PEDRO A. DELGADO HERNÁNDEZ, District Judge.
This is a breach-of-contract action derived from two municipal construction projects and a subsequent settlement agreement (Docket No. 1). On September 29, 2018, the court denied plaintiff's motion for summary judgment (Docket No. 90). At the time, it pointed out that a Memorandum and Order would follow.
Summary judgment is appropriate when "the pleadings, depositions, answers to interrogatories and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(c). A factual dispute is "genuine" if it could be resolved in favor of either party.
All reasonable factual inferences must be drawn in favor of the party against whom summary judgment is sought.
Travelers Casualty and Surety Company is organized under to the laws of the State of Connecticut, with principal place of business in that State.
On January 23, 2010, Travelers executed a General Agreement of Indemnity ("GAI") with Constructores del Este, S.E., pursuant to which the latter assigned to Travelers all rights, title and interest in all contracts bonded by Travelers, including its rights to any and all sums due or which may become due under all bonded contracts to the extent of losses incurred by Travelers as surety of Constructores del Este.
At some point, the Municipality entered into a contract with Constructores del Este for construction in a project known as "Remodelación de los Salones de Tutoría del Colegio Universitario" (the "Salones Project").
On September 11, 2015, the Municipality entered into a contract with Constructores del Este as general contractor for construction of a project known as Remodelación Plaza Barceló (the "Plaza Barceló Project").
First, the parties acknowledged: (1) the agreement between Constructores del Este and the Municipality for the Plaza Barceló Project; (2) the Performance Bond Travelers had issued naming both Constructores del Este and the Municipality; (3) the default the Municipality declared alleging that Constructores del Este: (i) had failed to perform the work in accordance with the project agreement, (ii) failed to adhere to the schedule, and (iii) abandoned the Project; and, (4) that under the GAI, Travelers had been assigned all rights, title and interests, sums due and accounts receivable under any contract.
Second, the parties agreed as to the accounting of Contract Funds balances pertaining to the Plaza Barceló Project, which included the amounts to be credited and paid to each party under the terms of the Settlement Agreement,
Third, the Municipality determined that the best interest of the government was served by immediately entering into a direct contract with an unidentified completion contractor to expeditiously complete the project. Travelers accepted the Municipality's determination to complete the project, and, except for the net amount of $300,000.00 to be paid by the Municipality, released and relinquished in favor of the Municipality any right, titled and interest over the remaining contract funds to be used by the Municipality to complete the Project.
Fourth, in connection with payment, the parties agreed that:
Count I of the complaint alleges the Municipality breached the Settlement Agreement (Docket No. 1 at ¶¶ 15-20) and, accordingly that Travelers is entitled to payment of the $300,000.00 corresponding to the Net Amount to be Paid to the Surety after the accounting contemplated in the agreement. Count II, in turn, asserts violation of the Municipality's obligation to release a "retainage" upon completion of the Salones Project in the amount of $38,656.04.
To prevail and recover on a breach-of-contract claim in Puerto Rico, a party must prove: (i) a valid contract; (ii) a breach of that contract; and (iii) resulting damages.
The Municipality does not question the $36,907.23 owed and not paid for the retainage under the Salones Project, and concedes that it has not paid the $300,000.00 due under the Settlement Agreement. Instead, it alleges the Settlement Agreement is void because to be valid, municipal contracts in Puerto Rico must include a budget account identifying the source of payment, that is, "from where the money is to be paid," and in its view, the Settlement Agreement does not satisfy this requirement (Docket No. 72, pp. 2-3).
Careful review of the Settlement Agreement confirms that all payments and credits referred to therein are from the monies the Municipality set aside in the Plaza Barceló construction contract, to pay for that Project. In particular, Section 2 provides that the parties agreed on an "... accounting of the Contract funds balances, to be credited and to be paid under the terms of this Agreement..."
Invoking rebus sic stantibus, the Municipality asks the court to modify or reduce the payment obligation under the Settlement Agreement (Docket No. 72, pp. 4-12). To this end, it basically claims to have been deprived of GDB funds for the Barceló Project, which prevented it from making the required payment and made the Project Barceló's contract —and the subsequent Settlement Agreement— unjust, oppressive and impossible to comply with.
Broadly stated, rebus sic stantibus is a mechanism that serves to adjust or set aside a debtor's contractual obligations "when unforeseeable circumstances render strict compliance with the contract unfair."
In this light, the Municipality alleges that rebus sic stantibus should be applied because: (1) the GDB was supposed to provide financing for the project; (2) the Municipality lacked control over the sudden discontinuance of GDB-fund disbursements and has no other accounts or budget available to meet this obligation; (3) that situation, coming out of the GDB's financial crisis and restructuring process, was unforeseen; (4) the agreement is not aleatory; (5) no fraudulent acts were committed; (6) the contract for the Plaza Barceló Project was not one of immediate completion; and (7) the Municipality as interested party is petitioning the court to apply rebus sic stantibus (Docket No. 72, pp. 7-12). The court is not persuaded by the Municipality's reasoning.
The contract requiring payment was entered into in September 2016, approximately four months after in May 2016, the GDB defaulted on payments to its bondholders.
Travelers seeks the imposition of attorney's fees against the Municipality because of what it has characterized as the Municipality's obstinacy under Rule 44.1(d) of Puerto Rico's Rules of Civil Procedure, which requires that attorney's fees be imposed on a party that "has acted obstinately or frivolously." P.R. Laws Ann. tit. 32, App. III, R. 44.1(d) (Docket No. 63 at pp. 8-19). Furthermore, Travelers requests imposition of economic sanctions against the Municipality's initial record counsel pursuant to 28 U.S.C. § 1927, which provides that "any attorney or other person admitted to conduct cases in [this court] who so multiplies the proceedings in any case unreasonably and vexatiously may be required by the court to satisfy personally the excess costs, expenses, and attorneys' fees reasonably incurred because of such conduct" (Docket No. 63, pp. 19-23; Docket No. 89). Neither the Municipality nor its record counsel addressed these requests.
Careful review of Travelers' arguments shows that the Municipality's actions did not promote pre-suit resolution of the issues as the court would have expected and did not follow the most appropriate post-suit approach toward disposition. They were close to the line demarcating sanctionable from non-sanctionable behavior under Rule 44.1(d) and Section 1927. Travelers's asserted frustration and requests for sanctions and fees are thus understandable. Nevertheless, the court will not grant the requests. While Travelers properly laid out the facts which in its view support the requests and cited to cases related to various propositions included in its argument, it did not refer to, or discuss, cases where, in light of analogous facts and circumstances, sanctions and fees were imposed under Rule 44.1(d) and Section 1927, specifically linking the corresponding court's ruling under those provisions to the facts and circumstances underlying the ruling.
For the reasons stated, Travelers' motion for summary judgment (Docket No. 63) is GRANTED IN PART and DENIED IN PART. Judgment shall be entered accordingly.