VERONICA L. DUFFY, Magistrate Judge.
This is a Miller Act action (40 U.S.C. § 3133(b)(3)(B)), brought by the United States of America for the use and benefit of Ash Equipment Company, Inc., doing business as American Hydro ("Hydro"). Defendants are Morris, Inc. ("Morris), United Fire and Casualty Company ("UF&CC), and Red Wilk Construction, Inc. (Red Wilk). Pending before the court is a motion filed by Hydro to compel Morris to provide certain discovery.
Defendant Morris contracted with the United States Army Corps of Engineers ("the Corps") to do work on the Fort Randall Dam spillway at Pickstown, South Dakota. Morris obtained a Miller Act payment bond on the project from defendant UF&CC in the amount of $7,472,670.25. The payment bond obligated Morris and UF&CC jointly and severally to guarantee payment to any subcontractor of Morris' who furnished labor and materials on the project as well as to persons who had a direct contractual relationship with Morris on the project.
Part of the project required concrete removal using hydrodemolition methods as required by the Corps in its project plans and specifications. Morris subcontracted this work to Red Wilk, who in turn subcontracted with Hydro. Red Wilk promised to pay Hydro for Hydro's work on the project within 10 working days after Morris paid Red Wilk on monthly progress payments. Hydro brought suit after Red Wilk allegedly failed to pay for certain claims made by Hydro for completed work on the project. Hydro gave notice to Morris that it had not been paid. Hydro's first notice to Morris claims amounts unpaid of $520,135.00; its supplemental notice claimed unpaid amounts of $1,168,018.49. In its complaint, Hydro asserts a breach of contract claim against Red Wilk, an equitable claim in quantum meruit against Morris, and claim against the UF&CC bond.
Morris responded to this lawsuit by filing a crossclaim for indemnity against Red Wilk, asserting that Red Wilk must indemnify Morris for any monies Morris must pay to Hydro. Red Wilk asserted a compulsory counterclaim against Hydro, asserting that the prime contract was part and parcel of the contract between Red Wilk and Hydro. Red Wilk further asserted that Hydro did defective and/or incomplete work pursuant to its contract with Red Wilk.
Hydro served Morris with a number of discovery requests about which disputes arose.
Before a party may make a motion to compel another party to make discovery or disclosure, the movant must certify that they have in good faith conferred or attempted to confer with the opposing party from whom the discovery or disclosure is sought in an attempt to resolve the disagreement without court intervention.
Federal Rule of Civil Procedure 26(b)(1) sets forth the scope of discovery in civil cases pending in federal court:
A party claiming a privilege as to requested discovery has the burden of proving the basis for the application of the privilege:
If a party fails to respond to a proper request for discovery, or if an evasive or incomplete response is made, the party requesting the discovery is entitled to move for a motion compelling disclosure after having made a good faith effort to resolve the dispute by conferring first with the other party.
The scope of discovery under Rule 26(b) is extremely broad.
"Relevancy is to be broadly construed for discovery issues and is not limited to the precise issues set out in the pleadings. Relevancy . . . encompass[es] àny matter that could bear on, or that reasonably could lead to other matter that could bear on, any issue that is or may be in the case.'"
Discoverable information itself need not be admissible at trial; rather, the defining question is whether it is within the scope of discovery.
Rule 34 of the Federal Rules of Civil Procedure governs requests for the production of documents and provides that a party may ask another party to permit copying of documents "in the responding party's possession, custody, or control."
The rule that has developed is that if a party "has the legal right to obtain the document," then the document is within that party's "control" and, thus, subject to production under Rule 34.
Merely because documents gathered by an attorney are subject to the client's control does not, however, automatically mean they are discoverable. The work product doctrine and the attorney-client privilege still apply and may be asserted in opposition to discovery, along with the appropriate privilege log.
After filing the instant motion to compel, Morris provided documents responsive to Hydro's requests for the Jake Russell photos and for the submittals made by Morris to the Corps. Therefore, these two issues are moot.
In its reply, Hydro asks the court to allow further discovery to follow up on the discovery received. This issue is moot as well because the district court recently extended the discovery deadline to September 15, 2016, thus allowing Hydro and the other parties to conduct what remaining discovery is left. The issue of sanctions, if any, is left for another date. The court notes, however, that Hydro itself was the object of a recent successful motion to compel by Morris.
Hydro served Morris with request for production numbers 8 and 44, both of which seek documents relative to concrete testing.
Here, it is necessary to discuss a few more facts of the underlying construction project. The Corps' project required first the hydrodemolition of the existing spillway at the Fort Randall Dam, and then the construction of a new spillway. Hydro was hired in connection with the demolition of the old spillway. Hydro had nothing to do with that part of the contract regarding the construction of the new spillway. However, Morris as the general contractor was involved in both parts of the project.
Morris has not asserted a counterclaim directly against Hydro, only against Red Wilk for indemnity. Red Wilk has asserted a counterclaim against Hydro, but in that counterclaim, it never alleges that Hydro caused the concrete in the new spillway to fail or be defective. Seemingly, then, documents regarding testing of the concrete on the new spillway are irrelevant to the claims, cross-claims and counterclaims asserted by Morris, Red Wilk and Hydro. That is certainly Morris' position.
Hydro asserts, however, that concrete testing is relevant. Hydro states that at the Rule 30(b)(6) deposition of Red Wilk, Red Wilk's designee testified that a dispute has arisen between Red Wilk and Morris over the concrete testing done on the new spillway (presumably constructed by Red Wilk). Hydro points out that Red Wilk has asserted a broad counterclaim against Hydro for damages Red Wilk has suffered due to delays on the project. Hydro posits that if concrete testing is responsible in whole or in part for the delays experienced on the contract, this would be relevant to Red Wilk's counterclaim against Hydro. In essence, Hydro disputes the causation for delays on the project, seeking evidence that something other than Hydro (i.e. concrete testing) has caused or contributed to the delay, which would defeat or reduce Red Wilk's counterclaim damages against Hydro.
This is a somewhat attenuated argument. However, the court is cognizant that it is not familiar with all the details and facts of this construction project like the parties themselves are. Furthermore, the court notes that a parallel discovery dispute was recently filed by Hydro against Red Wilk with one of the contested items being requests by Hydro for concrete testing documents. Red Wilk never asserted that the documents in question were not relevant.
Morris has not asserted that the number of documents or the expense of marshalling them or providing them poses an undue burden. This is significant because discovery is proportional and the less relevant discovery is to the heart of the case, the more the expense or work needed to produce the discovery weighs in the balance. Given the broad scope of discovery under the federal rules, the showing of relevancy Hydro has made, and the absence of a claim of undue burden, the court will grant the discovery.
Good cause appearing, it is hereby
ORDERED that plaintiff's motion to compel against defendant Morris Construction, Inc. [Docket No. 81] is denied in part and granted in part as indicated above. Morris must deliver the concrete testing documents to plaintiff no later than 15 days from the date of this opinion.
Pursuant to 28 U.S.C. § 636(b)(1)(A), any party may seek reconsideration of this order before the district court upon a showing that the order is clearly erroneous or contrary to law. The parties have fourteen (14) days after service of this order to file written objections pursuant to 28 U.S.C. § 636(b)(1)(A), unless an extension of time for good cause is obtained.