit and account stated claims.
The Court did not direct the Clerk to enter judgment, because Hilt indicated at the time of the bench ruling that it sought prejudgment interest on its breach of contract claim. Instead, the Court ordered Hilt to submit a letter outlining (i) the legal basis for its request for prejudgment interest, (ii) the date from which it believed prejudgment interest should be calculated, and (iii) the prejudgment interest rate it sought. (Doc. #76). The Court also ordered the Mission to respond to Hilt's submission by letter.
On July 29, 2019, Hilt submitted a letter in compliance with the Court's July 22 Order. (Doc. #77). The Mission responded on August 2, 2019. (Doc. #78). In addition to opposing Hilt's request for prejudgment interest, the Mission seeks a "post-trial motion to amend" (id.), which the Court construes as a motion for reconsideration of its July 22 bench ruling.
For the following reasons, Hilt's request for prejudgment interest is GRANTED and the Mission's motion for reconsideration is DENIED. The Court will direct the Clerk to enter judgment in Hilt's favor for $100,335.62, which includes $25,335.62 in prejudgment interest.
The Court assumes the parties' familiarity with the facts and procedural history of this case.
Hilt argues it is entitled to $25,238.85 in prejudgment interest on the $75,000 damages award on its breach of contract claim, calculated at nine percent per annum from November 5, 2015, to August 5, 2019.
The Court agrees, but finds Hilt is entitled to $25,335.62 in interest, from November 5, 2015, to August 6, 2019.
"The awarding of prejudgment interest is considered a question of substantive law."
Under New York law, a party may recover prejudgment interest on "a sum awarded because of a breach of performance of a contract." N.Y. C.P.L.R. § 5001(a). New York's statutory rate of nine percent per annum applies.
As for the date from which prejudgment interest is calculated:
N.Y. C.P.L.R. § 5001(b). When the precise date upon which damages were incurred is ambiguous, the date of commencement of the action is an appropriate date from which to compute damages.
Here, Hilt requests prejudgment interest from November 5, 2015, the date on which Hilt filed a complaint in an earlier related action. Complaint,
The Mission argues Hilt is not entitled to prejudgment interest because (i) Hilt has not shown it incurred interest on a loan from a bank; (ii) the Mission did not know in advance the sum of damages it owed Hilt; and (iii) both parties breached the contract. The Mission's arguments are without merit. Hilt does not need to show that it borrowed from a bank to be entitled to prejudgment interest, and the Mission does not provide any legal support for its argument that the breaching party must know in advance the sum of damages it owes the aggrieved party. Finally, the Court found that Hilt did not breach the contract; thus, the Mission's argument would fail even if the Mission had provided legal support for its third argument (which it does not).
Accordingly, Hilt is entitled to $25,335.62 in prejudgment interest on its $75,000 damages award.
The Mission argues the Court improperly relied on plaintiff's exhibits ("PX") 49, 54, and 57 to calculate damages, after holding Ajaz Ahmed's testimony was generally not credible and that those exhibits did not themselves constitute reliable evidence of additional work performed due to concealed or unknown conditions. The Mission further argues the Court instead should have used "fair market value" to determine damages.
It is unclear what the procedural basis is for the Mission's so-called "post-trial motion to amend." (Doc. #78). Nevertheless, the Court construes the Mission's request as a motion for reconsideration. To that end, the Court finds the Mission has failed to demonstrate any error, clear or otherwise, in the Court's July 22 bench ruling, or any other basis to prevail on its motion.
"To prevail on a motion for reconsideration, the movant must demonstrate `an intervening change of controlling law, the availability of new evidence, or the need to correct a clear error or prevent manifest injustice.'"
Further, the motion "may not advance new facts, issues, or arguments not previously presented to the court."
Here, the Mission's argument is essentially a misunderstanding of the different standards for determining liability and calculating damages. "New York courts have significant flexibility in estimating general damages once the fact of liability is established."
Moreover, the Mission—not Hilt—bears the uncertainty of the amount of damages. When "the existence of damage is certain, and the only uncertainty is as to its amount, . . . the burden of uncertainty as to the amount of damage is upon the wrongdoer."
Therefore, the Mission's motion for reconsideration is DENIED.
Accordingly, the Clerk is directed to enter judgment in accordance with the following:
1. Granting judgment in favor of Hilt Construction & Management Corp. (i) on its breach of contract claim, and awarding damages on that claim in the amount of $100,335.62, which includes $75,000 plus $25,335.62 in prejudgment interest; and (ii) dismissing The Permanent Mission of Chad to the United Nations in New York's breach of contract counterclaim;
2. Granting judgment in favor of The Permanent Mission of Chad to the United Nations in New York dismissing Hilt Construction & Management Corp.'s quantum meruit and account stated claims.
The Clerk is also directed to terminate the letter-motion (Doc. #78) and close this case.
SO ORDERED.