ALETA A. TRAUGER, United States District Judge.
The defendant, Ashland Heights, LP ("Ashland"), has filed a Motion to Dismiss (Docket No. 5), to which the plaintiff, Summit Contracting Group, Inc. ("Summit"), has filed a Response (Docket No. 10) and a Supplemental Response (Docket No. 19) in opposition. For the following reasons, the motion will be denied.
This is a construction dispute between a commercial general contractor (Summit) and an owner (Ashland) for the construction of an assisted living facility at 2035 Vantage Pointe, Ashland City, Cheatham County, Tennessee. The court focuses on the well-pleaded allegations in the Complaint. (Docket No. 1.) Summit is a Florida corporation with offices in Florida, but it is authorized to do business in Tennessee and is a fully-licensed Tennessee general contractor. Ashland is a limited liability partnership that owned the land that is the subject of this dispute and wished to construct a senior living facility, known as Vantage Point Village, at that location (the "Project").
On September 16, 2013, Summit and Ashland entered into a construction contract for the Project (the "Contract"). The Contract provided that Summit would be the general contractor for the Project and
Summit began work on the Project in November of 2013. As alleged, Summit's work on the Project was substantially complete, as agreed to in writing by both Ashland and its architect, in May of 2015. On November 25, 2013, Summit submitted its Application for Payment No. 1 in the full amount of $279,062.32, which requested approval and payment of the amount of $265,075.00 ("AFP No. 1"). The difference in the amounts is the 5% Retainage in the amount of $13,951.32. Ashland approved AFP No 1, paid Summit $265,075.00 on December 10, 2013, and withheld 5% as the Retainage called for in the Contract (the "AFP No. 1 Retainage"). Summit alleges, however, that, upon the payment of AFP No. 1, Ashland did not deposit the AFP No. 1 Retainage into an interest bearing escrow account with a third party, as required by Tennessee's Retainage Laws. Summit further alleges that, for each and every subsequent progress payment application submitted by Summit to Ashland, Ashland withheld Retainage but did not deposit the Retainage into an interest bearing escrow account. The total Retainage withheld by Ashland from Summit is alleged to be $320,415.74.
On October 13, 2014, via letter from counsel and pursuant to the Tennessee Retainage Laws, Summit demanded from Ashland details on the third-party Retainage escrow account that Ashland had been required to create and fund. Summit also informed Ashland that, if such escrow account had not been created with the total
Summit alleges that it submitted other applications for payment to Ashland, along with change orders for work properly ordered and performed, for which Summit has allegedly not been paid despite multiple written demands. In addition, Summit alleges that many of Ashland's payments to Summit were not timely, in violation of the Contract, and that Summit is, therefore, entitled to recover interest.
Finally, Summit alleges that it is entitled to recover additional miscellaneous costs and expenses. Summit alleges that the total number of days in which Summit's work was stopped as a result of inclement weather exceeded 30 days and, therefore, Summit is entitled to payment of its extended general conditions. Summit also maintains that it incurred other expenses and costs associated with investigations and actions based on unwarranted claims by Ashland that Summit was the cause of the alarm system installed on the Project having "unwanted alarms."
Summit, therefore, brings a breach of contract claim and a claim under Tennessee's Prompt Pay Act and Retainage Laws. Summit also "contemporaneously filed with the Cheatham County, Tennessee Chancery Court a lawsuit against Ashland in order to timely and properly under Tennessee lien law enforce the mechanic's lien which Summit claims and has filed against the real property of the Project." (Docket No. 1 ¶ 45.) More specifically, on January 11, 2016, at 1:30 p.m., Summit filed a mechanic's lien
Ashland argues that this case should be dismissed, without prejudice, pursuant to the Colorado River abstention doctrine due to the prior pending state court lawsuit. See Colorado River Water Conservation Dist. v. U.S., 424 U.S. 800, 817, 96 S.Ct. 1236, 47 L.Ed.2d 483 (1976). The Supreme Court has explained that, despite the "virtually unflagging obligation of the federal courts to exercise the jurisdiction given them," considerations of judicial economy and federal-state comity may justify abstention in situations involving the contemporaneous, or "parallel," exercise of jurisdiction by state and federal courts. Id. The Sixth Circuit has stressed that the "principles underlying this doctrine `rest on considerations of wise judicial administration, giving regard to conservation of judicial resources and comprehensive disposition of litigation.'" Romine v. Compuserve Corp., 160 F.3d 337, 339 (6th Cir. 1998) (quoting Colorado River, 424 U.S. at 817, 96 S.Ct. 1236); Capitol Wholesale Fence Co. v. Lumber One Wood Preserving, LLC, No. 3:13-cv-00521, 2014 WL 7336236, *2 (M.D.Tenn. Dec. 22, 2014) (same).
The Colorado River analysis is composed of two parts: first, the court must determine that the concurrent state and federal actions are actually parallel; and second, the court must weigh several factors identified by the Supreme Court in Colorado River. Romine, 160 F.3d at 339. "Exact parallelism" is not required; it is enough if the two proceedings are substantially similar. Id. (citing Nakash v. Marciano, 882 F.2d 1411, 1416 (9th Cir.1989)). The Supreme Court has explained that a stay should only be granted where it would allow for a "quick and prompt resolution between the parties," such that the federal court "will have nothing further to do in resolving any substantive part of the case, whether it stays or dismisses." Moses H. Cone Mem'l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 23-26, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983) (emphasis added). For the cases to be considered parallel, "substantially the same parties must be contemporaneously litigating substantially the same issues," and "the critical question is whether there is a substantial likelihood that the state litigation will dispose of all claims presented in the federal case.'" Capitol Wholesale Fence Co., 2014 WL 7336236 at *3 (emphasis added) (quoting Huon v. Johnson & Bell, Ltd., 657 F.3d 641, 646 (7th Cir.2011)). "If there is any substantial doubt that the parallel litigation will be an adequate vehicle for the complete and prompt resolution of the issues before the parties, it would be a serious abuse of discretion for the district court to stay or dismiss a case in deference to the parallel litigation." Chellman-Shelton v. Glenn, 197 Fed.Appx. 392, 394 (6th Cir.2006). In providing further guidance to district courts, the Sixth Circuit has stated that, "in deciding whether a state action is parallel for abstention purposes, the district court must compare the issues in the federal action to the issues actually raised in the state court action." Baskin v. Bath Tp. Bd. of Zoning Appeals, 15 F.3d 569, 572 (6th Cir.1994)) (emphasis added); accord Iron Workers of W. Pa. Pension Plan v. Caremark RX, Inc., No. 3:06-1097, 2007 WL 60927, at *3 (M.D.Tenn. Jan. 5, 2007). Likewise, as an exemplar, in Crawley v. Hamilton County Com'rs, 744 F.2d 28 (6th Cir.1984), the court stressed, among other reasons for declining to apply Colorado River abstention, that there were claims in the federal suit not present in the state suit. Put simply, where there are issues
Ashland contends that "[a]s a threshold matter, the two proceedings are clearly parallel. They involve the same parties litigating identical issues arising out of the same contract. And because the claims in both lawsuits arise out of the same contract and seek the same contractual damages, the success of one lawsuit will necessarily render the second lawsuit moot." (Docket No. 6, p. 4.)
While the Sixth Circuit has never directly considered the question of whether a lien foreclosure action in state court was "clearly parallel" to a separate action in federal court seeking contract damages, two other courts of appeal have.
The court finds this application of the Colorado River doctrine by the Fourth and Eighth Circuits to be sound, particularly when viewed in light of the general guidance on abstention provided by the Sixth Circuit. The Federal Court Contract Action is premised upon (1) the common law elements of breach of contract and (2) Tenn. Code Ann. § 66-34-101 et seq. (Tennessee's Retainage Laws). The State Court Lien Action, on the other hand, is based on Tenn. Code Ann. § 66-11-101 et seq. (Tennessee's mechanic's lien laws). The State Court Lien Action seeks enforcement of a mechanic's lien in the amount of $1,074,668.74, while the Federal Court Contract Action seeks well in excess of that amount in damages generated by, among others, breach of contract, statutory penalties, and attorney's fees. Viewed through the required lens, the State Court Lien Action is based upon only one issue: attachment and the enforcement of the mechanic's lien. The lien amount cannot include "any interest, service charges, late fees, attorney fees, or other amounts to which the lienor may be entitled by contract or law that do not result in an improvement to the real property." Tenn. Code Ann. § 66-11-102(e). The Federal Court Contract Action, on the other hand, is not tied to the lien; it includes damages, inter alia, for breach of contract, statutory penalties, and attorney's fees, some of which are plainly non-recoverable in the other action.
While Ashland may believe that the amount of damages sought by Summit in the two actions overlap, it is clear that the State Court Lien Action raises issues not raised in the Federal Court Contract Action (i.e., Summit could potentially prevail on the lien and have some of its federal court claims remain unresolved). More importantly, it is also clear that the Federal Court Contract Action raises issues that go beyond that contemplated by the more limited State Court Lien Action. Thus, there is substantial doubt that resolution of the State Court Lien Action would result in a complete resolution of the issues between the parties — the critical question under Sixth Circuit guidance. Put more simply, Summit's State Court Lien Action against Ashland does not encompass all claims and amounts pursued from Ashland by Summit in the Federal Court Contract Action. In such a situation, the issues in the two actions cannot be considered parallel and Colorado River abstention is not appropriate.
This case will proceed.
For the foregoing reasons, the defendant's Motion to Dismiss (Docket No. 5) will be denied.
An appropriate Order will enter.