CHARLES L. NAIL, JR., Bankruptcy Judge.
The matter before the Court is the allowance of Defendant Scott Olson Digging, Inc.'s claim. This is a core proceeding pursuant to 28 U.S.C. § 157(b)(2)(B). The Court enters these findings and conclusions pursuant to Fed.R.Bankr.P. 7052. As discussed below, the Court concludes Defendant Scott Olson Digging, Inc. holds a secured claim for $205,104.07 against the bankruptcy estate of Debtor-Defendant Northern Beef Packers Limited Partnership, plus applicable interest to the petition
Northern Beef Packers Limited Partnership ("Debtor") filed a chapter 11 petition in bankruptcy. Debtor is not reorganizing. Most of Debtor's assets were sold at auction. Limited funds remain to pay claims.
Two of Debtor's secured creditors, SDIF Limited Partnership 6 and SDIF Limited Partnership 9, initiated this adversary proceeding, asking the Court to determine several claims and sort out the priority of various parties' liens and other encumbrances against Debtor's assets (doc. 1). The final major issue to be resolved in the adversary proceeding is the amount of the claim held by Defendant Scott Olson Digging, Inc. ("SOD").
SOD provided various earth-moving related services to Debtor as construction of Debtor's beef processing plant began. Dennis Hellwig, one of Debtor's founders and organizers, and Scott Olson, the president of SOD, executed four written contracts, one each on October 20, 2006,
Though the record is not clear, it appears in the first several months of their relationship, SOD did not produce and Debtor did not require invoices that were tied to a particular written or oral agreement, and Debtor made rounded payments to SOD that did not necessarily match specific sums set forth in particular invoices. Later, Donald B. Ulmer, who served Debtor as a project engineer beginning in June 2007, kept a closer eye on Debtor's payments to SOD. Debtor's payments to SOD totaled $3,109,771.89 by the end of October 2007. The record does not reflect which particular invoices Debtor paid. Debtor has not made any more payments to SOD since October 2007.
Representatives for Debtor and SOD conferred in late 2007 and early 2008, attempting to reconcile accounts. SOD produced several invoices dated around the time of their meetings. An accord was not reached. SOD filed a mechanic's lien on March 27, 2008, and Debtor and an affiliate started a state court action against SOD in 2008. The matter remained unresolved for a handful of years, carrying into Debtor's 2013 chapter 11 bankruptcy case, Bankr. No. 13-10118 (D.S.D.), and this adversary proceeding.
In Debtor's bankruptcy case, SOD filed a proof of claim for $3,311,417.00 (proof of claim 69-1). SOD stated its claim was comprised of $2,114,975.49 principal as of November 29, 2007 and $1,196,441.64 statutory pre-petition interest. SOD further indicated its claim was fully secured by the mechanic's lien on Debtor's real property. In addition to the interest, SOD also stated in its claim that it was entitled, under S.D.C.L. §§ 44-9-40, 44-9-41, and 44-9-2, to other costs, including attorney fees, but said it had not yet determined what those additional costs were.
As supporting documentation for its proof of claim, SOD attached its Answer and Counterclaim from the state court action. Attached to the state court pleadings was a Bill of Particulars, and attached to the Bill of Particulars was SOD's Mechanic's Lien Statement and 42 invoices. The invoices totaled $5,096,228.26. The Court was unable to find anything in the proof of claim or the several attachments that distinguished paid invoices from unpaid invoices or otherwise itemized SOD's principal claim of $2,114,975.49. Though no party filed an objection to SOD's proof of claim, challenges to SOD's claim were raised through the adversary proceeding.
Through various motions and defaults in the adversary proceeding, and consistent with SOD's counterclaim and cross-claim (doc. 38), it has been determined SOD's secured claim, once the claim is liquidated, has priority over the mortgages held by
In its cross-claim against SOD, Debtor said SOD is not owed any more for its work and has actually been overpaid "by nearly $100,000.00" (doc. 53). Debtor asked the Court to disallow SOD's claim and avoid SOD's mechanic's lien to the extent the claim is disallowed. Citing 28 U.S.C. § 2201, Debtor also asked the Court to disallow SOD's mechanic's lien because SOD filed a "false and exaggerated account in support of its mechanic's lien statement[.]" Debtor did not ask that SOD be required to return any overpayment.
In its answer to SOD's cross-claim, Debtor essentially agreed SOD holds a mechanic's lien to the extent SOD has a valid claim and its mechanic's lien has priority over Plaintiffs' and the other defendants' secured claims (doc. 92). Debtor then made numerous, generalized equitable arguments against SOD's claim, and again argued SOD's mechanic's lien should be voided because it was fraudulently claimed.
In its answer to Debtor's cross-claim, SOD reiterated many of its earlier allegations and essentially reminded Debtor that Debtor's counsel, in a letter dated May 18, 2010, had conceded SOD had not been overpaid but instead was actually owed $182,682.00 (doc. 71). As with SOD's proof of claim, the Court was unable to find anything in SOD's various adversary proceeding pleadings or the attachments thereto that itemized SOD's $2,114,975.49 principal claim.
The parties in interest
As with SOD's proof of claim and its pleadings in the adversary proceeding, the parties' stipulated facts did not include an itemization of what comprised SOD's principal claim of $2,114,975.49 as of November 29, 2007. According to Exhibits E and F attached to the stipulated facts, the disputed invoices bear several different dates and total $3,377,848.03, well in excess of SOD's principal claim of $2,114,975.49.
A four-day trial to determine the amount of SOD's claim was held. As noted above, Debtor did not dispute several of SOD's invoices. What remained for the
If a creditor executes and files a proof of claim in compliance with the Federal Rules of Bankruptcy Procedure,
The parties do not dispute SOD's claim arises from South Dakota law. In South Dakota, a contract, oral or written, is formed when the four essential elements exist: (1) the parties are capable of contracting; (2) they consent to the subject of the contract; (3) the object of the contract is lawful; and (4) there is sufficient cause or consideration. S.D.C.L. § 53-1-2.
If a contract does not specify the amount of consideration or how it is to be determined, "the consideration must be so much money as the object of the contract is reasonably worth." S.D.C.L. § 53-6-11.
Schmidt v. Clark County, 65 S.D. 101, 271 N.W. 667, 669 (1937) (citing 28 R.C.L. 668).
Once a contract has formed, whether written or oral, the Court's job, when interpreting it, is to give effect to the parties' mutual intent by considering the entire contract. Mueller v. Cedar Shore Resort, Inc., 643 N.W.2d 56, 70 (S.D.2002); Chord v. Pacer Corp., 326 N.W.2d 224, 225-26 (S.D.1982). Only if a contract is ambiguous does the Court consider parol and extrinsic evidence to provide clarification. Hanks v. Corson County Bd. of County Com'rs, 727 N.W.2d 296, 301 (S.D. 2007).
Ducheneaux v. Miller, 488 N.W.2d 902, 909 (S.D.1992) (quoting therein 17A Am. Jur. 2d Contracts § 338) (quoted in LaMore Restaurant Group, LLC v. Akers, 748 N.W.2d 756, 765 (S.D.2008)). Whether the language of a contract is ambiguous is a question of law. LaMore Restaurant Group, 748 N.W.2d at 765. If a contract is ambiguous, it is interpreted and construed against the scrivener, which here is SOD. Advanced Recycling Systems, LLC v. Southeast Properties Ltd. Partnership, 787 N.W.2d 778, 785 (S.D.2010).
If an express contract does not exist, the doctrine of quantum meruit implies one and awards restitution for the value of the services provided under the implied contract. Johnson v. Larson, 779 N.W.2d 412, 417 (S.D.2010); S.D.C.L. § 53-1-3 (distinguishing between express and implied contracts). In determining whether an implied contract exists, the Court objectively views the conduct of the parties, their language, their acts, and other pertinent circumstances attendant to the transaction. Cowan v. Mervin Mewes, Inc., 546 N.W.2d 104, 108 (S.D.1996) (quoting therein Lien v. McGladrey & Pullen, 509 N.W.2d 421, 423-24 (S.D.1993)). To recover under quantum meruit, the party performing the work must prove the other party requested it to perform the work and the party performing the work expected reasonable compensation for that work. Lindquist Ford, Inc. v. Middleton Motors, Inc., 557 F.3d 469, 477-78 (7th Cir.2009), cited in Johnson, 779 N.W.2d at 417-18. The party performing the work may recover even if the work conferred no benefit. Lindquist Ford, 557 F.3d at 477-78; Johnson, 779 N.W.2d at 417-18.
The doctrine of unjust enrichment is similar but distinct. To recover under this equitable doctrine, the party performing
In South Dakota, a mechanic's lien on property is created by statute when someone furnishes skill, labor, services, equipment, or materials for the improvement or development of that property, including the grading, filling in, or excavating of the property. S.D.C.L. § 44-9-1(1). An express or implied contract must underpin the lien. Randall Stanley Architects, Inc. v. All Saints Community Corp., 555 N.W.2d 802, 804-05 (S.D.1996). The mechanic's lien does not substitute for the mechanic's claim but provides security for it. Lytle v. Morgan, 270 N.W.2d 359, 361 (S.D.1978).
The extent of the lien is determined by S.D.C.L. § 44-9-6.
Thus, a mechanic's lien is created for the contract price plus the cost of any additional material and work agreed upon. To the extent a contract — written or oral — did not include an agreed price or to the extent the party asserting the mechanic's lien made a contribution other than by contract, that party has the burden under state law to establish the reasonable value of its work or the material or machinery furnished under the second provision of § 44-9-6. Action Mechanical, Inc. v. Deadwood Historic Preservation Com'n, 652 N.W.2d 742, 754 (S.D.2002).
Burden of Proof. As discussed above, by application of federal bankruptcy law, SOD is presumed to have met its initial burden of proof upon its filing of a proper proof of claim. 11 U.S.C. § 502(a); Fed. R.Bankr.P. 3001(f); Be-Mac Transport Co., 83 F.3d at 1025-26. Debtor did not challenge the efficacy of SOD's proof of claim, only its accuracy or truthfulness. Accordingly, at trial. Debtor had to come forward with substantial evidence rebutting the initial presumption of the validity and amount of SOD's mechanic's lien. Debtor did so.
As noted above, nothing in SOD's proof of claim or the parties' pre-trial stipulation set forth how SOD's principal claim of $2,114,975.49 had been calculated, tied the four written contracts to particular invoices, or clarified what other express or implied contracts existed and then tied those express or implied contracts to particular invoices. It was even unclear whether the 42 invoices attached to SOD's proof of claim were all the invoices SOD had ever submitted to Debtor. Thus, as the trial opened, there was little in the record supporting SOD's claim as filed. Resultantly, the evidentiary knoll Debtor needed to level, to return the burden of persuasion to SOD, was low.
Debtor met its burden through the direct examination of Ulmer and the cross-examination
Disputed invoices regarding excavation.
Much of SOD's evidentiary presentation focused on its theory that the amount of clay it excavated should be calculated based on the number of truck loads SOD hauled from the borrow sites rather than on calculations from before and after surveys of either the borrow pits or the building site or based on the quantity of material for which SOD paid the borrow site owners. No reliable testimony or other evidence indicated SOD and Debtor ever agreed Debtor would pay SOD for clay fill based on a truck count method. There was no corroborating documentation for Olson's testimony that this was their agreement. There was no evidence a truck count method of measuring is common in the industry for a large project like Debtor's. Also problematic was the fact that written contracts 1 and 3 called for specific amounts of excavation at specific sums, not estimates, though both parties seemed to overlook this contract language. Further, while all the relevant testimony indicated the building plans were changed a few times to raise the finished elevation, including a significant addition following major flooding in the spring of 2007, little credible evidence established what the terms of SOD and Debtor's agreements were related to the additional excavation, as to either the amount of fill to be provided or the cost. Therefore, based on the entire record presented, the Court may only conclude written contract 2 covered the extra fill placed in late 2006 and early 2007 and that it was modified or supplemented again in the spring of 2007 by executed oral agreements, as required by S.D.C.L. § 53-8-7, to cover the extra fill needed to raise the project elevation after the major spring flooding. What remains to be determined is whether SOD's five invoices reflect the parties' modified agreements and whether the compensation sought is reasonable. Registered land surveyor Randy D. Bacon calculated a total of 309,513 cubic yards of fill were placed on site, based on before and after surveys of the building site. His figure did not distinguish between the types of fill and may not have accounted for the topsoil that was removed before the fill was placed.
Civil engineer and registered land surveyor Derek McTighe calculated 495,988 cubic yards of compacted fill were placed on site by SOD based on before and after surveys of the building site; he rounded
Civil engineer and registered land surveyor Randall V. Hoscheid calculated, based on surveys of the borrow pits owned by the Young family and Dean Rogers,
Another available computation was the amount of excavation SOD reported to the borrow pit owners when it paid them. Based on these figures, SOD excavated 314,429 cubic yards of fill from the Braun, the Young family, and the Rogers properties.
In its post-trial brief, SOD argued McTighe's at-trial calculation of 650,000 cubic yards should be accepted. SOD argued this figure was an accurate reflection of both its own "truck count" method and the "as-built" survey by Helms & Associates.
For three reasons, the Court finds the most reliable figure to be the calculation of yardage based on SOD's actual payments to the Young family and Rogers and the agreed yardage from the Braun pit.
One caveat to the Court's conclusion is neither party's calculations regarding the clay fill were reconciled with the total fill of 365,000 cubic yards set forth in written contracts 1 and 3, which were both signed well before the elevation was raised again in the spring of 2007. However, when the record is considered as a whole, it appears both Debtor and SOD operated with the understanding the amount of fill in these two contracts included sand, gravel, and other materials — not just clay — and the stated amounts were no longer, if ever, "fixed" but only estimates. Further, with the exception of invoice 1243 for apparent additional fill from the Braun pit,
Finally, the record only yielded one figure for the amount Debtor was to pay SOD for the clay fill: $4.50 per cubic yard. This figure was reflected in written contracts 1 and 3, and Debtor never seriously challenged the $4.50 as being unreasonable in light of the work actually performed or industry standards. Thus, the Court concludes Debtor is obligated to pay SOD, under invoices 1137a, 1141, 1142, 1189, and 1221, for 314,429 cubic yards of clay fill at $4.50 per yard for a total cost of $1,414,930.50.
Disputed invoices 1137b and 1142a regarding stripping of topsoil. That SOD removed topsoil from at least the building site and that it is entitled to payment from Debtor for that work is undisputed. What is disputed is whether the removal of topsoil was covered by written contract 1, how much topsoil was actually removed or should have been removed, and what is the compensation to which SOD is entitled.
Disputed invoice 1137b is for $74,571.56, including excise tax. On it, SOD described its work as "Black Dirt stripped — Main
Based on the language used in written contract 1, the Court concludes removal of topsoil was not covered thereunder. "Topsoil" is not referenced in the document's ten items of work to be completed. The contract terms are not ambiguous. Further, neither party offered any evidence a particular descriptive term used in the contract specifically included or excluded the removal of topsoil based on industry-wide usage of that term. Debtor's argument that the invoices were not received by Debtor contemporaneous with their dates is well taken, but neither party presented any reliable evidence regarding when SOD presented a particular invoice or when Debtor actually received it. And it certainly would have made sense that removal of topsoil be in a separate contract that preceded written contract 1 or that removal of topsoil be a separate line item in written contract 1, as Breukelman testified, but neither happened. Accordingly, based on the record presented, the Court finds written contract 1 did not include the removal of topsoil.
The record also did not establish the particular terms of an oral contract the parties made for the removal of the topsoil. The parties' witnesses offered discrepant testimony on who authorized what and when. The record only showed Debtor and SOD had an understanding SOD would remove topsoil for Debtor in preparation for construction of the packing plant buildings and related work areas and parking lots. Thus, the Court must determine a reasonable compensation for the work performed under quantum meruit, as discussed above.
SOD contended it removed an average of two feet of topsoil from the entire work site; Debtor contended only six to seven inches was — or needed to be — removed from the approximately 19 acres where construction actually took place. Aerial photographs that were offered were skewed by prior flooding, and who took the photos and when were never clearly discussed. The aerial photographs, as well as the various maps and drawings offered, and the testimony about them never produced a definitive answer concerning what areas were stripped and how deep.
Based on the record before it, the Court finds SOD is entitled to compensation for removing 12 inches of topsoil from 19 acres for a total of 30,653
As to the cost of removal, Debtor did not challenge the $2.50 per cubic yard set forth by SOD on its invoices as unreasonable or outside the industry norm. The charge is, therefore, accepted by the Court as reasonable, and the claim allowance under invoices 1137b and 1142a is $76,632.50.
Disputed invoice regarding flooding abatement. Disputed invoice 1226 is for $35,714.35, including excise tax. On it, SOD described its work as "Blade, level, pump water, and keep subcontractors going in out of project." The date or dates of service are not included. A "1" was listed in the "Quantity" column, and the unit price is "35,000.00." The Item Code is "lump sum." The invoice is dated December 10, 2007 and has a "Ship" date of December 10, 2007. The "P.O. Number" section is blank.
Based on Barse's testimony and when comparing the date of and the services listed on disputed invoice 1226 to undisputed invoice 1211, the Court finds the services rendered on invoice 1226 are duplicative of those on invoice 1211. SOD offered no supporting documentation for invoice 1226 but only claimed, through Olson's testimony, these charges related to prolonged rain in October 2007. Twenty-five dates in October, however, are already covered in invoice 1211. Accordingly, SOD is allowed nothing under invoice 1226.
Disputed invoice regarding 2007 mobilization. On invoice 1228, SOD described its work as "2007 Spring Mobilization" for $75,000.00, plus excise tax. The invoice is dated December 10, 2007 and has a "Ship" date of December 10, 2007. The "P.O. Number" section is blank.
While Olson testified he negotiated this payment with Hellwig when SOD began working again at the plant site in the spring of 2007, Hellwig flatly denied asking SOD to return to the work site. Hellwig's testimony was more credible, and Olson had no supporting evidence of an agreement with Debtor for the mobilization reimbursement. Olson also acknowledged SOD first returned to the site only to pump flood water; agreements for SOD to do more earth moving followed thereafter. Further, the invoice was not generated by SOD contemporaneous with the "work" performed. Finally, SOD did not establish Debtor benefited from the "work" performed. Accordingly, SOD's allowed
Disputed invoice 1231. This invoice is for $3,571.44, including excise tax. On it, SOD described its work as "Haul rock and sand around project." The invoice is dated December 10, 2007 and has a "Ship" date of December 10, 2007. The "P.O. Number" section is blank. The dates of service are not set forth on the invoice.
Olson testified he talked to Hellwig about this work. He did not state the dates the work was done or state what consideration was agreed to; he only testified at trial that, "[w]e hauled rock around to the other part, the other side of the basement, and other places on the — on the site, or if it was muddy or if they needed it by the basement or something." His testimony during an earlier deposition was more limited; at that time he could not remember what he and Hellwig had discussed, and he stated the $4.25 per cubic yard charge may have just been what he thought the work was worth.
Without more reliable evidence, the Court cannot conclude an express or implied contract was reached. Moreover, SOD did not demonstrate Debtor was unjustly enriched. Accordingly, SOD's allowed claim will not include payment for invoice 1231.
Disputed invoices regarding black dirt. Disputed invoice 1232 is for $14,285.74, including excise tax. On it, SOD described its work as "Blade Black dirt in front of project site." The invoice is dated December 10, 2007 and has a "Ship" date of December 10, 2007. The "P.O. Number" section is blank.
Hellwig initially testified Debtor accepted this invoice. Other witnesses, in particular Barse and Breukelman, pointed out the work itemized on invoice 1232 was already covered by undisputed invoice 1175. Barse testified the deal he had negotiated between SOD and Debtor encompassed both moving a pile of black dirt, putting it "north of the parking lot" in the lower area, and leveling it out for $2.50 per cubic yard, which is reflected on invoice 1175. His testimony was more definitive and credible than Olson's testimony about making a deal with Hellwig for the work in front of Debtor's lot that is reflected in invoice 1232. Accordingly, payment for invoice 1232 is not included in SOD's allowed claim.
Disputed invoice 1235 is for $10,612.26, including excise tax. On it, SOD described its work as "2,500 Cu. yds. Black Dirt put on site." The quantity is listed as "2,500" and the unit price is listed as "4.00." The invoice is dated December 11, 2007 and has a "Ship" date of December 11, 2007, but when the service was performed is not stated. The "P.O. Number" section is blank. The "Item Code" is "Dirt."
The record on invoice 1235 was very limited. Hellwig and Barse testified they were not aware of the work listed on this invoice. Breukelman testified that $4.00 per cubic yard to move black dirt from one place to another and level it was not a reasonable charge. He too did not have a specific recollection of the invoice or any agreement with SOD to do this work. Ulmer testified he did not authorize the payment of this invoice on Debtor's behalf because there was "nothing here that justifies that payment." Olson testified the black dirt referenced in invoice 1235 was "put on behind the curve around where Red [Wilk, the road builder] worked." Olson said he made the deal for it with Hellwig.
For three reasons, SOD's allowed claim will not include payment of invoice 1235.
Disputed invoice regarding the screening of sand. Invoice 1233 is for $87,857.30, including excise tax. On it, SOD described its work as "41,000 tons of screening sand." The invoice is dated December 10, 2007 and has a "Ship" date of December 10, 2007. The "P.O. Number" section is blank, and the Item Code is "Misc." The quantity listed is "41,000" and the unit price listed is "2.10." The date the work was performed is not listed.
Barse credibly testified he negotiated, between Olson and Breukelman, for SOD to screen the sand for $1.00 per ton. While Olson cursorily testified he negotiated a higher rate with Hellwig, he had no supporting documentation to aid his self-serving testimony. Accordingly, the Court finds SOD is entitled to payment of $41,000.00 under invoice 1233 for screening sand.
Disputed invoice 1234. This invoice is for $179,935.78, including excise tax. On it, SOD described two claims. The first was for "Cu. yrd. Dirt-Place, level and pack out of rendering" for $37,825.00. SOD listed this quantity as "8,900" and the unit price as "4.25." The second was for "Cu. yrd. Dirt-Place, level and pack out of basement" for $138,511.75. SOD listed this quantity as "32,591" and the unit price as "4.25." The "Item Code" for each claim was "Dirt." The invoice is dated December 10, 2007 and has a "Ship" date of December 10, 2007. The "P.O. Number" is blank. The date or dates these services were performed are not on the invoice.
As testified to by Barse, invoice 1234 is duplicative of undisputed invoices 1176 and 1177. Olson said they represented separate work. Barse's testimony was more credible, especially where SOD had no supportive evidence for Olson's testimony and where SOD did not establish the December 2007 date on invoice 1234 was somewhat contemporaneous with when the particular services would have been performed by SOD. Accordingly, SOD's allowed claim will not include payment for invoice 1234.
Disputed invoice regarding excise tax. SOD produced an unnumbered invoice to get reimbursed for some excise tax that it paid the state but that Debtor owed (SOD Exhibit 32).
Total allowed claim. The undisputed invoices identified by the parties before trial totaled $1,718,380.23. Debtor conceded post-trial to the inclusion of $32,653.12 from previously disputed invoice 1227, resulting in an undisputed total of $1,751,033.35. Based on this decision, that sum is increased by $1,532,563.00, plus a 2.041 % excise tax of $31,279.61,
The Court further concludes SOD's claim remains secured by its pre-petition mechanic's lien. The record was insufficient for the Court to find SOD intentionally and willfully filed a false or exaggerated claim. See R & L Supply, Ltd. v. Evangelical Lutheran Good Samaritan Society, 462 N.W.2d 515, 518-19 (S.D.1990). The record only shows Debtor and SOD's loose working agreements, Debtor's indistinct chain of command, and Debtor's changing construction requirements resulted in less than ideal bookkeeping on both sides.
As part of its proof of claim and as argued in its closing brief in this adversary proceeding, SOD wants pre-petition attorney fees under S.D.C.L. § 44-9-42 and postpetition costs on its fully secured claim under 11 U.S.C. § 506(b).
So the matter may be fully and fairly presented, SOD may, in Debtor's main bankruptcy case, file and give notice of an application for its request for attorney fees under § 44-9-42 and, separately but in the same application, its request for post-petition costs under § 506(b). See Bankr. D.S.D. R.2016-3. The Court will cross-docket the application on the claims register as a supplement to SOD's proof of claim and resolve any timely filed objections. Any allowances under the application will be added to SOD's allowed secured claim of $205,104.07 plus the pre-petition statutory interest the parties will calculate.
In a chapter 11 case a § 506(b) allowance is generally calculated to the effective date of a plan. See, e.g., 11 U.S.C. §§ 506(b) and 1129(b)(2)(A)(I) and In re DeQueen General Hosp., 418 B.R. 289, 295-96 (Bankr.W.D.Ark.2009). However, there will be no plan in this case, and the Court has heard loud whispers Debtor may soon seek voluntarily conversion to chapter 7. Thus, Unless SOD can establish law in this circuit to the contrary, SOD's request under § 506(b) should be calculated to the date of the trial on its claim in this adversary proceeding.
SOD and Debtor shall confer to calculate pre-petition statutory interest on SOD's allowed principal claim of $205,104.07. After SOD has filed and given notice of an application as discussed above, the Court will consider SOD's entitlement to pre-petition attorney fees under S.D.C.L. § 44-9-42 and post-petition costs, including post-petition interest and attorney fees, under 11 U.S.C. § 506(b). Once those figures are known, an order will be entered establishing the amount of SOD's secured claim. The order will then be
This agreement is between Northern Beef Packers, Inc. and Scott Olson Digging, Inc. Scott Olson Digging, Inc. will perform the following work:
This agreement is between Northern Beef Packers, Inc. and Scott Olson Digging, Inc. Scott Olson Digging, Inc. will perform the following work:
This agreement is between Northern Beef Packers, Inc. and Scott Olson Digging, Inc. Scott Olson Digging, Inc. will perform the following work:
This agreement is between Northern Beef Packers, Inc. and Scott Olson Digging, Inc. Scott Olson Digging, Inc. [is] to perform the following work:
There is a handwritten note beside the line that references "South Dakota base course." The note says "Lay in place[.]" The handwritten note does not appear to be initialed by either party.
If SOD's payment to Braun is calculated based on 9,606 cubic yards, SOD's check to Braun should have been for $5,763.60 — exactly $10,000.00 less than what is reflected on SOD Exhibit 40. Because there has been no explanation in the record for the extra $10,000.00, the Court's calculation reflects only the agreed 9,606 cubic yards from the Braun pit at SOD's agreed price of $5,763.60. SOD's $10,000.00 payment to Braun on November 30, 2006, and Debtor's apparent agreement to reimburse SOD for it, remains a mystery.
Young also testified Debtor paid him and his family another $35,000.00 — half of an apparent agreed $70,000.00 — in part for fill and in part for an unspecified "contract change." However, neither SOD nor Debtor elicited testimony from Young or produced an exhibit that established what portion of this side agreement was for actual fill SOD removed from the borrow pits or piles and placed on site. Young only stated.
Thus, the record was insufficient to allow the Court to factor this additional payment into its calculation of total clay fill based on what the borrow pit owners were paid.