J. CURTIS JOYNER, District Judge.
Presently before the Court are Defendant's Motion for Summary Judgment, (Def. Motion for Summary Judgment, Doc. No. 12) and Plaintiff's Motion for Partial Summary Judgment, (Pl. Motion for Partial Summary Judgment, Doc. No. 13). For the reasons that follow, the Motions will be granted in part and denied in part.
Plaintiff Allegheny Construction Group, Inc. ("ACG") brings claims against Walsh Heery Joint Venture ("WHJV"). (Pl. Complaint, Doc. No. 1.) Plaintiff alleges breach of contract and violation of Pennsylvania's Prompt Pay Act ("PPA") 62 Pa.C.S.A. § 3901,
The following facts are undisputed: The Commonwealth Department of General Services ("DGS") hired Defendant to complete a construction project ("Project"). (
Plaintiff claims that, according to DGS, Defendant is at least partially responsible for the delay. (Doc. No. 13-1 at 2.) Plaintiff contends that, because Plaintiff has satisfactorily completed its work under the subcontract and because Defendant, not Plaintiff, caused the delay, Defendant has breached the subcontract and the PPA by refusing to pay the retainage to Plaintiff. (
Defendant avers that, because DGS has not yet paid Defendant, (Doc. No. 13-1 at 3; Doc. No. 15-5 ¶8), and because Defendant did not cause the delay, (Doc. No. 15-5 ¶7), Defendant is rightfully withholding the retainage from Plaintiff. (Doc. No. 15-1 at 2.)
Lastly, the parties dispute the proper retainage amount. (Doc. No. 13-1 at 4, 19-22; Doc. No. 15-1 at 14-15.)
Subject matter jurisdiction in this case is proper under 28 U.S.C. § 1332(a)(1), as Plaintiff and Defendant are citizens of different states and the amount in controversy exceeds $75,000. § 1332(a)(1). Because Defendant has litigated the merits of its claim without contesting personal jurisdiction, we may exercise personal jurisdiction over Defendant.
To obtain summary judgment, a movant must show "that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a). Disputes about "material" facts are those that "might affect the outcome of the suit under the governing law."
Once the movant meets its initial burden, the nonmoving party must then "go beyond the pleadings and come forward with specific facts showing that there is a genuine issue for trial."
"The court must review the record `taken as a whole.'"
Still, the non-movant must show more than "[t]he mere existence of a scintilla of evidence in support of . . . [the non-movant's] position" to defeat a motion for summary judgment.
In a prior case involving similar facts and the same Defendant as here, a subcontractor plaintiff sued Defendant for failing to pay a retainage.
Here, Plaintiff argues that collateral estoppel precludes Defendant from relying on the prevention doctrine in this case.
Though a pay-if-paid clause creates a condition precedent to payment, a party that frustrated occurrence of the underlying payment may not rely on a pay-if-paid clause to avoid its payment obligation.
Though deliberate frustration certainly bars reliance on a pay-if-paid clause, inadvertent acts can sometimes constitute frustration precluding reliance on the clause.
In correspondence from DGS to Defendant, DGS highlighted concerns about Defendant's performance and indicated that Defendant's deficiencies contributed to delaying the Project. (Doc. No. 13, Ex. B, December 22, 2016 DGS Letter; Doc. No. 13, Ex. C, January 18, 2017 DGS Letter.) The record sufficiently establishes that Defendant was at least partially responsible for the Project delay. (Doc. No. 13, Exs. B, C;
Therefore, we need not address whether collateral estoppel precludes Defendant from relying on the pay-if-paid clause in this proceeding.
The parties agree that the contested laydown yard backcharge is for the cost of remediating the laydown yard. (Doc. No. 13-1; Doc. No. 15-1 at 5.) The parties also agree that Plaintiff did not perform the laydown yard work. (Doc. No. 13-1 at 20-21; Doc. No. 15-1 at 5.) The parties do not assert that Plaintiff was ultimately responsible for performing the laydown yard remediation. (
However, the parties disagree on whether Defendant has already compensated Plaintiff or otherwise accounted for the uncompleted laydown yard remediation and, thus, whether Defendant should adjust the retainage to reflect remuneration for the laydown yard subproject. (Doc. No. 13-1 at 21; Doc. No. 15-1 at 5.) Plaintiff asserts that Defendant, in calculating the retainage payment, should not reduce the retainage to factor in a laydown yard payment because, Plaintiff avers, Defendant has not compensated Plaintiff for the laydown yard remediation. (Doc. No. 13-1 at 21.) In calculating the retainage, Defendant claims a credit, or deduction, measured by what Defendant would have paid Plaintiff had Plaintiff completed the laydown yard remediation. (Doc. No. 15-1 at 5.) Specifically, Defendant argues that, to avoid paying Plaintiff for work that Plaintiff did not perform, Defendant "is deducting from any funds due to Allegheny a credit for the work," (
We find that there is a material dispute of fact as to whether Defendant has already compensated Plaintiff for the uncompleted layback yard remediation. (Doc. No. 13-1 at 21; Doc. No. 15-1 at 5.) Thus, because factual issues preclude determining whether the retainage payment should factor in the layback yard subproject, we deny both Defendant's and Plaintiff's summary judgment motions as to the laydown yard backcharge.
The subcontract requires subcontractors to keep the worksite clean and authorizes Defendant to assess clean-up costs if a subcontractor fails to begin cleaning the site within twenty-four hours after Defendant provides written notice to the subcontractor that the subcontractor is out of compliance with the clean-up provision. (Doc. No. 13, Ex. A, Art. 6.4, Subcontract.)
Though Defendant eventually charged Plaintiff for clean-up costs, (Doc. No. 13, Ex. O, February 11, 2015 Letter from Defendant), it is unclear whether Defendant properly notified Plaintiff of Plaintiff's purported noncompliance before assessing charges. (Doc. No. 13-1 at 21-22; Doc. No. 15-1 at 6; Doc. No. 13, Ex. O.)
We find that there is a material dispute of fact over whether Defendant provided notice to Plaintiff specifically before assessing the clean-up backcharge. (Doc. No. 13-1 at 22; Doc. No. 15-1 at 6; Doc. No. 13, Ex. O.) Thus, we deny the summary judgment motions as to the clean-up backcharge.
Under Pennsylvania law, the elements for a breach of contract action are: (1) "`the existence of a contract . . .; (2) a breach of duty imposed by the contract; and (3) resultant damages.'"
Here, it is undisputed that there is a subcontract. (Doc. No. 1 ¶7; Doc. No. 13, Ex. A; Doc. No. 12-5 ¶3.) Additionally, the subcontract imposed on Defendant a duty to pay the retainage to Plaintiff, and Defendant has failed to pay the retainage for Plaintiff's performance. (
As to damages, though the parties disagree on the amount of backcharge owed, (Doc. No. 13-1 at 21-22; Doc. No. 15-1 at 5, 6), the parties agree that Defendant has not paid the retainage, (Doc. No. 13-1 at 4; Doc. No. 15-5 ¶9).
Thus, setting aside the disputed backcharges, Defendant has breached the subcontract as to the retainage for Plaintiff's completed work. Accordingly, we deny Defendant's Motion for Summary Judgment on Count I. We grant Plaintiff's Motion for Partial Summary Judgment on the breach of contract claim but deny Plaintiff's Motion as to the disputed backcharges.
As is relevant here, the PPA applies to construction contracts and subcontracts for projects by Pennsylvania governmental agencies,
The PPA requires a contractor to pay a subcontractor upon performance by the subcontractor.
Here, it is undisputed that Defendant has not fully compensated Plaintiff for performance of the subcontract. (Doc. No. 13-1 at 3-4; Doc. No. 12-5 ¶9.) Thus, regarding the work aside from the backcharges, we find no disputes of material facts as to PPA liability. Accordingly, we hold that Defendant has violated the PPA. Because there are material disputes of fact as to the backcharges, we decline to determine at the summary judgment stage whether Defendant has violated the PPA regarding the disputed backcharges.
Under the PPA, the Court may grant interest, penalties, and attorney fees.
According, we grant Plaintiff's Motion as to liability under the PPA and deny Defendant's Motion as to PPA liability. We deny both summary judgment motions as to interest, penalties, and attorney fees under the PPA.
Under Pennsylvania law, a Court may not find unjust enrichment when an express contract governs the parties' relationship.
Here, it is undisputed that the subcontract covers the parties' relationship. (Doc. No. 12-5 ¶3; Doc. No. 13-1 at 3; Doc. No. 13, Ex. A.) Thus, we deny Plaintiff's Motion and grant Defendant's Motion as to Count III.
Under Pennsylvania law, quantum meruit is unavailable when a contract establishes the value of the services provided under the contract.
Here, the subcontract contains numerous payment provisions that govern the value of services provided under the subcontract. (Doc. No. 13, Ex. A, Art. 3.) Thus, Plaintiff cannot recover under a quantum meruit theory. As to Count VI, we deny Plaintiff's Motion for Partial Summary Judgment and grant Defendant's Motion for Summary Judgment.
We deny Defendant's Motion for Summary Judgment on Count I and Count II and grant said Motion as to Counts III and VI. We deny Plaintiff's Motion for Partial Summary Judgment as to Count I on the disputed backcharges but otherwise grant Plaintiff's Motion as to Count I. We grant Plaintiff's Motion for Partial Summary Judgment as to Count II on PPA liability. We deny Plaintiff's Motion for Partial Summary Judgment as to Counts III and VI. We grant a hearing to determine the appropriate amount of damages and whether, under the PPA, interest, penalties, and attorney fees are proper. An appropriate Order follows.