JOHN JELDERKS, Magistrate Judge.
Plaintiff Stellar J Corporation (Stellar J) brings this action against defendant Smith & Loveless, Inc. (Smith). Smith asserts counterclaims, and asserts third-party claims against Travelers Casualty and Surety Company of America (Travelers).
Defendant Smith moves for summary judgment on all of plaintiff Stellar J's claims. The motion should be granted in part and denied in part as set out below.
This action arises from a contract between plaintiff Stellar J and defendant Smith for the purchase and installation of equipment for use in a wastewater treatment improvement project (the Project) in the City of Rainer, Oregon (the City). Plaintiff Stellar J was the general contractor hired by the City. Stellar J and defendant Smith entered into a sales and subcontract agreement under which Smith agreed to specially fabricate and install a new treatment unit, and to supply retrofit equipment that would be used in refurbishing the City's existing treatment plant.
On January 10, 2008, the City issued Stellar J a notice to proceed with construction. The notice allowed Stellar J until January 10, 2009 (365 days) to substantially complete the Project, and until March 9, 2009 (420 days) for final completion according to the terms of the Contract Documents.
During the course of the Project, the City issued Stellar J a series of Change Orders which extended the deadline for substantial completion to May 17, 2009, and extended the final completion date to July 11, 2009. With these extensions, the contract price to be paid to Stellar J for the Project was increased by $616,441.35, to $9,007,880.05. None of the Change Orders extending contract deadlines were caused by Smith's delay in delivering or installing equipment for the Project.
Based upon its assertion that Smith failed to provide services and materials within the time frame required, Stellar J terminated the parties' subcontract on February 24, 2009. Thereafter, Stellar J contracted with another supplier to obtain the equipment that Smith had agreed to provide.
In a letter to the City's consultant dated May 21, 2009, Tim Bauman, Stellar J's Project Manager, stated that the Project was substantially complete. Stellar J finished the start up of the retrofitted treatment unit by July 7, 2009, and began demobilizing from the job site the following day. Except for certain punch list items that were not related to defendant Smith, all remaining work was completed by mid-July, 2009. Because Stellar J's work was completed within the revised allowable Contract Period, as extended by the Change Orders noted above, the City asserted no claims for liquidated damages against Stellar J.
Section 5.17 of the General Conditions of the Project Manual for the Project provides that:
Several provisions of the subcontract agreement between Stellar J and Smith are relevant to the analysis of the pending motion. Under Paragraph 2 of the subcontract agreement, plaintiff Stellar J and defendant Smith agreed "to be bound by the terms of [the] MAIN CONTRACT with the Owner, including every part of and all the general and specific conditions, drawings, specifications, and addenda in anyway applicable to [the] SUBCONTRACT."
Paragraph 6 of the subcontract agreement states that:
Paragraph 16 of the subcontract agreement provides that:
Paragraph 26 of the subcontract agreement provides that:
In the present action, plaintiff Stellar J alleges that it was damaged by defendant Smith's late delivery and/or installation of the equipment that it was required to provide pursuant to the subcontract agreement. In his expert report dated March 1, 2010, Jeffery Busch, Stellar J's "delay and damage" expert, opined that defendant Smith's failure to timely perform delayed completion of the Project by 94 work days and 134 calendar days. Busch opined that, because of delays caused by Smith, Stellar J incurred $436,215.21 in damages. In his expert report, he itemizes these damages as follows:
Because Stellar J withheld $233,087.12 from defendant Smith's contract payments, Busch concludes Smith now owes net damages in the amount of $203,128.09.
Plaintiff Stellar J acknowledges that it never suspended work on the Project because of any delays allegedly caused by defendant Smith, and acknowledges that it "re-sequenced its work" to minimize the impact of these alleged delays. Smith has cited documents supporting the conclusion that Stellar J "recorded a 24% gross profit of $2,126,418 on the Rainer job, exceeding its original budgeted or anticipated Project profit margin of 10.1%." Stellar asserts that this calculation is irrelevant and inaccurate.
Federal Rule of Civil Procedure 56 (c) authorizes summary judgment if no genuine issue exists regarding any material fact and the moving party is entitled to judgment as a matter of law. The moving party must show the absence of an issue of material fact.
The substantive law governing a claim or defense determines whether a fact is material.
Defendant Smith contends that it is entitled to summary judgment because the parties' subcontract agreement, incorporating the Main Contract between Stellar J and the City, precludes recovery of damages based upon delay. Smith also contends that plaintiff Stellar J's claim of $172,283.95 for home office overhead is in fact a claim for "unabsorbed home office overhead" that is barred because Stellar J cannot show that it was "on standby" because of delay allegedly caused by Smith and "unable to take on other work." Smith further contends that Stellar J's claims for "field and home office" are too speculative to support an award of damages, and that recovery on these claims would result in an impermissible "windfall."
Defendant Smith contends that Stellar J is contractually barred from recovering most of the costs allegedly caused by any delay for which Smith might otherwise be responsible
This argument has some superficial appeal. As noted above, Section 5.17 of the "Main Contract" between Stellar J and the City prohibits Stellar J from recovering "extended overhead or other charges" for delays that extended the completion date beyond the date "planned by the Contractor but not beyond the Contract Time. . . ." Paragraph 2 of the parties' subcontract Agreement incorporated the terms of the "Main Contract" into the agreement between Stellar J and Smith, and there is no question that Stellar J ultimately completed its work within the allowable Contract Period, as extended by the Change Orders noted above.
Nevertheless, I am not convinced that these or any other provisions of the Main Contract and the subcontract Agreement preclude Stellar J's recovery of damages shown to result from delay caused by defendant Smith. Though the Main Agreement is incorporated into the parties' subcontract agreement, the limitations on damages recoverable for delay set out in Section 5.17 of the Main Agreement were included for the benefit of the City, not subcontractors like Smith. In a portion of Section 5.17 not cited by Smith, on behalf of itself and its subcontractors, Stellar J expressly waived claims for damages for delays caused by the City and its employees, engineers, and agents. Section 5.17 expressly provides that extension of the Contract Time is the "exclusive remedy" available to Stellar J and its subcontractors for delays caused by the City or these individuals.
When a subcontract incorporates the terms of a contract between a general contractor and an owner, the subcontractor cannot rely on terms that are included in the "main contract" for the sole benefit of the owner.
As noted above, paragraph 6 of the subcontract agreement required Smith to comply with Stellar J's schedule, and obligated it to pay any "extended overhead costs" that Stellar J incurred as a result of its failure to do so. Paragraph 16 required Smith to provide sufficient workmen and materials to carry out its work "with promptness and diligence," and provided remedies, including Smith's liability for costs, if these obligations were not met. Paragraph 26 allowed Stellar J to recover costs it incurred as extended overhead because of delay by Smith as a "backcharge."
Defendant Smith has not established that provisions of the "Main Contract" which were incorporated into the parties' subcontract Agreement preclude Stellar J's recovery of damages resulting from delay. Smith cannot rely upon terms of the "Main Contract" that were included for the benefit of the City, and nothing in the provision upon which Smith relies addresses Stellar J's right to recover damages caused by a subcontractor's delay. That this right is expressly set out in other provisions in the subcontract agreement supports the conclusion that incorporation of the Main Contract into the subcontract was not intended to preclude such recovery.
Defendant Smith's assertion that it is entitled to summary judgment as to most of Stellar J's claim because it has already recovered any added expenses through change orders extending the completion deadline also fails. Stellar J has submitted evidence supporting the conclusion that the change orders did not reflect delays caused by S&L, and correctly notes that change orders do not in any event include a line item for extended overhead. Stellar J cites evidence in the record supporting the conclusion that it has not been compensated for damages allegedly resulting from delay caused by defendant Smith. Stellar J also correctly notes that, under the "Main Contract," it is entitled to a 15% mark-up on change orders whether or not they extend the contract time. The record does not conclusively establish that Stellar J has been fully compensated for all damages allegedly arising from delay caused by defendant Smith. Material issues of fact exist as to whether Smith breached its contractual obligation to timely perform, and as to whether, but for any delays caused by Smith, Stellar could have completed the project sooner and realized greater profits.
In his expert report prepared for Stellar J, Jeffrey Busch opined that delays caused by defendant Smith caused Stellar J to incur damages for "Extended Home Office Overhead" in the amount of $172,283.95. In its memoranda submitted in support of its motion for summary judgment, defendant Smith characterizes Stellar J's claim for this amount as a claim for "Unabsorbed Home Office Overhead." Smith asserts that this claim is "nothing more than a `disguised Eichleay formulation' for its extended home office overhead calculation." Smith contends that this claim "should be summarily dismissed as a matter of law where work on the Project was never suspended, Stellar J was never placed on standby, and there is no evidence Stellar J was unable to take on additional work due to the delay."
These assertions require a brief examination of the difference between claims for "extended overhead" and "unabsorbed overhead." "Extended overhead" has been described as "a concept unique to construction contracting," and defined as "the additional costs incurred when a job's performance period is prolonged."
In order to recover damages for "extended overhead," a contractor must "show added overhead costs which exceed its normally incurred fixed expenses attributable to ongoing business operations. . . ."
In
Defendant Smith asserts that, in his calculation of Stellar J's claim for "Extended Home Office Overhead," Busch used a "disguised Eichleay formula," prorating Stellar J's home office overhead expenses between Stellar J's billings for the Rainier project and the total billings on all of its projects during the contract period, and multiplying the resulting amount of daily home office overhead attributable to the Rainer project by the number of days of delay allegedly caused by Smith. Smith contends that, because Busch used the Eichleay formula applicable for calculating unabsorbed home office overhead, Stellar J's claim for purported "extended home office overhead" is simply a claim for "unabsorbed home office overhead." It further contends that Stellar J cannot recover these costs because it was not on "standby" during the period of delay for which recovery is sought, and because it has not shown that it was unable to take on additional work during that period.
If Stellar J were asserting a claim for "unabsorbed overhead," that claim would fail because it cannot show that it was ever required to be on "standby" while work on the project was suspended because defendant Smith failed to timely perform its obligations, and has not shown that it was unable to take on additional work during such a period.
As noted above, in order to prevail on a claim for extended overhead, a contractor must show that it has incurred
As the
Smith contends that Stellar J's claims for "extended field
As discussed above, Smith is entitled to summary judgment as to the claim for "extended home office overhead" in the amount of $172,283.95. However, material issues of fact preclude summary judgment as to Stellar J's claim for "direct added jobsite costs." Stellar J has cited evidence supporting the conclusion that the change orders granted by the City were not related to the delays caused by Smith, and that Stellar J accordingly did not cover the additional jobsite expenses it incurred because of delays allegedly caused by Smith. Stellar notes that the change orders in any event do not include a line item for extended overhead, and cites evidence that, though it was granted additional time to complete the Project under the change orders, it could have completed the Project sooner if Smith had timely performed. Stellar also correctly notes that the profits it ultimately realized on the Project are not relevant in determining whether it would have earned more but for Smith's alleged failure to timely perform.
Defendant Smith's motion for summary judgment (# 44) should be GRANTED in part and DENIED in part. The motion should be GRANTED as to plaintiff Stellar J's claim in the amount of $172,283.95 for extended home office overhead, and should be DENIED as to the balance of Stellar J's claims.
This Findings and Recommendation will be referred to a district judge. Objections, if any, are due August 23, 2010. If no objections are filed, then the Findings and Recommendation will go under advisement on that date.
If objections are filed, then a response is due within 14 days after being served with a copy of the objections. When the response is due or filed, whichever date is earlier, the Findings and Recommendation will go under advisement.