MEMORANDUM
ERIC L. FRANK, Bankruptcy Judge.
I. INTRODUCTION
Northwest 15th Street Associates ("the Debtor") is the owner of the surface and air rights to a parcel of real property located on the northwest corner of 15th and Arch Streets in Philadelphia, Pennsylvania ("the Property"). In April 2009, Debtor entered into a written contract with EwingCole, Inc. ("Ewing"), pursuant to which Ewing provided architectural services to the Debtor. The services included the preparation of certain architectural plans. The plans were prepared in connection with a multi-party project for the construction of a sixteen-story courthouse and underground parking garage on the Property ("the Courthouse Project"). The parties contemplated that the new courthouse would be the future home of the Philadelphia Family Court. The Debtor not only owned the Property, but served as the developer of the sit for the Courthouse Project. Also involved in the Courthouse Project were: (1) the First Judicial District of Pennsylvania ("the FJD"), the party for whom the Debtor was to build the courthouse and (2) the Philadelphia Parking Authority ("the PPA"), the party that granted the surface and air rights to the Debtor (while retaining the below-surface rights) and for whom the Debtor was to construct the underground garage.
Shortly after the filing of this case, the parties brought before the bankruptcy court a dispute involving ownership of certain architectural plans that Ewing prepared in connection with the Courthouse Project. Ewing and the Debtor each claim ownership of the plans that Ewing completed in March 2010 ("the March Plans"). Their dispute is grounded in the parties' different interpretations of their written contract.
Ewing has requested the entry of an order: (1) determining that Ewing, as the rightful owner of the plans, may use and exercise control over them without violating the automatic stay, see 11 U.S.C. § 362(a)(3),1 or (b) otherwise granting Ewing relief from the automatic stay to do so for "cause," see 11 U.S.C. § 362(d)(1).2 The Debtor has opposed the relief requested by Ewing, asserting that it owns the March Plans, that the March Plans are property of the bankruptcy estate, see 11 U.S.C. § 541(a), and that cause does not exist to authorize Ewing to use or exercise control over bankruptcy estate property.
Based on the evidence presented at the hearing held in this matter and my interpretation of the parties' contract, I have concluded that Ewing's ownership claim over the disputed March Plans is superior to the Debtor's. As a result, on August 26, 2010, I entered an order granting Ewing's request for relief under 11 U.S.C. § 362(d).3 In this Memorandum, to be docketed on August 27, 2010, I explain the reasons for my ruling.
II. PROCEDURAL BACKGROUND
The Debtor commenced this case by filing a voluntary petition under chapter 11 of the Bankruptcy Code on June 23, 2010. In the petition, the Debtor described its business as "single asset real estate."4 (See Debtor's Schedule A) (Doc. # 17).5
On July 23, 2010, the FJD filed a motion for relief from the automatic stay ("the FJD Motion") (Doc. # 38). On the same day, the PPA filed a motion for relief from the automatic stay ("the PPA Motion") (Doc. # 37).6 On July 28, 2010, the Debtor filed a Motion to Strike both the FJD Motion and the PPA Motion, primarily on the ground that the relief requested by the movants required the initiation of an adversary proceeding pursuant to Fed. R. Bankr.P. 7001. By order dated August 19, 2010, the court denied the Debtor's Motion to Strike without prejudice to any defenses the Debtor may have to the Motions. (Doc # 72). However, presently, only the FJD Motion remains pending before the court.7
In its motion, the FJD contends that the March Plans are owned by Ewing.8 Alternatively, the FJD contends it owns the March Plans, but that under no circumstances does the Debtor own the Plans. The FJD requests the entry of an order authorizing the FJD to use the March Plans in connection with the planning and construction of the new Family Court building. (FJD Motion ¶¶ 1, 27, 35, 38).
On July 26, 2010, Ewing filed what it styled as a "Joinder" to the FJD Motion. (Doc. # 44). In the Joinder, Ewing asserted that it is the owner of the Plans and requested that the court grant the FJD Motion. (See Ewing Joinder ¶¶ 3, 25, prayer for relief).
On August 11, 2010, one week before the scheduled hearings, the court conducted a pretrial conference on the FJD Motion and the (then still pending) PPA Motion. After a colloquy with the court, the parties agreed that the hearing on the FJD Motion would be handled as follows:
1. the court would first hold a hearing on the issues raised by Ewing's Joinder, i.e., under the Ewing Contract, whether the Debtor or Ewing owns the Plans ("the First Hearing");
2. if the court determined that Ewing owns the plans and may exercise control over them without violating the automatic stay, or otherwise grants relief for Ewing to do so, the FJD likely would withdraw its request for relief from the automatic stay;9 if, however, the Debtor prevailed on the issue, a further hearing would be held on the FJD Motion ("the Second Hearing").10
In effect, while not expressly labeled as such in the colloquy, the parties agreed that Ewing's "Joinder" would be treated as a separate Motion for Relief from the Automatic Stay.11
On August 18, 2010, the First Hearing was held and concluded. Ewing submitted a post-hearing memorandum in support of its position on August 20, 2010. The Debtor did likewise on August 23, 2010. The court entered its order granting Ewing's request for relief from the automatic stay on August 26, 2010.
III. FINDINGS OF FACT
Based on the evidence presented at the First Hearing,12 I make the following findings of fact.13
1. In 2006, Ewing was retained on a pro bono basis by the "tenant representative" of the FJD to assist the FJD in evaluating potential sites for the construction of a new facility to house the Philadelphia Family Court.
2. In April 2008, the FJD selected the Property as the development site.
3. In April 2008, the Debtor was (and presently is) the owner of the surface and air rights to the Property. The PPA owns the below-surface rights to the Property.
4. Pursuant to a Development Services Agreement between the PPA and the Debtor, originally entered into in 2004, and subsequently amended on various occasions, including on May 23, 2008, and other related agreements, in 2008, the Debtor agreed to serve as the developer for the construction of a courthouse and an underground garage on the Property (i.e., the Courthouse Project).
5. Between April 2008 and April 2009, Ewing began providing architectural services to the Debtor for the development of the Courthouse Project on the Property. During that time period, the parties did not have a signed, written contract governing the terms of the Debtor's retention of Ewing as the architect for the Courthouse Project.
6. Between April 2008 and April 2009, Ewing and the Debtor negotiated the terms of a written contract.
7. In the negotiations, Ewing was represented by John Gerbner, the President of Ewing and an architect with thirty (30) years of experience in the field. The Debtor was represented by Anastasius Efstratiades, an attorney at the law firm Obermayer Rebmann Maxwell & Hippel, LLP.
8. On April 7, 2009, Ewing and the Debtor entered into a written contact, titled "AIA Document B141—Standard Form of Agreement Between Owner and Architect," which included a Part I and Part II ("the O/A Agreement" or "the Agreement").
9. In the O/A Agreement, Ewing agreed to provide various services to the Debtor including: (a) evaluation and planning services, (b) design services; (c) preparation of construction documents (such as drawings and specifications); (d) assistance in developing and preparing bidding and procurement information; (e) assistance in obtaining competitive bids and proposals; (f) assistance in administering contracts with contractors; (f) site evaluations during construction; and (g) review of facility operations after substantial completion of the project. (O/A Agreement §§ 2.1.1-2.8.3).
10. The O/A Agreement between the parties is based on a form contract developed by the American Institute of Architects ("the Form O/A Agreement").
11. The O/A Agreement includes an "integration clause." (O/A Agreement § 1.4.1).
12. As a result of negotiations, the parties modified certain provisions of the Form O/A Agreement by striking out certain words and adding other words.
13. The parties modified § 1.3.2.1 of the Form O/A Agreement as follows:14
Drawings, specifications and other documents, including those in electronic form, prepared by the Architect, and the Architect's consultants are Instruments of Service for use solely with respect to of this Project. The Architect and the Architect's consultants shall be deemed the authors and owners of their respective Instruments of Service and shall retain all common law, statutory and other reserved rights, including copyrights copyrights until transfer of ownership of the Instruments of Service to Owner. Upon payment to Architect of sums due hereunder, those drawings, specifications, models, renderings and work product prepared in connection with the Project (sometimes referred to as the "Instruments of Service") for which Architect has been paid shall become the property of Owner. Upon payment of all sums due hereunder, all Instruments of Service shall become the property of Owner. Architect shall deliver any and all such drawings and specifications to Owner, and Architect agrees to make no further use thereof.
14. The parties modified § 1.3.2.2 of the Form O/A Agreement as follows:
Upon execution of this Agreement, and during the period that Ownership of the Instruments of Service remain with the Architect, the Architect grants to the Owner a nonexclusive license to reproduce the Architect's Instruments of Service solely for purposes of constructing, using and maintaining the Project, provided that the Owner shall comply with all obligations, including prompt payment of all sums when due, under this Agreement. The Architect shall obtain similar nonexclusive licenses from the Architect's consultants consistent with this Agreement. Any termination of this Agreement prior to completion of the Project shall terminate this license. Upon such termination, the Owner shall refrain from making further reproductions of Instruments of Service and shall return to the Architect within seven days of termination all originals and reproductions in the Owner's possession or control. If and upon the date the Architect is adjudged in default of this Agreement, the foregoing license shall be deemed terminated and replaced by a second, nonexclusive license permitting the Owner to authorize other similarly credentialed design professionals to reproduce and, where permitted by law, to make changes, corrections or additions to the Instruments of Service solely for purposes of completing, using and maintaining the Project. To the fullest extent permitted by law, the Owner shall indemnify and save harmless the Architect from and against any and all claims, demands, suits, judgments, liability, damages, costs of expenses (including attorney's fees and other defense costs) arising in connection with any use by the Owner or others authorized by the Owner of the Instruments of Service subsequent to the termination of the Architect for default.
15. As Ewing provided services to the Debtor, it sent monthly invoices to the Debtor, as authorized by § 1. 5.7 of the O/A Agreement.15
16. Section 1.5.8 of the O/A Agreement provides that payments are due thirty (30) days from the date of the invoice.
17. In March 2010, Ewing completed preparation of the initial Plans for the Courthouse Project, the March Plans.16
18. Prior to April 27, 2010, Ewing invoiced the Debtor for all of the work it performed in preparing the March Plans.
19. Prior to April 27, 2010, the Debtor paid Ewing for all of the services Ewing provided in preparing the March Plans.
20. After the March Plans were completed, certain governmental authorities made comments or mandated changes in the Courthouse Project that required Ewing to revise the March Plans.
21. Between March and May 2010, Ewing revised the March Plans and created a set of modified plans ("the May Plans").
22. On April 27, 2010, Ewing sent the Debtor an invoice in the amount of $298,953.00 ("the April 27, 2010 Invoice").
23. The Debtor did not pay the April 27, 2010 Invoice and has made no payments to Ewing since the issuance of the April 27, 2010 Invoice.
24. The Debtor did not pay for the services rendered by Ewing in preparing the May Plans.
25. On June 8, 2010, Ewing, through its counsel, sent the Debtor a letter that:
a. gave the Debtor notice of the default in failing to pay the April 27, 2010 Invoice under § 1.3.8.1 of the O/A Agreement;17
b. advised the Debtor that due to its nonpayment of all sums due under the O/A Agreement, Ewing considered itself the owner of "the Construction Documents and Specifications," which include the March Plans and the May Plans.
26. On June 17, 2010, Ewing, through its counsel, sent the Debtor a letter that:
a. gave the Debtor notice of Ewing's termination of the O/A Agreement;18
b. demanded payment of the April 27, 2010 Invoice and monies falling due after the date of that invoice, for a total demand of $651,604.71;
c. reiterated Ewing's position that Ewing is the owner of all of the Plans it prepared in connection with the Courthouse Project.
27. Prior to approximately seven to ten years ago, and consistent with § 1.3.2.1 of the Form O/A Agreement, it was common for architects' contracts with property owners to provide for the architect to retain all ownership rights of the plans prepared by the architect in connection with the project that was the subject of the contract, while providing the owner with a nonexclusive license to use the plans in connection with the project.
28. In the past seven to ten years, it has become common in the industry for property owners to request, and for architects to consent to, modifications of § 1.3.2.1 of the Form O/A Agreement. Section 1.3.2.1 is modified regularly to provide that ownership of the architectural plans will pass from the architect to the property owner at some point in time.
29. There is no settled custom or usage in the industry, however, regarding precisely when the ownership of the plans will pass to the property owner in connection with those contracts that provide that ownership of the architectural plans will pass from the architect to the property owner.19
IV. CONCLUSIONS OF LAW—DISCUSSION
A.
Resolution of this contested matter requires that the court interpret a contract.20 Central to the dispute is the meaning of two sentences in § 1.3.2.1 of the O/A Agreement. Both of these sentences were added to the Form O/A Agreement, a form contract regularly used in the industry. The sentences are quoted below.
Sentence # 1
Upon payment to Architect of sums due hereunder, those drawings, specifications, models, renderings and work product prepared in connection with the Project (sometimes referred to as the "Instruments of Service") for which Architect has been paid shall become the property of Owner.
Sentence # 2
Upon payment of all sums due hereunder, all Instruments of Service shall become the property of Owner.
Ewing maintains that ownership of the March Plans never passed to the Debtor because, in its view, Sentence # 2 provides for the Debtor to become the owner of the Plans only after the Debtor has paid all sums due the entire Agreement. Because it is undisputed that the Debtor has not done so, Ewing contends that it retains ownership of the Plans. Further, Ewing contends that, pursuant to § 1.3.2.2 of the Agreement, the termination of the O/A Agreement terminated the Debtor's license to use the March Plans.
The Debtor reads Sentence # 1 to provide that ownership of work documents prepared by Ewing (such as the March Plans) passes to the owner as soon as the Debtor has paid the invoice for the services that produced those documents and that the vesting of ownership pursuant to Sentence # 1 is unaffected if the owner subsequently default in its payment obligations under the Agreement. Here, because Debtor paid all of Ewing's invoices that were related to the preparation of the March Plans, the Debtor argues that it owns those Plans. The Debtor acknowledges that it did not pay all of the invoices for services Ewing provided, inter alia, in revising the March Plans and therefore, claims no ownership interest in those revisions.21 The Debtor argues that its payment default after April 27, 2010 has no effect on its ownership of the March Plans.
B.
The O/A Agreement provides that it is governed by and is to be construed under Pennsylvania law. (O/A Agreement §§ 1.3.5.2, 1.3.7.1). Last year, in In re Stuart, 402 B.R. 111 (Bankr. E.D.Pa.2009), I had occasion to summarize certain cardinal principles of contract interpretation in Pennsylvania. For the sake of brevity, I can distill that general discussion down to three principles that are applicable in the present matter:
1. The meaning of an unambiguous written contract must be determined by its contents alone without resort to extrinsic aids or evidence.
2. A term is ambiguous if it is reasonably susceptible to different meanings and in evaluating whether a term is ambiguous, the term should be give its plain and ordinary meaning.22
3. If a contract provision is ambiguous, two consequences follow. First, the meaning of the provisions is an issue of fact to be determined by the factfinder, rather than an issue of law. Second, the parties may offer extrinsic evidence to clarify the meaning of the ambiguity.
Stuart, 402 B.R. at 127-28 ( & authorities cited therein).23
C.
At the beginning of the First Hearing, I ruled that § 1.3.2.1 of the O/A Agreement is ambiguous and therefore, that the parties could offer extrinsic evidence to assist in clarifying its meaning. I adhere to that view.
Standing alone, Sentence # 1 is clear. It provides that the Debtor becomes the owner of the Instruments of Service (which include what I have been calling "the Plans") as soon as the Debtor has paid for them. Viewed in isolation, Sentence # 1 provides a comprehensive rule for determining when ownership passes. Based on this principle, at every stage of their contractual relationship the parties would know, with some degree of certainty,24 whether a set of Plans is owned by the Debtor or by Ewing.
To be clear and complete on the subject of the passage of ownership, the Agreement need not have stated anything further after Sentence # 1. But the Agreement does say more. Sentence # 2 immediately follows Sentence # 1 and addresses the same subject, i.e., when ownership of the Plans passes to the Debtor. Sentence # 2 then states a different rule: that ownership of the Plans passes to the Debtor, not after payment for the discrete set of services rendered that are related to the creation of particular work documents, but only upon completion of all of the payments due Ewing under the entire Agreement, i.e., ownership passes at the end of the project after the Debtor has fully performed its entire payment obligation under the O/A Agreement.25 Just as Sentence # 1, standing alone, provides a clear and complete rule for the timing of the passage of ownership of the Plans to the Debtor, so too does Sentence # 2, standing alone.
The problems created by the juxtaposition of these two sentences are: (1) Sentence # 2 states a different rule that conflicts with Sentence # 1 and (2) neither sentence can be applied on its own terms without negating the other or rendering the other surplusage. See generally Restatement § 203(a) (favoring interpretation that give effect to all contract terms over interpretation that does not).
Ewing has presented no argument to harmonize the two sentences. The Debtor, however, argues that the two sentences can be harmonized because they address different time periods in the contractual relationship. Therefore, the Debtor suggests that there is no ambiguity in § 1.3.2.1.
According to the Debtor, Sentence # 1 is clear and specific and because, by its terms, the conditions for passage of ownership of the March Plans have occurred (i.e., payment), the court need not analyze the contract any further. As for Sentence # 2, the Debtor implies that it serves as a kind of residuary provision that comes into play at the end of the contract, providing for the transfer of any work documents that were not previously transferred to the Debtor pursuant to Sentence # 1.
While perhaps a cursory reading of the two sentences at issue may support the Debtor's position, upon closer examination of the text, the argument does not hold up. The flaw is that if, at the end of the contract, any work documents exist that have not yet been paid for (and therefore, are still owned by Ewing), the final payment by the Debtor under the contract that purportedly would trigger the asserted "residuary" effect of Sentence # 2 would also effectuate the transfer or ownership under Sentence # 1. In other words, based on the Debtor's final payment, the last set of plans still owned by Ewing would pass to the Debtor under Sentence # 1, even if Sentence # 2 did not exist. Thus, the Debtor's suggested interpretation gives Sentence # 2 no independent meaning. There is no residuary effect; if Sentence # 1 is given effect, Sentence # 2 adds nothing to Sentence # 1. Moreover, if Sentence # 2 is read to mean that no Plans pass to the Debtor until payment in full of the Debtor's entire payment obligation under the Agreement, then Sentence # 1 completely negates Sentence # 2.
To summarize, read independently, each of the two sentences is clear. When put together in succession in the same contract provision, Sentence # 2 negates Sentence # 1, while Sentence # 1, at best, renders Sentence # 2 superfluous and, at worst, negates it. Due to this conflict, § 1.3.2.1 is an ambiguous contract provision. See Com., Dept. of Transp. v. Gramar Const. Co., 71 Pa.Cmwlth. 481, 454 A.2d 1205, 1207 (1983) (conflicting provisions support conclusion that contract is ambiguous); see also United Rentals, Inc. v. RAM Holdings, Inc., 937 A.2d 810, 813 (Del.Ch.2007) (same).
D.
Faced with an ambiguous contract provision, a court may consider extrinsic evidence in interpreting the meaning of the provision. Unfortunately, the extrinsic evidence in the record provides no meaningful assistance in determining the parties' intentions with respect to the issue at hand.
It is obvious from the revisions to § 1.3.2.1 that the parties intended to change the Form O/A Agreement, which, untouched, would have left ownership of the Plans with Ewing. But there was no testimony at the First Hearing of any negotiations regarding when ownership would pass or why the particular language added to § 1.3.2.1 was chosen.
Also, while there was some evidence presented regarding custom and usage in the industry, it too, did not address the precise issue before the court. The testimony offered suggested only that architects frequently agree to modify § 1.3.2.1. to permit ownership of the Instruments of Service to pass to the property owner. However, there was no testimony suggesting that any custom or usage exists regarding when such ownership passes, i.e., whether it will pass in the midst of the construction project on a "pay and own as you go" basis or only when the owner's entire payment obligation has been satisfied.
E.
Another tool a court may use to ascertain the meaning of an ambiguous contract term is to search for textual clues elsewhere in the O/A Agreement, outside of Sentence # 1 and Sentence # 2. Unfortunately (again), this exercise does not yield an answer.
1.
To bolster their respective interpretations of § 1.3.2.1, both parties claim to find support in the next provision of the Agreement, § 1.3.2.2. Generally speaking, in § 1.3.2.2, Ewing grants the Debtor a license to use the Plans in connection with the Courthouse Project. The grant of the license necessarily is premised on the assumption that Ewing owns the licensed Plans. The provision also provides for the termination of the license in certain circumstances prior to the completion of the Courthouse Project.
During the hearing, the Debtor pointed to Sentence # 1 of § 1.3.2.2 (which in the context of this Memorandum, I will refer to as "Sentence # 3").26 Sentence # 3 states:
Sentence # 3
Upon execution of this Agreement, and during the period that Ownership of the Instruments of Service remain with the Architect, the Architect grants to the Owner a nonexclusive license to reproduce the Architect's Instruments of Service solely for purposes of constructing, using and maintaining the Project, provided that the Owner shall comply with all obligations, including prompt payment of all sums when due, under this Agreement.27
The Debtor maintains that the addition of the phrase "during [the] period that Ownership of the Instruments of Service remain with the Architect" to the Form O/A Agreement is instructive. The Debtor suggests that use of this phrase is consistent with Sentence # 1 and its inclusion manifests the parties' implicit recognition that there may be circumstances throughout the course of the O/A Agreement that ownership of the Plans will not remain with Ewing.
However, I find Ewing's response on this issue blunts the force of the Debtor's argument. As Ewing points out, this language added to § 1.3.2.2 was only one of a number of changes and additions to the Form O/A Agreement. Prior to the changes in § 1.3.2.1 and § 1.3.2.2, there were no circumstances in which § 1.3.2.1 provided for ownership of the Plans to pass from the architect to the owner; the architect retained the ownership rights in perpetuity. Therefore, in its original form in § 1.3.2.2 of the Form O/A Agreement, Sentence # 3 provided that upon execution, the architect granted the owner a license to use the plans in order to construct the project, subject to certain subsequent events that might result in termination of the license. There was no reference in "old" § 1.3.2.2 to any period of time that the Plans remained with Ewing because such a reference was unnecessary; the Plans always remained with Ewing. Ewing contends that the additional language added to Sentence # 3 simply serves to clarify that the license arrangement need be in place only during those periods in which Ewing, and not the Debtor, owns the Plans.
I agree with Ewing's main point on this issue. While the additional phrase in Sentence # 3 certainly recognizes that ownership of the Plans may pass from Ewing to the Debtor, it does not speak to the question of when the ownership will pass. Sentence # 3 can be read to complement Sentence # 2 just as much as it complements Sentence # 1. Therefore, it does not assist in the interpretation of § 1.3.2.1 of the Agreement.28
2.
Ewing too, comes up short in its effort to find textual support for its interpretation of § 1.3.2.1 in § 1.3.2.2 of the Agreement.
Ewing argues that the following two consecutive sentences in § 1.3.2.2 (referred to as "Sentence # 4" and "Sentence # 5") demonstrate the parties' intent that ownership of the Plans would pass to the Debtor only after full payment under the O/A Agreement:
Sentence # 4
Any termination of this Agreement prior to completion of the Project shall terminate this license.
Sentence # 5
Upon such termination, [the Debtor] shall refrain from making further reproductions of Instruments of Service and shall return to [Ewing] within seven days of termination all originals and reproductions in [the Debtor's] possession or control, (emphasis added).
Based on the emphasized language of Sentence # 5, particularly the word "all," Ewing suggests that these two sentences reflect the parties' understanding that any termination of the Agreement before both parties have fully performed would result in the Debtor's return of all Plans in the Debtor's possession, thus implying that all of the Plans remained property of Ewing (subject to the license granted to the Debtor) until the completion of the Courthouse Project.
The Debtor responds by pointing out that the word "all" in Sentence # 5 modifies "originals and reproductions," not Instruments of Service. Thus, according to the Debtor,
"Instruments of Service" is the antecedent of "all originals and reproductions." [The phrase] "all originals and reproductions" is merely a subset of "Instruments and Service." The meaning of the phrase "Instruments of Service" is the real question. It is not informed by the phrase "all originals and reproductions."
Debtor's Memorandum at 2.
I agree with the Debtor on this point. The purpose of Sentence # 5 is to impose certain obligations on the Debtor, after termination of the Agreement, with respect to the Plans or other documents in which the Debtor previously held a license. Sentence # 5 merely points out that if the termination occurs and the Debtor's license is terminated, the Debtor's duty is comprehensive with respect to those "licensed" documents that the Debtor has the duty to return to Ewing. If, however, as the Debtor contends, ownership of certain Plans has already passed to the Debtor pursuant to Sentence # 1, then Sentence # 5 is irrelevant because the Plans are not subject to the license; they are owned outright by the Debtor. In short, Sentence # 5 is as consistent with Sentence # 1 as with Sentence # 2.
F.
Ewing argues that the doctrine of contra proferentem (construe against the drafter) should be applied in this case and that the ambiguity in § 1.3.2.1 in the O/A Agreement be construed against the Debtor.
In Pennsylvania, the doctrine of contra proferentem is a rule of policy, not one of contract interpretation:
The rule is not actually one of interpretation, because its application does not assist in determining the meaning that the two parties gave to the words, or even the meaning that a reasonable person would have assigned to the language used. It is chiefly a rule of policy, generally favoring the underdog. It directs the court to choose between two or more possible reasonable meanings on the basis of their legal operation, i.e., whether they favor the drafter or the other party.
Stuart, 402 B.R. at 132 (quoting 5 Arthur L. Corbin & Margaret N. Kniffin, Corbin on Contracts § 24.27 (rev. ed.2007)).
The Pennsylvania Supreme Court has cautioned that the doctrine is to be applied only in limited situations.
[T]he rule is not intended as a talismanic solution to the construction of ambiguous language.... Where a document is found to be ambiguous, inquiry should always be made into the circumstances surrounding the execution of the document in an effort to clarify the meaning that the parties sought to express in the language which they chose. It is only when such an inquiry fails to clarify the ambiguity that the rule of construction relied upon by the chancellor should be used to conclude the matter against that party responsible for the ambiguity, the drafter of the document.
Stuart, 402 B.R. at 133 (quoting Burns Mfg. Co. v. Boehm, 467 Pa. 307, 356 A.2d 763, 767 n. 3 (1976) (citations omitted)). For the reasons expressed in Boehm, the doctrine also has been described as a "rule of last resort" or a "tie breaker," invoked when no other sound basis exists for choosing one contract interpretation over another. Stuart, 402 B.R. at 133 (quoting Gardiner, Kamya & Assocs., P.C. v. Jackson, 467 F.3d 1348, 1353 (Fed.Cir.2006)).
In the circumstances presented here, I find it appropriate to apply the doctrine of contra proferentem. Because I have concluded that neither a textual examination of the O/A Agreement nor the extrinsic evidence presented by the parties clarifies the parties' intentions with respect to the point in time that ownership of the March Plans was to pass from Ewing to the Debtor, I find it necessary, as a last resort, to invoke the doctrine of contra proferentem and construe the ambiguity in § 1.3.2.1 of the O/A Agreement against the drafter.
Further, as a policy matter, I find it equitable in the present circumstances to apply the doctrine.
Presumably, the starting point in the parties' negotiations, was § 1.3.2.1 of the Form O/A Agreement, which provided for ownership of all Plans to remain with Ewing. There is no dispute that parties agreed to modify § 1.3.2.1 to provide for ownership to vest in the Debtor under certain conditions. Undoubtedly, this change was made at the Debtor's request. Ewing acceded to the Debtor's request, agreeing in principle to relinquish ownership of the Plans upon certain conditions. I have no specific information regarding the process that led to this meeting of minds;29 I know only that the final language was drafted by the Debtor's representative.
It strikes me as appropriate to construe the contract ambiguity against the Debtor because it was the Debtor that both requested the change in the prior status quo (i.e., that requested that the version § 1.3.2.1 found in the Form O/A Agreement be modified) and drafted the ambiguous language to effectuate that change. As between the two parties, it seems reasonable to impose on the Debtor (as both the party moving to modify the form contract and the drafter of the proposed revision) the responsibility to express clearly the degree to which it was proposing to alter the status quo. This analysis finds support in the Restatement:
Where one party chooses the terms of a contract, he is likely to provide more carefully for the protection of his own interests than for those of the other party. He is also more likely than the other party to have reason to know of uncertainties of meaning. Indeed, he may leave meaning deliberately obscure, intending to decide at a later date what meaning to assert. In cases of doubt, therefore, so long as other factors are not decisive, there is substantial reason for preferring the meaning of the other party.
Restatement § 206 cmt. a.
For these reasons, and there being no dispute that the ambiguous language in the O/A Agreement at issue was drafted by the Debtor's representative, I will construe the ambiguity against the Debtor.
G.
I write further only to clarify briefly the reach of this decision.
The only matter being determined is Ewing's request for relief from the automatic stay. Ewing asserts that, to the extent the automatic stay even applies, "cause" for relief from the automatic stay exists under § 362(d) because Ewing, not the Debtor, is the owner of the Plans. As the Debtor pointed out in its Motion to Strike, see Part II, supra, Ewing's request for relief requires a determination regarding the existence and the extent of each party's asserted property interest in the March Plans.
Arguably, a definitive adjudication on the issue of ownership of the March Plans requires the initiation of an adversary proceeding. See Fed. R. Bankr.P. 7001(2), (9).30 But see In re ExpressTrak, L.L.C., 2004 WL 3735126, at *3 (Bankr.E.D.Mich. Jan. 20, 2004) (based on text of Rule 7001(9), suggesting that not every type of request for declaratory relief requires the initiation of an adversary proceeding). However, the mere fact that the merits of a dispute regarding ownership of an asset in which the bankruptcy estate claims an interest is relevant in determining the merits of a motion for relief from the automatic stay is not, by itself, grounds to deny the motion or to compel the movant to seek stay relief by way of adversary complaint.
The Bankruptcy Code mandates that stay relief hearings relating to a creditor's interest in property be heard expeditiously, see 11 U.S.C. § 362(e). Accordingly, such hearings are summary in nature.
The limited grounds set forth in the statutory language, read in the context of the overall scheme of § 362, and combined with the preliminary, summary nature of the relief from stay proceedings, have led most courts to find that such hearings do not involve a full adjudication on the merits of claims, defenses, or counterclaims....
In re Sunshine Three Real Estate Corp., 2009 WL 3617798, at *7 (Bankr.D.Mass. Oct.26, 2009).
How then should a court handle a stay relief motion that requires a determination that ordinarily would be resolved through a Rule 7001 adversary proceeding or some other proceeding (such as an objection to the movant's claim) that is less summary in nature than a motion for relief under § 362(d)?
In In re Nuclear Imaging Sys., Inc., 260 B.R. 724, 731 (Bankr.E.D.Pa.2000), the court suggested the following:
Given the need for summary treatment of lift stay motions, when a party opposes a motion of a creditor to terminate the stay and raises affirmative defenses to the validity of the claim itself, it may often be proper to require that the objector come forward during the lift stay hearing simply with sufficient evidence to demonstrate that there is a reasonable probability that the objector would prevail in later litigation which can completely determine those challenges to the claim.
Accord Sunshine Three Real Estate Corp., 2009 WL 3617798, at *8 ("To allow a relief from stay hearing to become any more extensive than a quick determination of whether a creditor has a colorable claim would turn the hearing into a fullscale adversary lawsuit ... and would be inconsistent with this procedural scheme"). In effect, the determinations made in a stay relief hearing are akin to those made in a preliminary injunction hearing.31
Applying the Nuclear Imaging Systems model to the case at hand, I have concluded that the Debtor is not likely to prevail in its position that it, rather than Ewing, owns the March Plans. Consequently, as the likely owner of the Plans, Ewing should be able to use and control those Plans. These findings establish that "cause" exists for relief from the automatic stay under 11 U.S.C. § 362(d)(1).
An order consistent with this Memorandum was entered on August 26, 2010.
ORDER
AND NOW, a Motion for Relief from the Automatic Stay having been filed by the First Judicial District of Pennsylvania ("the FJD Motion") (Doc. # 38);
AND, Ewing Cole, Inc. ("Ewing") having filed a Joinder to the FJD Motion (Doc. # 44);
AND, the parties having agreed to treat Ewing's Joinder as if it were a Motion for Relief from the Automatic Stay (hereinafter, the Joinder being referred to as "the Ewing Motion");
AND, a hearing on the Ewing Motion having been held and concluded on August 18, 2010;32
AND, upon consideration of the evidence presented and the arguments of counsel;
It is hereby ORDERED that:
1. The Ewing Motion is GRANTED.
2. To the extent that the automatic stay, 11 U.S.C. § 362(a), applies, Ewing is GRANTED RELIEF FROM THE AUTOMATIC STAY, for cause, see 11 U.S.C. § 362(d)(1), to use or control or otherwise exercise ownership rights with respect to the "Instruments of Service," as that term is defined in § 1.3.2.1 of the April 7, 2009 contract between Ewing and the Debtor.