JOHN R. ADAMS, District Judge.
On July 14, 2017, this Court referred the Plaintiffs' motion for a preliminary injunction (Doc. 6) to Magistrate Judge Burke for a report and recommendation. On August 7, 2017, Magistrate Judge Burke issued a Report and Recommendation ("the Report") that this Court deny the motion for a preliminary injunction. Plaintiffs objected to the Report, and Defendants responded to those objections.
Plaintiffs are a group of property owners that assert that they will be negatively impacted by a natural gas pipeline that Nexus seeks to build. As such, they filed suit on May 12, 2017 and sought injunctive relief. In their request, Plaintiffs contend that there is error in the Final Environmental Impact Statement issued by FERC and that Nexus proceeded under the wrong section of the Natural Gas Act. The Report, however, does not reach the merits of these contentions. Instead, the Report concludes that this Court lacks subject matter jurisdiction over the complaint in its entirety.
Section 7 of the Natural Gas Act grants FERC the jurisdiction to approve or deny the construction of interstate natural-gas pipelines. See 15 U.S.C. § 717f. Before any such pipeline can be built, FERC must grant the developer a "certificate of public convenience and necessity," id. § 717f(c)(1)(A), also called a Section 7 certificate, upon a finding that the project will serve the public interest. See id. § 717f(e). FERC is also empowered to attach "reasonable terms and conditions" to the certificate, as necessary to protect the public. Id. A certificate holder has the ability to acquire necessary rights-of-way from unwilling landowners by eminent domain proceedings. See id. § 717f(h). Any party to a proceeding under the Act who is "aggrieved" by a FERC order may petition for review of that order in a Federal Circuit Court of Appeals, provided that they first seek rehearing before FERC. Id. § 717r(a)-(b).
The Sixth Circuit has described this process as follows:
Am. Energy Corp. v. Rockies Express Pipeline LLC, 622 F.3d 602, 605-606 (6th Cir. 2010) (emphasis added). The Tenth Circuit stated that 15 U.S.C. § 717r(b) "vests exclusive jurisdiction to review all decisions of the Commission in the circuit court of appeals . . . there is no area of review, whether relating to final or preliminary orders, available in the district court." Consolidated Gas Supply Corp v. Federal Energy Regulatory Commission, 611 F.2d 951, 957 (10th Cir. 1979) (internal citations omitted).
Plaintiffs herein seek to avoid the conclusion that appears compelled by the reasoning expressed by the Sixth Circuit. Specifically, Plaintiffs contends that this litigation was filed prior to the issuance of a Certificate and that 15 U.S.C. § 717u must be read to confer jurisdiction upon this Court. Section 717u reads in part: "The District Courts of the United States and the United States courts of any Territory or other place subject to the jurisdiction of the United States shall have exclusive jurisdiction of violations of this chapter or the rules, regulations, and orders thereunder, and of all suits in equity and actions at law brought to enforce any liability or duty created by, or to enjoin any violation of, this chapter or any rule, regulation, or order thereunder." This Court, however, agrees that the "highly reticulated procedure" detailed by the Sixth Circuit "would be entirely undermined if unhappy parties could come to district courts" prior to the issuance of a Certificate to avoid that process. Lovelace v. United States, Case No. 15CV30131 (D.Mass. Feb. 18, 2016).
Similarly, the Court finds no error in the Report's conclusion that the Leedom exception is not invoked under the facts presented herein. As the Report properly notes, the Leedom exception allows for Court review in limited circumstances despite an otherwise comprehensive statutory scheme of review. Greater Detroit Res. Recovery Auth v. U.S. E.P.A., 916 F.2d 317, 323 (6th Cir. 1990). "In order to bring a case within the exception, it must be shown that the action of the agency was a patent violation of its authority or that there has been a manifest infringement of substantial rights irremediable by the statutorily prescribed method of review." Id. Plaintiffs' contentions are that FERC improperly delegated safety regulation to another agency and improperly permitted Nexus to pursue a certificate as an interstate pipeline rather than an export pipeline. Neither argument demonstrates a "patent violation of authority." Rather, both simply represent claims that FERC improperly exercised its discretion in evaluating the circumstances before it. Those claims are precisely the type of claims that can and should be reviewed in compliance with the regulatory scheme set forth in the Natural Gas Act.
Having found no merit in Plaintiffs' objections and finding itself in agreement with the logic espoused in the Report, the Court hereby ADOPTS the Report in its entirety. Based upon that adoption, the motion for preliminary injunction (Doc. 6) is DENIED. Moreover, based upon the above, both motions to dismiss for lack of subject matter jurisdiction (Docs. 24 and 28) are GRANTED. This matter is hereby dismissed for lack of subject matter jurisdiction.
IT IS SO ORDERED.