Cathy Bissoon, United States District Judge.
Pending before the Court are a motion for summary judgment (Doc. 36) filed by Plaintiffs Equitrans Services LLC and Equitrans Investments, LLC, trading as Equitrans, LP (collectively, "Equitrans") and a cross-motion for partial summary judgment (Doc. 40) filed by Defendant Precision Pipeline ("Precision"). For the reasons that follow, the parties' motions will be granted in part and denied in part.
This civil action arises from a contractual dispute concerning a pipeline construction project known as the "Sunrise Project" (hereafter, the "Project"). The Project involved the construction of approximately 45 miles of natural gas pipeline through Green County, Pennsylvania and Wetzel County, West Virginia. (DSMF at ¶ 1.)
In June 2011, the parties entered into a contract relative to the Project (hereafter, the "Contract"), pursuant to which Equitrans agreed to pay Precision an estimated base contract price of $75,358,176.54 for its construction of the pipeline. (
The dispute in this case centers primarily on the meaning and application of certain warranty and indemnification provisions in the Contract. One key warranty provision is Section 8.1 of the MSA, entitled "Warranty of Work," which states:
(Def.'s Ex. 8-19, Doc. 43-8.) Another key warranty provision is Article 64 of the Project Specifications, wherein Precision warranted its earthwork as follows:
(Def.'s Ex. 8-25, p. 52, Doc. 43-10 (emphasis in the original).) Of potential relevance to these warranty obligations is Section 9.7 of the MSA, "Quality of Work," which states:
(Def.'s Ex. 8-19, Doc. 43-8.)
Precision also assumed the following indemnity obligations pursuant to Section 12.1 of the MSA:
(Def.'s Ex. 8-19, Doc. 43-8.)
It is undisputed that, following the completion of construction, twenty-nine (29) slides occurred along parts of the right-of-way that Equitrans had obtained for construction of the pipeline. (DSMF at ¶ 19.) Equitrans notified Precision of these occurrences and demanded that the slides be repaired. (PSMF at ¶¶ 43, 45.)
Equitrans alleges that it provided road bonds to municipalities and local government agencies in order for Precision to utilize certain public roads in connection with its work. (Compl. at ¶ 19, Doc. 1-2.) According to Equitrans, PennDOT and the municipalities demanded that the roads be restored to their pre-construction condition before Equitrans would be released from its road bonds. (
Pursuant to the EQT Pipeline Construction Standard — an element of the parties' Contract, Precision agreed that: "Contractor shall be responsible for maintaining and repairing existing roads such that the condition of the road after construction equals the condition of the road prior to construction." (PSMF at ¶ 79; Pl.s' Ex. O at p. 2121, § 2.2, bullet point 4, Doc. 39-8.) In accordance with the Project Specifications, Precision was required to produce both a pre-construction video of the access roads it would utilize on the Project, capturing their pre-existing conditions, and a post-construction video documenting the as-left condition of the right of way, ancillary sites and access roads restored by Precision. (PSMF at ¶¶ 60-61; Pl's Ex. M at §§ 19 and 56, Doc. 39-8.)
Precision viewed its obligation under these provisions as requiring it to pay for any road damage that it had caused, but not requiring it to pay for road damage caused by others. (PSMF at ¶ 74.) After paying over $1,000,000 toward road repairs, Precision advised Equitrans that it believed these payments had fulfilled its contractual obligations. (
In June 2013, Equitrans and Precision entered into a Settlement Agreement and Release ("Settlement Agreement") in an
Equitrans commenced this lawsuit on November 13, 2013, by filing its complaint in the Allegheny County Court of Common Pleas. (
The complaints sets forth three causes of action sounding in: breach of contract (Count I); breach of warranty (Count II); and breach of indemnity obligations (Count III). (
Precision argues that Equitrans's claims for breach of contract and breach of warranty fail because (1) Precision only warranted against defects in its materials or workmanship and (2) as to all but two of the slides, Equitrans has failed to present evidence sufficient to show that Precision's defective materials or workmanship (as opposed to Equitrans's defective design) caused the slides. As to Equitrans's indemnity claim, Precision argues that the language of the indemnity clause expressly limits Equitrans to recovering its losses on third-party claims and such losses have not been demonstrated. Precision further argues that certain of Equitrans's alleged damages were waived by the June 2013 Settlement Agreement.
At the heart of this case lies a dispute about the parties' respective rights and obligations under the Contract. Under Pennsylvania law,
Of some relevance here is the fact that the parties' Contract contains an integration clause. (
A contract is ambiguous if it "`is reasonably or fairly susceptible of different constructions and is capable of being understood in more senses than one and is obscure in meaning through indefiniteness of expression or has a double meaning.'"
For purposes of its summary judgment motion, Equitrans defines its breach of contract claim in terms of five separate breaches — namely, Precision's: (1) failure to comply with its warranty obligations; (2) refusal to indemnify Equitrans for losses arising out of Precision's work; (3) commencement of work despite having failed to familiarize itself with the conditions affecting construction; (4) representation to
Items (3) and (4) are based on Equitrans's interpretations of Sections 9.3 and 9.7 of the MSA and portions of Precision's April 8, 2011, proposal for the Project (Pl.'s Ex. P, Doc. 39-9.) According to Equitrans, these various provisions set forth Precision's "clear and undisputed duties under the Contract" (Pl.'s Mem. Supp. Mot. Summ. J. at 6, Doc. 37), whereby Precision:
(
(Pl.'s Mem. Supp. Mot. Summ. J. at 7, Doc. 37.)
Preliminarily, the Court concludes that, although these provisions may have relevance in the context of Equitrans's breach of warranty claim, they cannot form the basis of an independent breach of contract claim, because the parties' June 2013 Settlement Agreement effectuated a release of Equitrans's then-existing claims, other
Based on the unambiguous language of the Settlement Agreement, it is clear that the parties intended to release any breach of contract claims, other than those for alleged breaches of warranty or indemnity obligations, that existed as of the date of the Settlement Agreement. Accordingly, judgment for Precision is appropriate to the extent Equitrans is asserting non-warranty breach of contract claims based on: (a) Precision's failure to familiarize itself with the conditions affecting construction prior to commencing its work and/or (b) Precision's "representation" to Equitrans, by commencing and proceeding with the work, that it "accepted" the surface and subsurface conditions of the Project site.
Equitrans also bases its breach of contract claim on Precision's failure to restore roads that were bonded by Equitrans for Precision's use. Precision argues that certain aspects of Equitrans's damages claim in this regard are barred by the June 2013 Settlement Agreement. In particular, Precision challenges Equitrans's requests for damages relative to, among other things, road repair work that was completed and invoiced by Pennoni & Associates, Inc. ("Pennoni") prior to the date of the Settlement Agreement. As the Court discusses in more detail below in connection with Equitrans's indemnity claim, it is not clear from the present state of the record the extent to which these "Pennoni Claims" form the basis of Equitrans's third-party indemnity claims, which presumably were not waived by the Settlement Agreement. Consequently, to the extent Precision is
Following the completion of the pipeline's construction, twenty-nine (29) slides occurred along parts of the right-of-way that Equitrans had obtained for purposes of the construction. (DSMF at ¶ 19.) In Count II of the Complaint, Equitrans alleged that Precision has "breached its warranty obligations by failing to repair the slope failures when notified of the same...." (Compl. at ¶ 40.)
Equitrans's breach of warranty claim is based on MSA Section 8.1 and Article 64 of the Project Specifications. With regard to MSA Section 8.1, Equitrans interprets this provision as encompassing two separate warranties. The first sentence states that "Contractor warrants its Work against all deficiencies and defects in materials and/or workmanship and as required for [sic] in the Contract Documents." (MSA at § 8.1, Def.'s Ex. 8-19, Doc. 43-8.) Equitrans interprets this sentence as a promise by Precision that there will not be any defects or deficiencies in its workmanship or its materials, without any reference to a time limitation. The second sentence of Section 8.1 states that "Contractor shall guaranty or warrant its Work for a period of one (1) year from the date of substantial completion of its Work." (
Article 64 of the Specifications states that the "Contractor shall warrant all earthwork for a period of fifteen (15) months after the retention has been accepted," and "[e]arthwork shall cover all trench subsidence, any slips or slides and excessive erosion attributable to the improper installation of erosion control devices." (Project Specification Art. 64, Def.'s Ex. 8-25, Doc. 43-10.) Equitrans maintains that, under the plain language of Article 64, "any" slip or slide constitutes a breach of Precision's earthwork warranty; thus, by refusing to repair the slope failures that occurred within the warranty time frame, Precision breached its warranties.
By contrast, Precision maintains that the warranty provisions in question apply only to defects in its workmanship and materials. Precision concedes that there are issues of fact as to whether defects in its workmanship were responsible for two of the "slides" at issue — namely, the Watson West slide at Milepost 8.57-8.64 ("Watson West") and the Marisa sinkhole at Milepost 10.13 (the "Marisa Sinkhole").
As for the other twenty-seven (27) slope failures, however, Precision maintains that there is no evidence to establish that these slides resulted from defects in its workmanship or materials. Precision contends
In his expert report submitted on behalf of Precision, Steven Pasternack, P.E., Ph. D., opines that the slope failures were caused by: (a) the pipeline being routed on overly steep slopes and (b) the rights-of-way being located over old landslides, active landslides, or soil and rock susceptible to landslides. (Pl.'s Ex. I, Doc. 39-5.) Precision maintains that, under the terms of the Contract, it was not responsible for these conditions. On the other hand, Equitrans's expert witness, Jon D. Raab, P.E., opined that the slope failures were attributable to Precision's workmanship, including its selection of inadequate means and methods to reconstruct stable slopes and its failure in some cases to use engineered stability measures. (Def.'s Ex. 8-67, Doc. 43-15.) Precision interprets Mr. Raab's report and testimony as establishing that, with regard to each of the 17 Disputed Slides, the slopes required additional engineered stability measures because they were steeper than a ratio of 2H:1V. Precision insists that it had no responsibility under the Contract for such measures and that all engineering and design responsibility for slide mitigation measures rested with Equitrans. Accordingly, Precision maintains that the record cannot support a finding of any warranty liability on its part relative to the seventeen Disputed Slides.
Precision's interpretation of MSA Section 8.1 and Article 64 as warranting only against defects in workmanship and materials holds some appeal. This Court is inclined to agree that the more logical interpretation of Section 8.1 is that the first sentence merely describes the breadth or scope of the warranty (i.e., a warranty against defects in materials and workmanship), while the second sentence describes its length (i.e., one year from substantial completion). To interpret the second sentence as a distinct, stand-alone warranty whereby Precision broadly guaranteed or warranted its work would render the first sentence's warranty against defects in workmanship superfluous. This would violate the fundamental principle of contract interpretation that every phrase of a contract should be given meaning and none should be treated as surplusage if any other construction of the contract is rationally possible.
Precision's proposed interpretation of MSA Section 8.1 is buttressed by the language in Article 64, which similarly appears to restrict Precision's earthwork warranty to issues of defective workmanship. Equitrans's assertion that Article 64 obligates Precision to repair "any slips or slides" irrespective of their cause ignores the last sentence of the provision, whereby Precision "agree[d] to remobilize to repair any earthwork or piping defect
Thus, the Court is inclined to agree with Precision that MSA Section 8.1 and Article 64 of the Specifications imply warranties related to workmanship, as opposed to an absolute warranty against slope failures irrespective of their cause. Nevertheless, even if the Court accepts Precision's interpretation of the warranty provisions as limiting its liability to defects in workmanship, this does not entirely end the matter, because the Court must consider what Precision's contractual "workmanship" responsibilities entailed. Fundamentally, the parties disagree concerning the extent to which the Contract imposed responsibility on Precision for ensuring adequate earthwork stabilization measures.
As to this issue, the Court perceives an ambiguity in the Contract which cannot be resolved as a matter of law at the summary judgment stage. Precision maintains that its only responsibilities under the Contract were to construct what Equitrans designed. To support its position, Precision points to the testimony of Equitrans's project manager and Equitrans's filings with the Federal Energy Regulatory Commission as evidence that Equitrans was responsible to design any necessary slide mitigation measures but failed to incorporate such measures into its design. Precision also interprets Mr. Raab's report and testimony as establishing that, with regard to each of the 17 Disputed Slides, the terrain required additional engineered stability measures beyond those that were incorporated into Equitrans's design. Precision insists that it cannot be held contractually liable for any defects in Equitrans's design, since it was obligated to adhere to that design.
On the other hand, Equitrans has produced some evidence supportive of its position that Precision assumed contractual responsibility relative to earthwork mitigation measures. As previously discussed, Section 9.7 of the MSA, entitled "Quality of Work," ostensibly obligated Precision to inspect all surfaces prior to commencing its work, immediately inform Equitrans of any "unacceptable" surface or subsurface conditions, and refrain from commencing work "until deficiencies and other surface/subsurface conditions that would adversely affect the integrity of
Precision argues that, under the "Spearin doctrine," Equitrans's impliedly warranted the suitability of its design specifications, and Equitrans cannot rely on "boilerplate" contractual provisions to shift responsibility to Precision for defects in Equitrans's design.
However, this doctrine only applies where the contractor relies on the owner's design specifications. Design specifications "describe in precise detail the materials to be employed and the manner in which the work is to be performed. The contractor has no discretion to deviate from the specifications, but is required to follow them as one would a road map."
Here, Equitrans argues that it did not provide any design specifications that specifically related to earthwork. Equitrans further contends that the construction "typicals" it provided in its FERC filings were in the nature of performance specifications and that Precision exercised substantial discretion in performing the earthwork. As noted, Article 45 of the Project Specifications addresses Precision's
In addition, the Court concludes that factual issues as to the cause of certain slope failures cannot be resolved as a matter of law at the summary judgment stage. Although Precision claims that Mr. Raab testified unequivocally that the lack of additional engineered stability measures were the ultimate cause of the slope failures at the seventeen Disputed Slides, the Court does not interpret Mr. Raab's testimony as completely unequivocal in this regard. In actuality, Mr. Raab opined that such measures were "likely" required for areas exceeding a 2H:1V slope, but this was not a "definitive threshold," and the need for additional measures would entail an individualized inquiry on a "case-by-case basis" depending on the degree to which a slope exceeded a 2H:1V ratio. (Raab Dep. at 99-102, Doc. 43-5.) Based on information obtained from Equitrans's project manager and the language of the Contract documents, Mr. Raab agreed that Precision assumed design responsibilities with regard to earthwork and recontouring (see Raab Report at 3-6, Doc. 43-15; Raab Dep. at 69, Doc. 50-5), and he opined that numerous workmanship issues caused or influence the instability at the Disputed Slides, including (among other things): the quality of the fill used at the various slide sites, the placement of additional fill over steep natural slopes, the placement of fill on steep slopes without appropriate benching, and inadequate control of groundwater and seepage. To the extent Mr. Raab's testimony contains internal inconsistencies or is contradicted by other evidence of record, these are matters for the fact-finder to assess in determining his credibility. Given the disputed expert opinion evidence concerning the cause of the seventeen Disputed Slides, the ambiguities in the Contract concerning Precision's responsibilities relative to earthwork mitigation design, and the highly technical nature of these inquiries, the Court is not in a position to resolve the pending cross-motions based on the current state of the record. Accordingly, the parties' cross motions for summary judgment will be denied relative to Count II of the Complaint insofar those motions relate to the seventeen Disputed Slides, the Watson West Slide, and the Marisa Sinkhole.
That having been said, the Court agrees with Precision that it is entitled to judgment relative to the remaining ten (10) slides designated as numbers "20 through (29)" in Precision's Exhibit 9 (Doc. 43-31) that occurred at the Shultz, Marling, Ankrom, Raymont, Tennant, Minor, Efaw, and Fairbanks properties as well as Mileposts 0.26-0.53 and 0.33 at Underwood property. The Court agrees that the cause of these slope failures is a matter involving specialized or technical knowledge as to which expert testimony is required. Because Equitrans failed to proffer any expert opinion as to the cause of these slides, and because the existing evidence of record is otherwise insufficient as a matter of law to establish that the cause of these slides was attributable to defects in Precision's
In Count III of the Complaint, Equitrans asserts a claim for breach of Precision's indemnity obligations arising out of its failure to indemnify Equitrans for certain repairs. (Compl. at ¶ 40.) In moving for summary judgment on this claim, Equitrans notes that, under Section 12.1 of the MSA, Precision is obligated to indemnify Equitrans for any "damages, ... losses,... costs and expenses" arising out of Precision's "Work or other performance under [the MSA] and/or attributable to ... "breach by Contractor of any representation or warranty" or "Contractor's failure to comply with any provision of [the MSA] or the Contract Documents." (MSA at § 12.1, Def.'s Ex. 8-19, Doc. No. 43-8.) Equitrans argues that, due to Precision's breach of its contractual obligation to perform slope repairs along the pipeline right-of-way, Equitrans incurred costs in securing the repairs itself. Consequently, Equitrans argues that it incurred "damages, losses, costs and expenses" due to Precision's "work" or other performance under the contract, entitling Equitrans to recover all "damages, losses, costs and expenses" (including attorney fees) resulting from the breach of Precision's indemnity obligations.
Precision maintains that the language of the MSA's indemnification clause clearly limits Precision's obligations to situations involving third-party claims. The undersigned finds this argument persuasive for a number of reasons.
First, Section 12.1 expressly requires Precision to "defend, indemnify, and hold [Equitrans] harmless" from and against "any claims, demands, causes of action, damages, liabilities, judgments, losses, fines, awards, penalties, costs and expenses, including attorneys' fees and other costs of defense..." Courts in this circuit have recognized that the terms "defend, indemnify, and hold harmless" indicate an intent to restrict indemnification obligations to third party claims.
Second, Section 12.1's reference to "claims, demands, causes of action, damages, liabilities, judgments, losses, fines, awards, penalties, costs and expenses, including attorneys' fees and other costs of defense" supports the conclusion that only third-party claims are covered by the provision. This is particularly true given the provision's reference to "other costs of defense," which appears to modify the prior list of items.
Third, Pennsylvania law requires that indemnity clauses be construed narrowly against the party seeking indemnification.
Finally, Precision correctly notes that certain other indemnity provisions in Article 12 of the MSA only make sense in the context of third-party claims.
That having been said, the Court notes that Equitrans maintains that it has valid third-party claims based on expenses it incurred to rectify slope failures and to make necessary road repairs. At the same time, Precision has challenged Equitrans's requests for damages relative to (i) certain road repair work completed and invoiced by Pennoni & Associates, Inc. ("Pennoni") prior to the date of the Settlement Agreement (hereafter, "Pennoni Claims"); and (ii) certain payments made to various landowners and townships as set forth under category "806" on Precision's Exhibit 70 (Def. Ex. 8-70, p.1, Doc. 43-17) ("Township & Landowner Claims"). Precision contends that most of the invoices documenting payments on the Pennoni Claims predated the Settlement Agreement and thereby are within the category of claims waived by Equitrans pursuant to Paragraphs 6 and 8 of the Settlement Agreement. Similarly, Precision argues that certain payments made by Equitrans to landowners Kathy and Timothy Fretts, as well as to Jefferson and Gilmore Townships, predate the Settlement Agreement and are among the claims waived by the Settlement Agreement. Precision acknowledges that these Township & Landowner Claims encompassed payments made for various reasons, including "road repair," "road maintenance," and "property damage," among other things. According to Precision, some or all of these payments constituted the
What is not presently clear from the record is the extent to which any of these alleged damages can legitimately form the basis of Equitrans's third-party indemnification claims. Although Paragraphs 6 and 8 of the Settlement Agreement released a broad category of then-existing claims, the agreement also expressly reserved Equitrans's right to pursue past and future warranty and indemnity claims. Because the Court perceives issues of fact relative to Equitrans's purported third-party claims that are not capable of disposition on the present record, the Court will not presently grant either party's motion for summary judgment relative to Count III insofar as it is premised on the Pennoni Claims or the Township & Landowner Claims.
Finally, the Court notes that Precision has challenged Equitrans's request for attorney fees. These fees appear to be an element of Equitrans's indemnity claim, since the indemnity clause provides the only apparent contractual basis for recovery of attorney's fees. Because the Court is declining to dispose of the indemnity claim definitively at the present time, however, it is premature to dispose of Equitrans's attorney fee request, and Precision's motion in that regard will therefore be denied.
In its responsive pleading (Doc. 6), Precision asserted counterclaims against Equitrans for breach of contract (Count I) and an alleged violation of Pennsylvania's Contractor and Subcontractor Payment Act, 73 P.S. §§ 501 et seq. (Count II). These claims are based on Paragraph 4 of the Settlement Agreement, pursuant to which Equitrans withheld $987,875.20 of the retainage and agreed to release same "after all warranty items have been addressed by Precision as provided by the Contract." (Settlement Agreement at ¶ 4, Def.'s Ex. 8-97, Doc. 43-28.)
In its counterclaims, Precision alleged that "all warranty items [had] been completed" and "no further warranty items could arise that would justify withholding the payment." (Countercl. at ¶ 10, Doc. 6.)
Equitrans has moved for summary judgment on both of Precision's counterclaims. Equitrans acknowledges that it refused to release the $987,875.20 retainer that was withheld under the terms of the June 2013 Settlement Agreement; however, it maintains that its actions were appropriate because Precision's refusal to repair the slides on the Project demonstrate that all "warranty items" have not been addressed.
In responding to Equitrans's motion, Precision did not address or otherwise attempt to defend its counterclaims. Consequently, the Court deems Equitrans' motion for summary judgment to be unopposed relative to Precision's two counterclaims, and judgment will be entered in Equitrans's favor accordingly.
Consistent with the foregoing, Equitrans's motion for summary judgment (Doc. 36) will be granted insofar as it
Precision's motion for partial summary judgment (Doc. 40) will be granted with respect to the breach of contract claims asserted in Count I of the Complaint that are not founded on breach of warranty or indemnity theories. With respect to the breach of warranty claim in Count II of the Complaint, Precision's motion will be granted as to the slides numbered "20" through "29" in Precision's Exhibit 9 (Doc. 43-31) and pertaining to the Shultz, Marling, Ankrom, Raymont, Tennant, Minor, Efaw, and Fairbanks properties as well as Mileposts 0.26-0.53 and 0.33 at Underwood property. With respect to the indemnity claim in Count III of the Complaint, Precision's motion will be granted as to all claims premised exclusively on Equitrans's first party losses and/or any losses incurred relative to the aforementioned slides numbered "20" through "29" in Precision's Exhibit 9 (Doc. 43-31). In all other respects, Precision's motion for partial summary judgment will be denied.